Previous Issue: 31 August 2004 Next Planned Update: 19 June 2016
Revised paragraphs are indicated in the right margin
Page 1 of 28
Primary contact: Doiron Shannon Earl on 966-3-8735067
Engineering Procedure
SAEP-12
19 June 2011
Project Execution Plan
Document Responsibility: Project Management Office Department
Saudi Aramco DeskTop Standards
Table of Contents
1 Scope.............................................................
2 2 Applicable Documents.................................... 4
3 Instructions.....................................................
4 4
Responsibilities (17)
Exhibits............................................................... 19 Exhibit A - Table of Contents.............................. 19 Exhibit B - Approval Sheet.................................. 20 Exhibit C - Revision Control................................ 21 Exhibit D - Contracting Plan Matrix..................... 22 Exhibit E - Comparison of Various Contracting Alternatives............................... 23 Exhibit F - Project Milestone Schedule............... 24 Exhibit G.1 - SAPMT Organization (Typical Design Phase)................................ 25 Exhibit G.2 - SAPMT Organization (Typical Construction Phase)....................... 26 Exhibit H - Project Responsibility Matrix............. 27 Exhibit I - Value Practices
Optimum Implementation Timing (28)
Next Planned Update: 19 June 2016 Project Execution Plan
1 Scope
1.1 Definition
The Project Execution Plan (PEP) is a strategic planning document that defines
objectives, plans, requirements and related information necessary for optimum
project execution. It is a master reference guide that promotes common
understanding and alignment of all project participants. The PEP is prepared by
the Project Manager, with input from the Proponent and other Saudi Aramco
organizations that have key roles in a project's execution.
1.2 Purpose
The PEP serves as a communications and coordination tool that formally
establishes the Project Manager's front-end project planning, with emphasis on
identifying issues critical to project success and defining strategies to address
these issues. It is an agreement endorsed by the Saudi Aramco Project
Management Team (SAPMT), the Proponent, and Management defining the
execution of the project, including schedule, method(s) of executing the work
and the responsibilities of major participants. In one comprehensive document,
the PEP relates the approved project scope with contracting and material plans,
cost information, summary schedules, value practices implementation, risk
management, departmental responsibilities, and SAPMT staffing requirements.
The PEP is intended to provide strategic guidance to develop more detailed
tactical planning and execution tools as the project progresses.
1.3 Timing and Application
The PEP shall be issued in accordance with the timing outlined below, which is
designed to support the PEP's purpose of serving as a strategic planning tool:
?Abbreviated PEP is mandatory for all BI's
?Full PEP is mandatory for BI's
- over $50MM
- for ≤ $50MM, as recommended by the responsible Dep artment Manager ?PEPs are waived for Master Appropriation projects.
1.3.1 Abbreviated PEP
To be issued prior to release of Preliminary Engineering funds. When
requested, Project Management Office Department (PMOD)/ Project
Next Planned Update: 19 June 2016 Project Execution Plan
Execution Metrics Division (PEMD) shall participate and assist
SAPMT in the preparation of the PEP Level II Milestone Schedule.
The Abbreviated PEP is intended to provide a framework for
subsequent planning. It is not expected that every detail required by
SAEP-12 will be addressed at this time. As a minimum, the SAPMT
shall address the following items using the best information currently
available. It is understood that all sections are subject to further
development and change:
?Project Summary
?Contracting and Materials Procurement Strategy
?Organization Chart
?Milestone Schedule
?Value Improvement Practices
?Risk Management
?Contractor Saudization Plan
?Maximizing In-Kingdom Engineering, Procurement and
Construction Work
?Projects within Existing Facilities (Non-Grass Roots)
?Areas of Concern
The Abbreviated PEP will be the basis for development of the Full
PEP if one is to be prepared. The Abbreviated PEP shall be updated or
revised as required to reflect major changes in plans if a full PEP is not
required.
1.3.2 Full PEP
To be issued for approval by 30% preliminary engineering completion
or within 90 days of Project Proposal Start. SAPMT will report status
of PEP submittals in the PPU's comments section.
