旧路加宽综合处治方案设计的几点考虑(1)

旧路加宽综合处治方案设计的几点考虑(1)
旧路加宽综合处治方案设计的几点考虑(1)

论文作者:孙四平侯芸郭忠印张艳张树山仝运涛

摘要:旧路加宽改造对提高既有道路等级和改善路网结构具有较高的技术经济价值。在旧路加宽改造工程的方案设计时需进行多方案的比选,同时必须综合分析各方案的地基沉降、路基稳定性、路基静载压缩变形、以及路基土行车荷载作用塑性累积变形等造成的路基表面的不均匀变形,以便采取可靠而有效的综合处治方案。

关键词:旧路加宽土工合成材料不均匀变形;

随着国民经济的快速发展,道路交通运量迅猛增长,既有公路、城市道路等旧路加宽加铺改造工程也随着大量的付诸实施。对旧路进行加宽加铺改造时要特别注意:①新旧路基间的不均匀沉降以及新路基的塑性累积变形对路面结构响应的影响,②新旧路基间的刚度差异对路面结构响应的影响,③面层反射裂缝的防治等。为此,在旧路加宽改造工程的实施之前必须进行先期的方案试验研究。通常可采用软弱地基处理、基底清淤换填、旧路路堤台阶开挖、土工合成材料加筋垫层和加筋土路堤、土工织物防渗和排水、改良土高强路堤和轻质路堤、铺设土工合成材料防裂层或增大加铺层厚度等工程技术措施。本文结合大齐(大庆~齐齐哈尔)公路加宽改造工程的实施,提出旧路加宽综合处治方案设计时的几点考虑。

1. 大齐试验路路基加宽方案设计的比选

1.1 大齐试验路的基本概况

大齐公路位于黑龙江省西部松嫩平原301国道中段,属于我国东北冻融交替区,春季干旱风大,夏季短促多雨,秋季低温早霜。大齐路沿线地势平坦,草原、湿地和沼泽约占全线总长的20%。其地质条件主要属于第四纪沉积层,地表土多为粉质中液限黏土和中液限黏土、并间有弱碱性盐渍土的交错分布,其下为圆砾土、砂砾土和粉质黏土。地表排水不良,土壤含水量较大,对路基的稳定性与工程施工均有较大的影响。

1.2 大齐试验路路基加宽方案设计

根据大齐路现有路况、水文地质条件和可用的地方材料,综合考虑各种因素对路基刚度差异、不均匀沉降、侧向滑移和防水防渗的影响。经技术经济分析,分别在单侧和双侧加宽地段各选择了一个试验路段,共设计了7种方案进行试验研究。其中,单侧加宽试验路位于k74+600~k74+900,共3种方案;双侧加宽试验路位于k96+100~k96+400,共4种方案。

1.2.1 基本处治措施

⑴基底清淤与换填

旧路修筑时因就地取土而在路基边坡外侧形成了沿路线走向约1.5m深的积水沟,沟底堆积了大量的淤泥。因此,必须彻底清除边沟内的淤泥以提高路基基底强度,减小由此而造成的新旧路基间的不均匀沉降。边沟清淤后换填天然砂砾,砂砾层顶面需高出常水位20cm以上,并在其上设置3%的横向排水坡以利排水。

⑵台阶开挖与构筑

为增加新旧路基的整体稳定性,在填筑前须先将旧路路基边坡面开挖成台阶状。单侧加宽部分第一级台阶宽350cm,高100cm,其上三级台阶的宽×高均为150cm×100cm。双侧加宽部分均开挖成宽120cm,高分别为120cm、80cm、80cm的三级台阶。

1.2.2 旧路路基单侧加宽方案

方案一(s1):二灰填筑方案,即:基底换填天然砂砾+土工网+天然砂砾+粉质土+土工网+粉质土+二灰。

在路基顶面以下1.0m范围内采用粉煤灰∶熟石灰=0.9∶0.1(质量比)的比例均匀拌和后填筑,以构成轻质路堤。二灰作为轻质路堤填料具有很好的工程性质:其后期强度高、整体稳定性好,能够有效地减小新旧路基间的刚度差;其自重荷载小,能有效地减小路堤因自重荷载作用而产生的压缩变形,对确保路基的容许工后沉降非常有利。

方案二(s2):三层土工网方案,即:基底换填天然砂砾+土工网+天然砂砾+粉质土+土工网+粉质土+土工网+粉质土。

土工合成材料(本试验路用土工网)加筋路堤不仅可以增强新旧路基间的整体稳定性,而且还可以使新加宽路基的强度和刚度得到很大的提高,从而可有效地减小新旧路基间的刚度差异。土工合成材料还具有减小新加宽路基的不均匀沉降和侧向位移的作用,从而使得路基横断面上的沉降趋于均匀。

方案三(s3):两层土工网方案,即:基底换填天然砂砾+土工网+天然砂砾+粉质土+土工网+粉质土。

根据工程实践经验,当路堤填方高度低于4.0m时,在新加宽路基中可只铺设2层土工网。但考虑到行车荷载在新旧路基结合部的局部荷载作用和路基顶部可能产生的滑动对路面的剪切作用,故在s2方案中铺设了3层土工网以进行对比试验。

1.2.3 旧路路基双侧加宽方案

方案一(d1):粉质土填筑方案,即:基底换填天然砂砾+粉质土+不透水土工布+粉质土+不透水土工布。

在粉质土路堤的内部和顶面各铺设一层不透水土工布,可起加筋和隔离防渗的作用。由于不透水土工布的加筋作用可增强新旧路基间的整体稳定性好,减小路基的不均匀沉降;由于不透水土工布的隔离防渗作用,可防止垫层砂砾料的陷入,并能防止雨水浸入对路基的破坏,同时也可在一定的程度上减少路堤自身的压缩变形。

方案二(d2):粉煤灰填筑方案,即:基底换填天然砂砾+粉煤灰+二灰+不透水土工布。

d2方案的地质条件相对较差,采用粉煤灰+二灰的轻质填料填筑路堤,不仅可以降低新路堤自重,减小路堤的压缩变形,而且还可以提高新路堤的强度和刚度,并可减小路基在行车荷载作用下的塑性累积变形。轻质填料路堤同时起到了减小新旧路基间刚度差异和不均匀沉降的作用,从理论分析和工程实践上来看,是旧路加宽方案中较为理想的一种综合处治措施。

方案三(d3):砂砾填筑方案,即:自基底换填至整个路堤全填天然砂砾。

由于天然砂砾的渗水性填料,可以很好地将浸入路堤中的雨水排出,同时天然砂砾也具有很高的强度和刚度,有利于减小新旧路基间的刚度差,并可减小路基在行车荷载作用下的塑性累积变形。但天然砂砾由于自重较大,使得地基和路堤可能在自重荷载作用下产生较大的沉降和压缩变形,从而造成新旧路基间较大的不均匀沉降。