The PEP shall be updated as the need arises prior to implementing
major scope changes or significant changes in contracting plan, and at
other times deemed necessary by the PEP approval authority. SAPMT
may issue a completely revised document or an addendum covering the
changed section(s) only.
Next Planned Update: 19 June 2016 Project Execution Plan 2 Applicable Documents
The latest edition of the applicable reference documents shall be applied:
Saudi Aramco Engineering Procedures
SAEP-13Project Environmental Assessments
SAEP-14Project Proposal
SAEP-21Project Execution Requirements for Saudi Aramco
Royalty/Custody Metering Systems
SAEP-50Project Execution Requirements for Third Party
Royalty/Custody Metering Systems
SAEP-31Corporate Equipment and Spare Parts Data
Requirements
SAEP-125Preparation of Saudi Aramco Engineering Standards
SAEP-329Project Close-out Report
SAEP-367Value Improvement Practices Requirements
Saudi Aramco General Instructions
GI-0002.710Mechanical Completion and Performance Acceptance
of Facilities
GI-0400.001Quality Management Roles & Responsibilities
GI-0710.002Classification of Sensitive Documents
Saudi Aramco Cost and Scheduling Manual
Saudi Aramco Contracting Manual
Supply Chain Management Manual
Saudi Aramco Engineering Report
SAER-5437Guidelines for Conducting HAZOP Studies
3 Instructions
The PEP shall include the following sections:
3.1 Table of Contents, Approval Sheet and Revision Control
For format, see Exhibits A, B, and C.
Next Planned Update: 19 June 2016 Project Execution Plan
3.2 Project Summary
Provide a brief synopsis of the objectives, scope, and current progress status of
the Project. Incorporate into the Project Summary:
3.2.1 Project Purpose
Summarize the purpose of the project explaining why it is being done
(e.g., to increase production capacity of a plant by 100,000 barrels/day).
3.2.2 Design Basis
Provide a synopsis of how the project is to be accomplished (e.g., to
increase production by expanding existing facilities or by constructing
a new plant) by summarizing the project's basis of design as described
in the current scoping paper.
3.2.3 Project Scope
Briefly describe what is to be accomplished by the project, such as
project activities to be achieved, physical facilities to be built,
demolished, or revamped, etc. This information will be a summary of
the work described in the current Design Basis Scoping Paper and/or
Project Proposal scope of work.
3.2.4 Project Progress Status
Define where the project currently stands in the project life cycle, in
order to establish the information basis on which the PEP is being
prepared. Briefly identify the major ongoing activities and provide
current percent complete of project proposal, detailed engineering,
procurement, and construction, as applicable.
3.2.5 Project Location
PEP should state location of project and indicate whether offshore or
onshore.
3.2.6 Project Shutdown Requirements
PEP should identify shutdown requirements and if it is planned during
Plant T&I.
3.2.7 Related Projects
Next Planned Update: 19 June 2016 Project Execution Plan
3.3 Contracts
The contract development process is often intricate and interrelated and once
actions based on a particular strategy are initiated, it may not be practical or
all aspects of the work must be developed and presented by contract proponent
(SAPMT) to management at an early stage of every project.
3.3.1 Contracting Strategy
A Contracting Strategy document reflecting the SAPMT's initial view
any major changes (particularly related to OOK contracts, non-lump
Contracting Strategy is included for other organizations for
information purpose only. If a Full PEP is not prepared, the
Contracting Strategy (as applicable) shall be updated even if other
parts of the Abbreviated PEP are not.
The Contracting Strategy shall summarize the plans for developing and
procuring the necessary contracts for the project's major contracting
phases (i.e., Project Proposal, Detailed Design, Procurement and
Construction). Information shall be categorized by the major
contracting phases mentioned and include the following:
a) Type of Contract (Lump Sum Turnkey, Lump Sum, Lump Sum
Procure/Build, Reimbursable Cost, Unit Rate, etc.) and the
reasons for selection.
b) Procurement Method (Competitive Bid, Sole Source, etc.) and
reasons for selection and whether an existing General Bid Slate/
Screening List will be used.
c) Appropriate Project and Contracting Milestones, for example:
- Expenditure Request Approval (ERA)
- Prepare and Issue Bid Packages
- Contract Award
- Mechanical Completion
- On Stream
The Contacting Strategy shall include an exhibit illustrating the
contracting plan in matrix form (See Exhibit D).
Next Planned Update: 19 June 2016 Project Execution Plan
3.3.2 Contracting Plans
A Contracting Plan is required for each contract action (or related
contract actions) unless the requirement has been waived (in writing)
by the Contracting Representative. The Contracting Plan is the joint
responsibility of the Contracting Department and the contract
proponent (SAPMT). After approval by the Contract Signatory, the
For more detailed instructions, refer to the Saudi Aramco Contracting
Manual VII(1) - Contract Planning and VIII(24) - Contracting Plan
(Outline).
Prior to carrying out a detailed analysis as part of the Contract Plan,
potential contracting alternatives in the form of a summary level
schedule comparison shall be prepared (See Exhibit E).
For projects involving major LSTK contracts, the option of issuing the
bid package prior to ERA should be addressed. Analysis should
include estimated effects on schedule, cost, and other considerations
comparing the normal procedure of issuing bid package after ERA
with a proposed option of bidding prior to ERA. This analysis should
also include evaluation of the feasibility of using the LSTK bids in the
ER estimate.
3.4 Material Procurement Plan
The Material Procurement Plan addresses project material requirements, their
procurement and movement. It should define the proposed procurement and
traffic responsibilities of Saudi Aramco and the Contractor(s). SAPMT will
review proposed procurement actions with representatives of Material Supply.
This review shall involve, at a minimum, the project Liaison Coordinator of the
Projects Purchasing Division.
3.4.1 Critical and Long Lead-Time Material and Equipment
Prepare an itemized listing of material and equipment considered
critical and/or long lead items. Specific actions should be identified to
ensure that such items will arrive at the designated job site on or before
the required dates irrespective if handled by Saudi Aramco or by a
contractor. Examples of such actions include use of air freight,
dedicated trucks, premiums, penalty and incentives, identification,
prioritization, and close monitoring of critical material and its proper
ties to the construction schedule, SAPMT representative at vendor's
shop, expediting custom clearance, unloading and placing large
material on foundations rather than storing, etc.
Next Planned Update: 19 June 2016 Project Execution Plan
If procurement of major equipment and materials is on the critical path
of the project schedule, SAPMT shall consider various strategies to
reduce its impact to the project schedule. Such strategies may include
early Company procurement, early Company procurement and
assignment (“novation”), Company or Project Proposal Contractor
procurement of early vendor engineering (“beneficial engineering”),
and early engineering by vendors using time unit rates under the
Project Proposal Contractor's contract.
3.4.2 Other Material and Equipment
Designate responsibilities between Saudi Aramco and Contractors for
cost effective supply of materials and equipment to meet project
schedules.
The Material Procurement Plan requires addressing maximum cost-
effective usage of locally-manufactured materials, use of on-hand and
surplus material, material quantity concerns, standardization, and total
cost of ownership and takes into consideration the guidelines of
SAEP-125, Saudi Aramco Engineering Standards, and the Supply Chain
Management Manual. Furthermore, the plan should address the use of
existing corporate agreements; vendor selection criteria; material quality
concerns; documentation; expediting; inspection; packing and marking;
shipping, clearance and receiving; storing, issuing, staging, and the
return and disposal of excess project material and equipment.
3.4.3 Surplus 9COM Material and Equipment
Review Surplus 9COM (previously known as Direct Charge – DC)
material and equipment list that could be incorporated in the project's
design. Surplus 9COM material and equipment should be looked at in
the earliest stages of design so that it can be incorporated into the
design.
3.4.4 Excess 9CAT Materials
Review Excess 9CAT (previously known as Saudi Aramco Materials
System – SAMS) materials list of high-dollar-value items ($10,000 and
above) that could be incorporated in the project's design.
3.4.5 Heavy/Oversize Material or Equipment
Prepare a list of heavy/oversize material or equipment. Establish
responsibilities for heavy lift requirements. Heavy lift planning for
materials and equipment, and related requirements, will be coordinated
Next Planned Update: 19 June 2016 Project Execution Plan
with the Saudi Aramco Heavy Lift Group. Consult with the Materials
Traffic Department regarding proposed international shipping
arrangements and with the Transportation Department for in-Kingdom
movements of heavy/oversize material or equipment.