方案四(d4):二灰填筑方案,即:基底换填天然砂砾+粉质土+二灰+不透水土工布。

d4方案的地质条件相对较好,采用粉质土+二灰的半轻质路堤,可使高新路堤的强度和刚度得到部分提高,并能减小一部分路堤的压缩变形和塑性累积变形,可作为与其它加宽处治方案的对比试验。

2. 旧路加宽的地基沉降与路基稳定性分析

在旧路加宽改造中,地基沉降和路基稳定性分析无疑是非常重要的。沉降的处理就是在路基施工过程中加速因新修路基而引起的地基沉降,或者采取有效措施控制路基由于剪切变形而产生的侧向位移,从而减小路基的工后沉降。对于稳定性的处理则必须增大新修路堤及地基的强度,提高其抗剪切变形的能力。

由均质粘性土填筑的路堤的稳定性根据fellenius滑动圆弧法进行分析,路堤坍塌破坏时,其滑动面为一曲面,假定其为圆弧形,圆弧滑动面的位置用4.5h法确定。土工合成材料的加筋作用按在常规的圆弧稳定分析方法中增加一个拉力的办法进行考虑,把加筋力作为水平力施加于滑动土体,来计算其稳定性和确定加筋层数。

在旧路加宽改造工程中,由于新旧路基的固结程度不同,将会导致路基的横向不均匀沉降,从而造成路面的开裂破坏。因此,必须准确掌握加宽路基的最终沉降量及固结度,并验

算其剩余沉降量是否满足工后沉降量的要求。在沉降分析中,可假定旧路路基下的地基已趋于完全固结,采用分层总和法计算新加宽部分路基的地基总沉降量。

3. 旧路加宽的路基土压缩变形分析

路基土在其自重和路面结构等静荷载作用下的变形主要表现为土体的压缩变形,可通过室内试验测定土的相应变形指标,选取适宜的力学模型采用有限元法分析路基土的应力状态,从而得到路基与地基的总变形量、不均匀变形量、不均匀变形范围以及变形与时间的变化关系等控制指标。

在路基土压缩变形的有限元法分析中,将新填筑的路基土视为弹塑性材料,采用邓肯非线性模型。而将旧路路基视为弹性材料,将土工织物视为线弹性材料,按平面应变问题求解。其中,路基和地基采用平面四边形等参单元、土工织物采用接触面单元、路面结构层采用弹性梁单元进行模拟,假定土工织物与土体的界面间无相对位移,采用如此所示的有限元分析模型。

老城区改造施工组织设计

老城区改造施工组 织设计

目录 第一章 总体概述:施工组织总体设想、方案针对性及施工段划分; 第二章 施工现场平面布置和临时设施、临时道路布置; 第三章 施工进度计划和各阶段进度的保证措施; 第四章 各分部分项工程的施工方案及质量保证措施; 第五章 安全文明施工及环境保护措施; 第六章 劳动力、机械设备和材料投入计划;

第一章编制依据、范围及原则、质量方针与目标、安全目标 总体概述:施工组织总体设想、方案针对性及施工段划分 第一节编制依据 1、无锡市梁溪区住房和城乡建设局发布梁溪区(庄前、锡航新村等)旧住宅整治改造项目的市政、环卫工程(五标段)建设项目施工招标文件。 2、国家现行有关市政工程施工及验收规范、规程、标准以及省市对市政工程施工管理的有关规定。 3、现场初步踏勘所了解的有关情况和经过调查所掌握的有关资料信息。 4、其它相关的施工技术规范及质量评定标准。 5、我司的综合施工能力、机械设备装备情况、技术力量和多年参加市政工程施工所具有的丰富施工经验。 6、我公司有关质量、安全、文明施工的规定。

第二节编制范围及原则 一、编制范围 新都区宝光大道南段改造工程建设项目二标段包括的工程内容为: 1、道路工程:路基、沥青砼路面、人行道等。 2、拆除工程:拆除道路基层(水稳、砂砾石)及水泥混凝土路面等。 3、环卫工程:化粪池加高等。 二、编制原则 1、本施工组织设计严格遵循招标文件规定的内容和设计要求,编制的标前施工组织设计。 2、在仔细考察工程实地,认真研究招标文件和有关规定的基础上,充分地分析了本工程施工特点和设计文件,认识本工程组织施工的难度。我单位将根据多年来在市政工程施工中积累的经验,认真做好施工组织方案和交通转换方案,安排好各阶段工序、控制好关键部位工期,采取强有力的有效措施。在施工期间保证交通畅通,以及车辆、行人和生命财产安全,周围建筑物、地下及地上管线的正常使用及安全。 3、我单位将科学合理的组织施工,同时考虑各专业统一规划,同步施工又要避免交叉作业造成相互影响,体现我司强大的施工力量。

路基加宽施工方案1

大兴区兴业立交改造工程 路基土方(五环加宽)分项工程施工方案 一、工程概况 兴业立交位于北京市大兴区南五环李营桥节点处,是大兴黄村地区与市中心区交通换转的重要节点。本工程西起五环路兴旺路出口,东至西红门南桥西侧,南起现况北兴路,北至现况南环路,包含五环路改造、新建Z1匝道、新建Z2匝道、新建1号地方路、改造2号地方路,共计5条道路。 本工程路基填筑主要工程数量:Z1匝道路基填方6200m3、Z2匝道路基填方6500m3、K13+427—K13+792(875)段路基填方14800m3。 二、施工计划 2014年10月15日~2015年04月20日 三、作业人员 工长3人、质检员3人,试验员4人,测量员5人,机械工20人,司机23人,工人40人。 四、施工机具 挖掘机5台,装载机7台,压路机8台,自卸汽车20辆,洒水车3辆。 五、路基填筑 1、填料的选择与试验 路基回填所用的填料为挖方段借用土石方,为碎石渣和碎石土填料,填料按规定要求进行鉴别试验。严格控制路基填料的强度、不符合规定的不能使用,挖方中非合适材料严禁用于回填路基。压路机压实填筑时分层压实厚度不大于20cm。 路基填料最小强度和最大粒径及最小压实度按照以下设计要求控制:

注:①表列数值为重型压实度标准;括号内为地方路CBR值;②新建管线肥槽回填时,须回填道路可用土,并分层回填压实,压实度不小于表列填方要求(重型击实标准),防止路基沉陷。 2、工艺流程 场地清理→测量放线→清表(挖除旧路边坡、清表及填筑前碾压、基底处理)→基底检测→分层填筑(填料选定与检测)→摊平(检查摊铺厚度)→整平→洒水或晾晒→碾压→成型检测验收 3、新旧路基衔接处理 (1)施工前截断流向拓宽作业区水源,开挖临时排水沟,保证施工期间排水通畅; (2)新旧路搭接处的旧路边坡应拆除老路路缘石、旧路肩、边坡防护、边沟等。将旧土路肩翻晒或掺灰处理重新碾压,以达到质量要求; (3)同时清除旧路肩边坡上草皮、树根及腐殖土等杂物,并由硬路肩开始下挖台阶,以消除旧路基边坡压实度不足,加强新旧路基的结合程度,减少旧路基结合处的不均匀沉降; (4)施工时,为保证老路堤与新路堤交界坡面搭接良好,需挖除清理法向厚度不宜小于30cm虚土,然后从老路堤坡脚向上按设计要求挖设50cm宽台阶。挖设断面见后附图“五环加宽新旧路基衔接处理断面图” 当老路堤高度小于2米时,老路堤坡面处理后,可直接填筑新路堤。严禁将边坡清挖物作为新路堤填料。 (5)加宽路堤填料选用与老路堤基本相同的填料作为填料,挡墙路基回填采用砂砾透水性材料回填。路基其它段落加宽部分若采用非透水性填料时,应在地基表面铺设砂砾或碎石垫层。 4、加宽部分路基基底清表(软基处理) (1)开工前,根据设计图纸尺寸放出路基坡脚、边沟位置,并结合施工现场实际情况,修建临时排水工程。同时沿加宽路基宽度外侧50cm左右设定边线,对此范围进行清表,平整压实,基底经监理工程师验收合格再进行回填填筑施工。 (2)首先在施工便道打通之后,推土机、平地机、挖掘机进场把路基填筑范围原地面的树木、草皮、腐殖土等杂料清除原地面,至合格基底。表土清除深度一般为10~30cm,清除的表土杂物堆弃于加宽路基坡脚线与道路红线之间。清表后树根须全部挖除

桥梁加宽改建施工指南(1)

桥梁加宽改建 一、基本要求 1、本内容适用于T梁、空心板及小箱梁桥的加宽改建。 2、收集旧桥的设计、竣工资料和地质资料,对全线原有桥梁构造物进行归类分析和现场调查,进行必要的研究、论证,以选择合理可行的施工方案。 3、桥梁的拼接加宽宜采用与原桥同跨径、同结构型式,力求标准化、装配化、外观一致性。 4、在桥梁加宽改建时,应将拟实施的技术方案与施工期的交通组织统筹考虑,做到技术方案与交通组织方案的协调统一,努力实现“施工过程不中断交通”的目标,将施工期对现有交通的影响程度降到最低。 二、上部构造与下部构造均不连接 1、一般规定 (1)下部盖梁和上部梁板新旧结构间采用在连接处设纵向缝完全分离的形式,如图1.1所示,加宽后新旧结构间各自受力、互不影响。

图1.1 上部构造与下部构造均不连接示意(2)加宽桥与原桥各自受力明确、互不影响,减小连接的施工难度,桥墩基础的沉降差异对上部结构的受力影响小。 (3)汽车荷载作用和基础沉降差异,桥梁新旧结构连接处往往会出现纵向裂缝宽度扩大,新旧结构间有明显的挠度差等病害。由造成桥面沥青混凝土铺装破坏,增加后期养生费用;而且由于新旧结构明显的挠度差影响行车舒适性、使行车安全性受损。 2、施工工艺 上部构造与下部构造均不连接施工工艺流程见图2.1。

图2.1 上部构造与下部构造均不连接施工工艺流程 三、上部构造与下部构造均连接 1、一般规定 (1)为使加宽桥与原桥形成完整的整体,减小各种荷载(包括基础不均匀沉降、汽车活载、温度荷载等)作用下新老桥连接处产生过大的变形,减小上、下结构某些部位的内力,上部结构与下部结构均采用连接,如图1.1所示。 (2)将加宽桥梁的上部结构与原桥对应部位横向通过植筋、浇筑湿接缝等方式连接起来,原桥下部结构的桥墩、桥台帽梁及系梁也通过植筋技术将钢筋和加宽部分新桥相应部位钢筋连接,然后浇筑混凝土,将新老桥梁连为一体。

老旧小区改造项目施工组织设计

徐州市铜山区老旧小区 综合整治工程三标段 施工组织设计方案 江苏省建筑工程集团有限公司 2017年10月1日

施工方案审批表

第一章编制说明 1、编制依据 依据中国建筑标准设计研究院的改造施工图 2、编制原则 严格遵守国家、地方的技术规范、施工规程和质量评定与验收标准;坚持技术先进性、科学合理性、经济适用性与实事求是相结合。 第二章工程概况 1、工程概况简介: 工程名称:徐州市铜山区老旧小区综合整治工程三标段 工程地点:徐州市铜山区 设计单位:苏州立诚建筑设计院有限公司 本工程为了居民停车方便,休闲娱乐方便服务,为小区居民提供更好的生活环境,对小区进行地面、路面、花园、道板砖、外墙涂料、屋面渗水等部分工程设施进行改造。 第三章施工部署 1、项目组织机构及项目管理模式 我们施工组织的指导思想是以质量为中心,立工程质量保证

体系,编制项目质量计划,选配高素质的项目经理及专业工程技术管理人员。积极推广应用新技术、新设备、新工艺。项目部将成为一支充满活力、具有多专业、全面管理能力的领导班子。见项目管理组织机构图: 安全部门主要负责人: 组长—李文(负责协调工作) 副组长—李家彪(技术总部署)

安全员—胡传明(现场施工总指挥) 2、项目管理模式: 本公司将按照多年来积累的成功项目管理经验来运行和管理本项目,形成以项目经理负责制为核心,以项目合同管理和成本、进度、质量控制为主要内容,以科学系统管理和先进技术为手段的项目管理机制。 为规范本项目管理工作,项目部严格执行集团颁发的《质量手册》、《管理制度》,同时现场场区管理严格遵守西安市施工现场标准化管理的有关规定。 2、实施目标 工期目标: 为使本工程早日竣工,为业主提供服务,项目部应在人员组织、施工工艺、材料供应等方面进行精心布置。 确保合格,争创优质工程 现场管理目标: 为保持施工现场周围清洁的环境,我们将设专人打扫清洁等措施,做到物流有序、施工顺畅文明施工。确保现场管理达到文明施工样板现场。 安全目标: 完善安全措施,提高安全意识,杜绝死亡和重伤事故发生,工伤频率控制在2﹪以下。 服务目标: 服务周到、业主满意、重视建议、信守合同,认真协调与有