3.4.6 Start-up, Operating, and Capital Spares
Establish responsibilities and requirements for start-up, operating, and
capital spares procurement. Ensure compliance to requirements for
operating spare parts in accordance with SAEP-31, Corporate
Equipment and Spare Parts Data Requirements. Address the
disposition of contractor procured spares, if applicable.
3.4.7 Customs Duties
Address responsibility for payment of customs duties, based on the
most recent Government regulations including compliance with proper
customs exemption requirements if any.
3.4.8 Quality Assurance/Quality Control
Identify materials quality assurance and quality control planning
requirements. Address vendor inspection requirements and plans,
including identification of materials to be factory tested and
coordination with Saudi Aramco Vendor Inspection. For details, refer
to GI-0400.001Quality Management Roles & Responsibilities.
3.5 Pre-commissioning, Commissioning, and Startup Plan
Startup is defined as the transitional phase between facility construction
completion and on stream, including all activities that bridge these two phases
(i.e., pre-commissioning through performance acceptance). Overall project
success is strongly related to startup success, which depends heavily on the
degree and thoroughness of early startup planning. Saudi Aramco GI-0002.710,
Mechanical Completion and Performance Acceptance of Facilities, provide the
framework for startup planning. The Best Practices “Planning for Startup
Model” is a useful reference and provides tools designed to assist in developing
and implementing an early startup plan. In accordance with SAEP-367, Value
Improvement Practice Requirements procedure, 50% of the startup planning
effort should be completed by the end of Project Proposal phase. By the end of
detailed design the startup planning effort should be 80% complete.
The startup plan addresses the roles and responsibilities of key persons and
organizations, as well as the timing of startup planning and execution activities.
The startup plan shall address the following issues:
Next Planned Update: 19 June 2016 Project Execution Plan
3.5.1 Responsibilities and Timing
SAPMT in assistance with Proponent is responsible for developing
startup plans during design phases. SAPMT shall also ensure that
SAPMT and Proponent representative shall be assigned responsibility
for managing the planning of startup; specify when these assignments
will be made and what their startup planning responsibilities will
entail. Identify other key contributors to startup planning and
execution, including Inspection, Loss Prevention, contractors, vendors,
and others as required, and define their roles and responsibilities.
Provide estimated timing and duration of startup planning, pre-
commissioning, mechanical completion, and commissioning activities,
including operations and maintenance training required prior to startup.
3.5.2 Systems Turnover Sequence
Provide a conceptual plan of the breakdown of the facility into systems
and the sequence in which these systems will be checked out and
turned over to the Proponent. Address specific plans to implement
partial Mechanical Completions, if applicable.
3.5.3 Startup Execution Plan (SUEP) Preparation
The Startup Execution Plan (SUEP) is a planning document that
defines the objectives, plans, requirements, and related activities and
information necessary for a successful startup. It is a master reference
guide that promotes common understanding and alignment of all
project participants.
3.6 Project Cost
3.6.1 Project Funding
Describe Preliminary Engineering Funds requirements, Prior Approval
Expenditure Request (PAER) Funds requirements if applicable, and
plans for ER Estimate preparation. Also, describe the project budget
amount and provide a summary of its major elements of engineering,
material, and construction if available. Describe the basis of the
current estimate. Identify any critical cost items that will require
special attention to avoid cost overruns.
Next Planned Update: 19 June 2016 Project Execution Plan
3.6.2 Cost Control
Describe the strategies to be utilized to ensure effective cost control
and accurate cost reporting throughout the project life from
Preliminary Engineering Funds approval through project close-out.
Address the subjects of work breakdown structure, cost contingency
management, cost status reporting systems, and expenditure forecast
preparation. Identify any unique project characteristics that may
require deviations from standard Saudi Aramco cost control
procedures, and provide plans for handling such cases.
The project's work breakdown structure should be developed as a
unified system that supports integrated cost and schedule control.
3.7 Project Schedule
3.7.1 Project Plan
Describe the summary logic, interdependencies and contracting
strategy used to develop the Project Milestone Schedule. Identify
critical risk items, long lead equipment delivery durations and any
other factors that could result in potential schedule delays.
Provide Project Milestone Schedule (See Exhibit F) in bar chart format
summarizing major project activities, milestones, plant outages and
interfaces with other projects as applicable. The Project Milestone
Schedule shall include but not be limited to identify the following:
?Contract development and award milestone dates by packages.
?Value engineering studies dates
?Project proposal review and approval
?ER estimate preparation, review & approval dates
?Mobilization for engineering, procurement and construction dates
as applicable
?Detail engineering control points
?Long lead material procurement activities and durations including;
purchase requisitions, purchase orders, fabrication, ex-works and
site delivery dates.
?Interim construction milestones such as but not limited to;
discipline completion dates, building completion dates, shutdowns,
Next Planned Update: 19 June 2016 Project Execution Plan
pre-commissioning completions by area for Partial MCC’s,
pre-commissioning duration, commissioning and startup durations,
Beneficial On Stream (BOS) date where applicable, final
occupancy date.
The project summary schedule described in SAEP-14 shall also include
the requirements of tie-ins, hot tap/stopple operations durations and
dates as well as drilling milestones, as applicable.
3.7.2 Progress Measurement and Schedule Control
Describe the methodology to be utilized to ensure accurate progress
measurement and effective schedule control throughout the project life.
Address the subjects of work breakdown structure, progress reporting
systems, responsibilities of contractors with respect to progress
measurement and schedule control, and Critical Path Method (CPM)
scheduling software requirements. The Saudi Aramco Cost and
Scheduling Manual provides a definition of scheduling levels of detail
to be used on Saudi Aramco projects.
3.8 Project Organization and Interfaces
3.8.1 Establishing the SAPMT
Describe the process of establishing the SAPMT, including the following:
?Through review process that will be conducted to determine the
type of disciplines needed to be covered by the SAPMT.
?Objectives, and responsibilities (including correlation with work
breakdown structure) for the Project Manager, Senior Project
Engineers, and other SAPMT members as appropriate.
?Develop a project specific roles and responsibilities matrix that
includes all the SAPMT members.
Provide organization charts for each major phase of the project
(Exhibit G).
3.8.2 SAPMT Interfaces
Describe roles, responsibilities, and reporting relationships between the
SAPMT, Proponent, and other parties involved in the project,
including Saudi Aramco departments and contractors. Include a
typical project responsibility matrix (See Exhibit H).
Next Planned Update: 19 June 2016 Project Execution Plan
Roles and responsibilities of various organizations for execution of
projects related to Saudi Aramco and Third party Royalty/Custody
Metering Systems are specified in SAEP-21 and SAEP-50.
Describe how the SAPMT will provide effective and efficient
communications among the SAPMT, proponent, support groups, and
contractors during all phases of the project.
Describe how the SAPMT will provide close coordination and
effective interface with other BI SAPMTs or Proponents, whose work
will have direct impact on the Project's activities.
3.9 Value Improvement Practices
The oil and gas industry, as a whole, uses value practices that have been proven
through experience to assist projects in reaching goals of shorter schedules and
lower costs, as well as enhanced safety. The value practices outlined below are
applicable to Saudi Aramco projects and, when properly planned and
implemented, can help guide project teams to improved performance. If a
project team does not include the use of value practices as an activity in the
project plan, some value practices may be overlooked and potential benefits lost.
Value practices must be implemented early in the project cycle to be effective,
so the planning must reflect this approach.
Provide Value Practices Implementation Schedule (For optimum implementation
timing see Exhibit I)
SAPMT may contact PMOD/Project Execution Optimization Division (PEOD)
for assistance with this section, if required.
3.9.1 Value Engineering
Summarize SAPMT plan for implementing Value Engineering in
accordance with the requirements of SAEP-367, Value Improvement
Practice Requirements and SAEP-14, Project Proposal. Identify when
the VE study will be conducted and by whom.