旧桥拆除专项施工方案

旧桥拆除专项施工 方案

南皮向阳桥改建工程 旧 桥 拆 除 方 案

新乡市恒达建筑安装工程有限公司

旧桥拆除专项施工方案 一、编制依据 1.《建筑拆除工程安全技术规范》JGJ147— 2.《安全防范工程技术规范》(GB50348- ) 3. 施工图纸 4. 我单位多年来累积的施工经验 二、旧桥概况 向阳二桥位于沧州市南皮县乡道 CH14-王桥村公路上(路线编码 CH17130927),路线等级四级,桥梁中心桩号 K1+534,桥梁编码 CH17L00 0927,与水流方向自西向东成90°夹角,旧桥为3x10m钢筋混凝土双曲拱桥,重力式墩台,全宽 5.5m,净宽4.5m,沥青混凝土桥面,修建于1975年,桥梁病害较为严重,上部承重构件损坏,评定为四类桥,因此对该桥拆除改建。 三、施工准备 1.踏勘现场,了解建筑物或市政设施拆迁情况,对与工程相突的情况应及时报告建设单位,确定方案。 2.搭设临时设施,编制临时用水用电方案与有关部门联系。 3.根据方案确定交通封路及交通疏导、路线、修筑临时战备道路。

4.经调查施工现场无地下管线。 4.拆桥施工机具、机械进场。 5.施工管理人员进场后,会同各管线单位做好现场的移交工作。 6.做好安全防护,对拆除后产生的可回收旧料做好分类堆放,及时运走。 四、施工方案 1.施工技术措施 经我公司专业人员实地考察,本着确保安全、环保、高效拆除的思想,我公司结合多年的实践经验,认为该桥梁应采用全机械作业方式进行拆除。 2.拆除工程施工工艺框图 施工准备 现场勘查 人员到位设备进场

3.拆除方法 旧桥拆除破碎时先将废弃物排入河道,再用挖机清除。三座桥桥面为现浇砼桥面,桥跨度较小,拟采用挖掘机拆除桥梁,采用液压破碎锤作业对桥面人行道栏、桥面、柱进行破碎,用挖掘机将废弃物挖运。拆除步骤从上而下依次为:护栏、破碎桥面、基础。 桥为钢筋砼,我公司采用破碎拆除法进行拆除,挖机必须随时待

完整的旧路改造施工程施工组织方案

施工组织设计 第一章总体施工组织安排及规划 一、工程概况 1 、项目情况 2、路面结构情况 K1+300-K3+100(共1.8公里),本段道路采用破除新建处理。新建路面结构为:4厘米细粒式沥青混凝土+5厘米中粒式沥青混凝土+2X8厘米水泥稳定级配碎石+20 厘米砂砾垫层; K0+000-K1+300和K3+100-K5+522.016 (共3.722公里),对旧路面进行打裂稳压后,采用加宽补强处理,补强结构为:4厘米细粒式沥青混凝土+5厘米中粒式沥青混凝土+18厘米水泥稳定级配碎石;两侧加宽路面结构为:4厘米细粒式沥青混凝土+5厘米中粒式沥青混凝土+18厘米水泥稳定级配碎石+22厘米素混凝土。 二、总体施工组织布置及规划 (一)编制依据范围和原则 1、编制依据: (1)高阳县保沧线至北于八公路改建项目工程施工招标文件相关内容; (2)高阳县保沧线至北于八公路改建项目工程施工招标文件技术标准和要求 及招标文件设计图纸中的相关要求; (3)招标文件中明确规定的有关施工技术规范; (4)我单位拥有的机械设备状况、技术力量、施工能力、我单位类似工程的施工经验; 2、编制原则:

(1)遵照施工图纸、技术规范、现场实际情况、我单位实际情况和招标文件要求; (2)做到统筹安排,科学合理安排施工进度计划,组织均衡生产和工序衔接,做到紧张有序,确保工程质量,尽量缩短工期; (3)采用先进的施工技术和设备,提高机械化、标准化施工作业水平; (4)采用项目法组织施工,推行标准化管理,达到安全、文明、高效; (5)坚持技术创新,推广和应用新技术成果; (二)总体目标: 质量目标:工程质量要求:合格。 工期目标:本合同工期40日历天,计划开工时间为2016年10月1日,计划竣工时间2016年11月10日。 安全目标:严格遵守国家安全生产各项规定,不发生任何等级的安全生产责任事故。 (三)项目机构设置 根据本工程情况,我公司拟为本项目设立项目经理部,(组织机构见框图),并委派项目经理1名、项目总工1名,项目副经理1名,项目经理部下设工程管理部、材料设备部、财务人事部、安全保卫部、综合办公室、工地试验室等部门,项目部实行项目经理全权负责制,总部完全授权给项目经理,项目经理负责组织工程的实施。工程进行过程中,项目经理有人员调动权、财务签字权、机械设备调配权,并对工程质量负有全部责任。同时项目经理接受总部的监督,如项目经理不称职,经业主、监理工程师同意后,总部将更换项目经理。项目经理负责协调各部门之间的关系,各部门负责各自工

(完整版)旧桥维修施工方案

桥梁维修工程) 专项施工方案 编制单位:**建设集团有限公司 编制人: 审核人: 审批人: 编制日期:二〇一四年月 目录 1 ······························································································第一章编制依 据·········· 1 ··········································································

················第二章工程概 况··············· 1 ·······················································································第一节工程概况及地理位置 1 ····················································································第三章施工部 署···················· 1 ···············································································第一节·人员组 织·················· 2 ···························································第二节··················施工准 备····················· 2 ······································第三节···································材料用量计 划··················· 3 ························第四节··············································劳动力需用计划··················· 4 ···········第五节························································主要施工机具计划··················· 4 ···第六节······························································主要施工进度计划·····················4······························································第四章施工工艺、方法和技术························4···························································第一节处理方案··········································· :1. B2桥根据设计提出的桥梁现状病害,桥维修内容如下4··························································桥根据设计提出的桥梁现状病害,桥维修内容如下:2. B65··························································5···················································第二节维修材料及指标··········································混凝土 1.5 ·················································································································································钢材 2.5 ·····················································································································································浆砌片石 3.5 ·············································································································································.注入水泥原浆 45 ···································································································································.垫层砾(碎石)55·······························································································································5······················································第三节施工工艺、方法和技术要求························ .墩台基础处理 5 ····································································································1 ·······························.墩台身处理 7 ···················································································2 ····················································.上部结构8·························································································

单侧路基加宽施工方案

单侧路基加宽施工方案 随着我国经济的高速发展,近几年我国的交通流量急速增长。原双向四车道高速公路在通行能力和使用质量上都已经无法满足需求,结合当前通行需求,很多国家的主干道都进行了加宽拼接。旧路加宽处理不当,就会出现路面开裂、路基沉陷等病害问题。所以,新旧路基间的衔接以及新旧路面结构层的不均匀沉降都是路基加宽施工中的关键技术,同时,安全保通工作也是工作中的重中之重。 1 路基加宽拼接施工工艺流程及操作要点 1.1施工工艺流程图 1.2主要施工操作要点 1. 2.1施工前准备 (1)按照规范要求对沿线导线点和水准点进行复测和加密。如果是两侧拼接加宽,由于旧路基两侧导线点无法通视,需在旧路基两侧各布设一条附合导线,并且两条附合导线应闭合。 (2)路基开工前每隔20 m用全站仪准确放出旧路基外边缘点,并在老路基护栏上用喷漆标上桩号。 (3)每隔20m对旧路基和加宽路基原地面进行复测,核对或补充横断面,发现和设计图纸不符时,查明原因及时处理。 (4)加宽路基施工前,对旧路基填料和加宽路基基底土进行相关试验。每千米每侧至少取2个点;土质变化大时,视具体情况增加取样点数。 (5)按照规范要求对计划的路基填料进行相关试验,特别是对不同来源、不同性质的填料进行相关试验。填料尽量选取和旧路基填料性质相近的材料,避免和减少因新旧路基填料性质差异引起的不均匀沉降,确保新旧路基衔接处的施工质量。 1.2.2原地面清表、回填(1)严格按照设计和规范要求将加宽路基基底范围内的树根全部清除,并将坑穴填平夯实。 加宽路基基底范围内的水井和墓穴用优质填料换填处理。 (2)按照设计和规范要求的清表厚度,对加宽路基范围内原地面表层的腐殖土、草皮、表 土等进行清理。 (3)按照设计和规范要求将加宽路基范围内的边沟、池塘等地段清淤要干净、彻底,然后按设计的地基处理方案施工。 (3)场地清理的范围为高速公路原路基坡脚至新加宽工程路基坡脚外1m的范围内。 (4) (5)原地面清表的同时,将旧路的边沟和隔离栅等相关设施拆除。 (6)加宽路基基底清表完成后,按照设计要求进行原地面填前压实处理,压实度不小于90%,然后回填至原地面。 (5) (7)对于部分基底含水量较高,清表后不易压实的路段,基底可采用翻挖、晾晒或掺灰 处理,也可采用换填一定厚度的砂砾处理。 1.2.3台阶开挖 (1)台阶开挖前,先对老路基边坡进行清坡处理,清坡不易一次全部清理完成,应边挖台阶边清坡,以保证旧路基的稳定。 (2)边坡清理完成后,按照设计要求准确放样出每层台阶的开挖线,保证开挖台阶线型直顺、位置准确。 (3)旧路基台阶开挖针对老路不同的路基填料采用不同的台阶尺寸.对于老路基填料为黏土、亚黏土和卵砾石土时,拼接处的台阶高宜为1.0m。宽为1.5m;对于老路基填料为砂土、粉砂土时,拼接处的台阶高宜为0.4 m,宽为0.6 m。 4)开挖拼接至路床底面的台阶时,根据路基填筑高度确定其台阶高度和位置,台阶面距离路床底面小于130 cm时作为一个台阶开挖,距离路床底面大于130 cm时分成100 cm 和>130 cm两个台阶高度开挖。路床部位作为一个台阶开挖,开挖位置为距离旧路硬路肩

旧桥改造施工方案(2)

目录 第一章编制依据与原则 (1) 1.1 编制依据 (1) 1.2 编制原则 (1) 第二章工程概况 (2) 2.1 大桥概况. (2) 2.2 工程概况. (2) 2.2.1 加固改造的基本要求如下 (2) 2.2.2 设计技术标准 (3) 2.2.3 项目主要负责人 (3) 2.2.4 主要工程数量表 (3) 2.3 工程特点、重点、难点 (3) 2.3.1 工程特点、重点和难点 (3) 2.4 设备、人员动员周期和设备、人员、材料运到施工现场方法 (3) 第三章桥梁工程施工主要加固改造内容 (4) 3.1 上部构造. (4) 3.2 下部构造. (4) 3.3 基础工程. (4) 3.4 主要人员安排(见表02 表) (5) 第四章主要施工方法和工艺 (6) 4.1 改造加固施工顺序 (6) 4.1.1 陀市桥改造施工之前先进行临时汽车便道的施工,待完成可通车后,再 全封闭陀市桥进行改造施工 (6) 4.1.2 依据设计图纸并结合现场情况进行旧桥拱上建筑、桥台桥墩顶部部分的 拆除。 6 4.1.3 主拱圈施工 (6) 第五章分项工程的施工方案 (16) 5.1 汽车便道施工方案 (16) 5.1.1 工程概况 (16) 5.1.2 便道施工方案 (17) 5.2 悬挂吊架搭设方案 (17) 5.2.1 编制依据 (17) 5.2.2 工程概况 (18) 5.2.3 施工部署 (18) 5.2.4 搭设方案 (19)

5.2.5 搭设流程 (21) 5.3 钢筋制作与安装方案 (21) 连州市G323线城南大桥绿化工程施工组织设计 5.3.1 工程概况 (21) 5.3.2施工部署 (21) 5.3.3施工方法 (22) 5.3.4质量保障措施 (26) 5.3.5 安全保证措施 (26) 5.4植筋方案 (27) 5.4.1 工程概况 (27) 5.4.2施工部署 (28) 5.4.3施工方法 (30) 5.4.4质量保证措施 (32) 5.4.5施工安全措施 (32) 5.5主拱圈砼工程方案 (32) 5.5.1 工程概况 (32) 5.5.2施工部署 (33) 5.5.3施工方法 (35) 5.6其它部位改造施工工序 (36) 5.7质量保障措施 (36) 第六章确保工程安全、质量和工期的保障和措施 (37) 6.1安全组织机构保证 (37) 6.2安全保障体系框图 (38) 6.3安全生产重点注意的事项 (40) 6.4质量目标及管理 (40) 6.4.1建立健全质量保证体系 (40) 6.4.2 提高全员质量意识 (40) 6.4.3狠抓工序质量,确保整体质量 (41) 6.4.4选派具有丰富施工经验的队伍 (41) 6.4.5开展标准化作业 (41) 6.4.6 严格技术标准、切实尊重监理 (42) 6.4.7严把材料关 (42) 6.4.8技术措施 (42) 6.5确保工程质量的措施 (43) 6.5.1为确保上述目标的实现,并创造优良工程,具体拟采取以下管理 措施 (43)

老旧小区改造施工组织设计

目录 一、编制依据 二、工程概况 三、项目管理机构 四、施工部署 五、拟投入本标段的主要施工设备表 七、劳动力计划表 八、计划开、竣工日期和施工进度网络图 九、施工总平面图 十、关键部位施工方法及技术措施 十一、确保工程质量的技术措施 十二、安全生产管理体系及保证安全生产措施十三、文明施工管理体系及保证文明施工措施十四、季节性施工技术措施

一、编制依据 1. 中华人民共和国的施工验收规范及标准包括: a)《建筑装饰装修工程质量验收规范》(GB50210 —2001) b)《建筑工程施工质量验收统一标准》(GB50300 —2001) c)《建筑地面工程施工质量验收规范》(GB50209—2002) d)《建筑电气工程施工质量验收规范》(GB50303—2002) e)《建筑给水排水及采暖工程施工质量验收规范》(GB50242—2002) f)《通风与空调工程施工质量验收规范》(GB50243—2002) g)《民用建筑工程室内环境污染控制规范》(GB503325—2001) h)《人造板及其制品中甲醛释放限量》(GB18580—2001) i)《内墙涂料中有害物质限量》(GB18582—2001) j)《溶剂型木器涂料中有害物质限量》(GB18581—2001) k)《胶粘剂中有害物质限量》(GB18583—2001) l)《建筑材料放射性核素限量》(GB6566—2001) q) 《建筑工程项目管理规范》(GB/T50326-2001) r)《建设工程文件归档整理规范》(GB/T50328-2001) 及“装饰材料有害物质限量标准”等国家强制性标准和招标书规定的相关标 准。 2 中华人民共和国现行《装饰材料的施工和验收标准》; 3 有关安全生产、文明施工的规定; 4 公司ISO—9001贯标文件,《质量手册》; 5 公司编制的《质量验收评定的企业标准》; 6 公司编制的《建筑工程施工工艺标准》; 7 集团总公司和本公司制定的行业与企业标准化现场管理的有关规定和细则; 8 公司从事类似施工所积累的专业施工经验。

道路拓宽施工组织设计方案

施工组织设计 1.施工方案及技术措施 1.1工程概况 1.1.1 工程概述 大连市疏港路拓宽改造工程西起绿波桥,东至大连港,拓宽改造工程方案为向旧路南侧拓宽,占用部分铁路用地,将疏港路全线由双向4车道改造为双向8车道(差不多路段),工程主线全长约7.5km,其中道路(含引堤)长5.3km,桥梁2.2km;匝道及辅助路长6.8km,其中道路(含引堤)长5.5km,桥梁长1.3km。并对沿线香炉礁立交原部分转向匝道、疏港路终点人字形立交等节点及部分地面道路进行改建。 本工程为疏港路拓宽改造工程五标段施工,施工里程范围为主线施工里程K3+360—K4+580,施工内容为施工里程范围内的桥梁、道路、防撞柱、声屏障、雨水管线等设施的施工。依照本工程的特点又将本工程分成K3+360—K3+709.085(香炉礁立交桥桥内部分)和K3+709.085—K4+580(香炉礁立交桥桥外部分)。 其中主线K3+360—K3+709.085(香炉礁立交桥桥内部分)分多个独立断面,到K3+709.085后呈“人”字型汇入,以下将各个独立断面列入: (1)本段利用码头线空间新建东联路至香炉礁东匝道(以下

简称:“Z匝道”)道路长349.085m,原码头线框构铁路桥加固后利用; (2)本段利用原东北路与疏港路转向匝道拆除后的空间,新建2车道香炉礁立交西行桥梁(以下简称:“D匝道”)道路长498.147m; (3)原疏港路东行地面匝道改造后,顺接Z匝道新建香炉礁立交东行路东段(以下简称:“H匝道”)长235.693m,香炉礁立交东行路中段利用原有旧路与G&H匝道顺接,对其仅做病害维修; (4)改建东北路与疏港路两处转向匝道桥,其中香炉礁立交SE匝道(以下简称:“F匝道”)长349.881m; (5)新建铁路保障房配套道路(以下简称:“X匝道”)长570.425m。 1.1.2 编制依据 (1)《疏港路拓宽改造工程五标段施工招标文件》 (2)大连市市政设计研究院有限责任公司的施工招标图纸。 (3)国家有关方针政策和国家、辽宁省有关标准规范、规程和验标等: 《都市道路工程设计规范》(CJJ 37-2012); 《公路桥涵设计通用规范》 (JTGD60-2004) ;

旧桥拆除施工方案【最新】

旧桥拆除施工方案 第一章编制说明 一、本桥拆除方案编制依据1施工招标文件及承包合同书;2原西善桥竣工图;3前三次拆桥方案论证会的专家意见;4公路桥涵施工技术规范;5公路桥涵设计技术规范; 二、编制说明:1本方案编制时经项目部、公司有关部门讨论通过,经监理工程师和业主组织专家审查通过后,方能予以实施;2本方案通过后由G205宁芜公路养护改善工程B1标项目经理部负责实施。 第二章西善桥老桥概况 一、老桥概况:西善桥位于西善桥街道,跨秦淮新河,全长126m,桥型为5-23.6m连拱肋拱桥,桥面纵坡0.6%,桥面行车道宽9.0m,人行道宽2*1.75m,桥面总宽12.5m,两侧挑梁有煤气、自来水管道通过,人行道下有光缆、电缆、电讯光缆通过。设计荷载等级为汽车-15级、挂车-80级。因工程建设需要,需将老桥拆除。该桥下部结构为钢筋砼灌注桩基础,在桩顶(距河床2.5m)设一厚70cm、宽130cm、长1400cm的横向系梁,桩上接Φ1.0m钢筋砼柱,高度约4.1m,柱顶设厚170cm、宽160cm、长1400cm的钢筋砼盖梁。上部为钢筋砼拱肋,

横桥向6榀,间距244cm,拱上立柱最高约310cm,立柱上设盖梁,其上安装6.5cm厚预制微弯板,砼现浇基层最厚处约40cm,沥青砂面层10cm。 二、拱桥设计参数:五孔净跨22.2米等截面肋拱桥,f/l=1/6,m=1.347。 三、西善桥老桥现状:经现场调查,西善桥老桥拱肋完整,未发现裂缝;拱肋间的横隔板与拱肋连接完整,未发现裂缝;拱肋上的立柱与拱肋连接部位部分表层砼风化剥落,连接钢板外露。 第三章施工准备 一、竣工图纸审阅项目部组织拆桥有关人员进行老桥竣工图会审,认真阅图,了解老桥的基本概况及各部分构件的工程量,掌握桥梁的结构及受力特点。 二、测量定线项目部配专业测量人员对老桥进行现场测量定位,并与老桥竣工图一一核对,桥梁平面位置与老桥相符。在每孔桩顶盖梁中点、拱脚、1/4拱肋、拱顶布置7个观测点,以便在拆桥过程中及时观测墩顶、拱肋的变形情况。

(完整版)老旧小区改造施工组织设计

项目实施方案 二、项目部署及现场平面布置 场地布置是工程建设的关键之一,其计划布置的好坏,直接影响工程建设的进度,从长期的工程实践中总结的经验教训。 1、我们对场地布置的原则如下: (1)尽量使用建设单位提供的红线征地范围,减少临时租地。 (2)根据施工的先后次序,利用已完工程作未完工程的临时施工场地。 (3)不妨碍施工测量放线,保障运输道路通畅。 (4)依实际地形布置场地,减少建场费用。 (5)各工程的作业不产生干扰。 (6)尽量集中便于管理。 (7)符合环境保护法规、条例,满足使用、安全、卫生。 2、施工总平面图布置情况 (1)道路 施工时只需适当修建纵向施工便道,即可保证施工材料运输和施工机械的进出需要。 (2)生活设施 主要是满足工作人员住宿,饮食及日常生活方面的需要。

(3)供水设施 生产、生活用水均从当地水利网接入。 (4)供电设备 生产、生活用电沿线供电网络已形成,路线沿线为照明用电线路,施工地段大型机械设备用电考虑自发电。工地现场常设一台 50KW 的发电机备用,以满足供电短缺或出现故障时急用,使得施工不得以因电力供应而中断,确保施工工期。 (5)加工车间 各种加工车间,应以方便使用、安全防火、运输费用最少、不影响建筑安装工程施工的正常进行为原则;一般应将加工厂集中布置在同一个地区,且多处于工地边缘。应与相应的仓库或材料堆场布置在同一区域。 (6)设备及仓库主要用于机械设备以及其它材料的储存。 (7)临时设施 用于施工现场的主要机具、主要材料的存放的临时设施。 (8)现场办公主要用于施工现场管理人员办公的需要,以及施工人员安全文明施工教育的场地。 (9)门卫 现场主要出入口处设门卫室。重要材料堆放场地面进行硬化处理特殊材料要入库保存,并做好防腐、防锈等保护措施。 三、施工方法及主要技术措施 (一)墙面喷刷涂料施工方案 1、乳胶漆涂装技术的特点 内墙面一般很粗糙,在乳胶漆涂装之前,需要反复多次地进行处理,首先是用灰泥找平,接着是不止一次地满批腻子,且在每遍之后进行打磨并局部找平,所用的腻子为水性。外墙乳胶漆涂装之前遇到的基材主要是混凝土,乳胶漆的流平性远较工业涂料差,因而,待每涂装一道干燥后要进行打磨找平,然后再涂装下一道。虽然乳胶漆可以采用刷、滚和喷涂等方法涂装,但大部分还是采用长绒辊筒和刷涂相结合的方法涂装。在涂装外用乳胶漆时,需特别注意天气情况,乳胶漆在干燥成膜前必须避免雨淋、冰冻强气流的侵袭和高浓度尘埃的沾污。

一级公路老路拓宽施工方案

老路路面拓宽及处理施工方案 一、编制依据 根据本工程现场施工特点,结合我标施工实力、现有资源、机具的配套能力等,以全线控制工期为目标,统筹考虑各项目的施工工艺、工序衔接、施工进度等编制了本方案。 本施工方案的编制根据以下有关文件资料和建设单位要求及施工实际情况进行编制的: 1、湖南省芙蓉大道湘阴段道路工程(一期工程)施工招标文件, 2、合同文本、技术规范、施工图纸 3、《公路工程质量检验评定标准》(JTGF80/1—2004) 3、《公路养护技术规范》(JTGG H10-2009) 4、《公路路面基层施工技术规范》JTJ 034-2000 5、《公路沥青路面施工技术规范》JTG F40—2004 4、《公路路面施工技术规范》(JTG F10-2006) 5、《城镇道路工程施工与质量验收规范》(CJJ1-2008); 6、《给水排水管道工程施工和验收规范》(GB50268-2008) 7、当地水文、气象、地质资料; 二、工程概况 本项目路线大致呈南北走向,项目起于湘阴县界头铺镇,与芙蓉大道望城段对接,经文家铺、袁家铺,与在建的岳长高速相交,经涝溪桥、跨白水江,进入湘阴县城后与新世纪大道(S308城区段)相交,终于规划的火车站前车站路口,并与本项目漕溪港连接线连接。路线总长22.117KM,其中新建里程5.24KM,扩建里程14.221KM,湘阴大道利用段2.656KM。漕溪港连接线对接漕溪港和岳长高速湘阴东互通。连接线起于石塘乡栽松村,顺接S308,经石塘(规划火车站),终于漕溪港。线路总长6.66KM,为路基宽度15m的二级公路。 本项目主线是城市快速干道,设计行车速度80km/h,路基宽60m.中间带1m(含左侧路缘带2*0.75m)、行车道2*3*3.50m、2*3m的边分带,2*6m的辅道、2*3m的人行道、2*5.5m的绿化带.路拱坡度:主路2%,辅道-1.5%,人行道—2%。路面采用沥青砼路面。。 本合同段,起点桩号为K31+680,终点桩号为K39+860,路线全长8.18km.其中

旧桥加宽施工方案

防护加固建议性方案 一、工程简介 包茂高速孙家湾收费站北迁工程涉及主线一座1-8m空心板小桥加宽,新建加宽桥下部结构设计采用钻孔灌注桩基础,每测为两排Ф1.2米6跟桩基,全桥共计24跟,桩顶承台纵向长5.4m,右侧宽9.0m,左侧宽11.0m,台身为伏壁桥台,台身高7.01m。 该桥左侧加宽10.5m,右侧加宽8.5m。采取将原桥上部边板悬臂打掉改为中板。新建桥台与原桥台分离,新旧桥台间距1cm。 经过现场测量知该桥桥面至桩顶面高差8.2m。 该段原路基填料为风积沙,坡比为1:3,植被防护。 二、加固的必要性 加宽桥采取将原桥八字墙拆除后紧靠旧桥台身沿横向接长。施工加宽桥桩基时,必须将原八字墙及其后路基填土进行挖除,这样就会扰动现有包茂高速路基和路面,随着开挖加深,甚至造成路基坍塌,进而危及路基路面的稳定性和安全性。为有效防止危害的发生,开挖前必须对该段路基进行有效的加固保护。

三、加固方案 1、采用抗滑桩加固 先将加宽段路基段填方全断面填筑至现有路面标高;再在新旧路基接茬处的新路基范围内沿纵向钻孔灌注钢筋混凝土桩基,此为抗滑桩。拟用桩径1.2m,桩长20m,桩距1.7m,单侧布置8根桩基。详见下页方案1图。 2、打入钢管桩加固 先在新旧路基接茬处的新路基范围内沿纵向将钢管桩打入测量指定位置及标高;然后在钢管桩内注入1:2水泥砂浆,再在外侧土方开挖清理后插入1cm厚钢板。拟用钢管直径为 0.6m,桩长20m,桩距0.3m,单侧布置15根桩基。钢管桩外 侧焊接1cm厚钢板,防止路基填料外漏。详见下页方案2图。 四、施工顺序 方案1、测量放线→路基加宽段填筑→抗滑桩施工→桩外挂网喷锚防护→桩外侧土方开挖→加宽桥下部施工。 方案2、测量放线→钢管桩施工→管内灌注C15砼→桩外侧土方开挖→插入1cm厚钢板→加宽桥下部施工。 后CRK1+299.831加宽桥抗滑桩(钢管桩)示意图4页。 Xxxx

公路改扩建工程施工组织设计文字说明

五、施工组织设计 第一章总体施工组织布置及规划 (一)工程概况 1、工程范围及项目内容 北京至哈尔滨高速公路是国家高速公路网中所规划的由北京出发的七条放射状路线之一,沈阳(王家沟)至铁岭(杏山)段地处我国东北区域的南部,位于辽宁省的中北部,分布于辽宁省的沈阳市、铁岭市辖区内。京哈高速是东北地区公路交通运输的大动脉,是东三省南下西进入关的重要通道吗,沈铁高速作为京哈高速的组成部分之一,是辽宁省高速公路网的重要组成部分,是东三省相互联系的重要路段。 沈阳(王家沟)至铁岭(杏山)公路改扩建工程路线总体呈南北走向,起点位于沈阳王家沟,途径铁岭市、开原市、昌图县,终点位于铁岭杏山。 沈阳(王家沟)至铁岭(杏山)公路改扩建工程路基五标起点桩号为K779+420,

终点桩号为K794+000,路线长度为12564.302m。本项目原路基宽度26.0m,采用双侧加宽为主的扩建方案,路基两侧同时向外拓宽8.0m,扩建后路基宽度42.0m。其中: 1、整体式路基: 本项目主线为四车道改扩建成八车道工程,改建后全幅路基宽度42m,其中:中央分隔带3m+2*0.75m左侧路缘带+2*4*3.75m行车道+2*3.0m硬路肩+2*0.75m土路肩;行车道、硬路肩的标准横坡为2%、土路肩为4%。中央分隔带缘石高8cm,外侧路缘石填方段高12cm,挖方段与路面同高,路缘石采用花岗岩,缘石外土路肩与缘石同高。 2、分离式路基: 分离式路基单幅路基宽度20.75m,其中:0.75m路缘带+1.25m硬路肩+4*3.75m 行车道+3.0m硬路肩+0.75m土路肩;行车道、硬路肩的标准横坡为2%、土路肩为4%。路缘石填方段高12cm,路缘石采用花岗岩,缘石外土路肩与缘石同高。 双侧加宽路基 主要工程项目内容有: (1)路基土石方工程: 路基土石方数量表

新老路搭接专项施工方案范文

新老路搭接专项施 工方案

新旧路基搭接处理专项施工方案 一、工程概况 库拜玉项目为G579线一期工程,本项目第二合同段位于阿克苏地区拜城县境内。本合同段共有1段主线长12.655km、2条连接线合计为12.976km(包括化工业园区连接线、大桥乡连接线),主要包括路基工程、路面工程、桥梁与涵洞工程、交叉工程、交通安全设施工程等。 主线位于拜城县以西30km,路线大部分路段穿越荒漠戈壁,没有经过城镇。主线拜城段起点K113+083.199接于克拉苏石油公路k95+883处,从起点向西南方向向左偏出,路线在中段避让大宛齐油田。终点接于S307线K121+180处,终点桩号为K125+587.82(K115+546.103处设149.85m长链一处, K123+392.130处设长3.147m 短链一处),路线全长12.655km。公路等级为二级公路,设计速度80km/h,路基宽度12m。 大桥乡连接线为G579线与大桥乡之间的连接线,位于拜城县西侧约20km大桥乡境内。大桥乡连接线起点从G579线k118+883.52处岔出,沿农村公路Y414线向南布设,直至接于大桥乡北侧绿洲区边缘,改造路段全长4.4km。本段道路为老路改建工程,k0+000-k3+800段长3.8km老路为8.5m宽砂砾路,k3+800-k4+400段长0.6km为7.5m宽的沥青路,公路等级三级,设计速度为30km/h。 本项目新旧路基衔接的主线段落为K113+083-K113+330右侧,处

理方式为挖除旧路面层,重新铺设基层面层;K113+150-K113+350右侧,处理方式为路床超挖回填,挖台阶并铺设土工格栅。大桥乡连接线LK3+785-LK4+400段为挖除原有路面结构层,重新铺设基层面层。 二、施工准备 1、严格遵守《公路路基施工技术规范》(JTG F10- )以及现行相关质量验收标准的有关施工规范、规程。坚持实事求是,力求技术先进、方案科学可行、经济合理的原则,确保旧路现状交通流量和行车安全,确保对主体工程工期的要求。充分考虑各种不利施工进度和质量的因素,在工期安排、人员设备配置、施工方法等方面综合考虑。 2、根据本工程中路基施工进度计划的安排以及施工生产作业方式的特点和机械设备的生产率情况,项目部将及时地配备充分的土方挖、填、压实机械设备和土方运距机械,以加大机械化的使用程度,满足工程施工进度和施工质量的要求。 3、根据设计图纸进行测量放样,测量放样应符合下列要求:平面位置允许误差±50mm,高程允许误差+10mm,-15 mm。 4、在开工前,对取料场的路基填料以每5000m3以及在土质变化时取有代表性的土样,按有关标准进行天然密实度、含水量、液限、塑性指数等试验,对填料进行颗粒分析,天然密度试验,并测定填料的最大干密度、最佳含水量和土的CBR强度值,并将测试结果报请业主方和监理方审批。 三、施工程序及施工方法