3.9.2 Project Risk Management
Summarize SAPMT plan for implementing Project Risk Management
currently identified in accordance with the requirements of SAEP-367,
Value Improvement Practice Requirements.
3.9.3 Best Practices Implementation
Summarize SAPMT plan for implementing Project Management's
Next Planned Update: 19 June 2016 Project Execution Plan
currently-identified or other industry best practices in accordance with
the requirements of SAEP-367, Value Improvement Practice
Requirements and the requirements of SAEP-14, Project Proposal.
3.9.4 Benchmarking
Summarize SAPMT plans for initiating a formal benchmarking
analysis in accordance with SAEP-14, Project Proposal. Identify when
the benchmarking study will be conducted and by whom.
3.10 Project Safety and Environmental
3.10.1 Hazard and Operability (HAZOP) Studies
?Plans and Objectives
Summarize SAPMT plan for implementing HAZOP studies.
The objective in performing HAZOP studies is to identify any
problems. An additional goal is to provide further insight for risk
management decisions by assigning a qualitative risk factor to each
potential hazard or operability problem.
For reference, see SAER-5437 Guidelines for Conducting HAZOP
Studies
?Requirements and Timing
The SAPMT and Proponent, in conjunction with the Loss
Prevention Department (LPD), Environmental Protection
Department (EPD), and Process & Controls System Department
(P&CSD) shall decide which projects and specific facilities require
HAZOP studies, how many and how detailed each should be.
Duplicate facilities shall not require new HAZOP studies. Only
new or upgrade facilities that use, produce, process, transport, or
store flammable, explosive, toxic or reactive substances in large
quantities should have HAZOP studies.
The first of the HAZOP studies shall be conducted during the
project proposal stage and the report shall be incorporated into the
Project Proposal. The HAZOP studies, concentrating on
continuous mode of operation, shall be performed during the
changes are forecasted. HAZOP study recommendations shall be
incorporated into the final design of the facility.
Next Planned Update: 19 June 2016 Project Execution Plan
The final HAZOP study shall be performed as soon as the
operating procedures are developed in sufficient detail to allow
analysis of startup, shutdown, and emergency shutdown modes of
operation. HAZOP study recommendations shall be incorporated
before startup of the facility.
HAZOP Studies Execution
The HAZOP studies should be part of the project proposal and
detailed design contract, if Saudi Aramco decides the Contractor is
qualified to support conducting the studies. If the Contractor is not
qualified to support conducting the study, a subcontractor can be
used.
SAPMT shall notify LPD, EPD, P&CSD, and all other concerned
parties at least six weeks in advance of any PHA or HAZOP study
so that qualified personnel can be assigned and to participate and
also the supporting documentation can be prepared (PFDs, P&IDs,
operating procedures, etc.).
A copy of each report shall be provided to LPD for review prior to
release. SAPMT shall distribute copies of HAZOP study reports to
all participants within four weeks after the study.
3.10.2 Environmental Assessment
Describe the plan for preparing the Environmental Impact Assessment
as required by SAEP-13, Project Environmental Impact Assessment.
3.10.3 Project Safety Program
Describe the safety program for the project. The program should
describe the safety objectives for the project and how the program will
be managed to ensure these objectives are met. Address the issues of
safety.
3.11 Contractor Saudization Plan
Address what actions will be taken to promote and support the hiring and
training of Saudi Arab personnel by contractors working on the project.
3.12 Maximizing In-Kingdom Engineering, Procurement and Construction Work
Address what actions will be taken to promote maximizing the IK engineering,
procurement and construction work. Also, address the feasibility of performing
Next Planned Update: 19 June 2016 Project Execution Plan
portions of any planned LSTK OOK design work IK.
3.13 Projects within Existing Facilities (Non-Grass Roots)
Address what actions will be taken with regards to upgrade renovation or
addition to existing facilities in the following areas:
?Design and site investigation work required during the project proposal
development and detail design phases to determine as-built condition of
existing facilities.
?Risk assessment for items that may impact the project cost estimate.
3.14 Areas of Concern
Address project concerns where corresponding plans of action or solutions have
not been completely defined. Concerns for project delivery should be addressed
by Project Risk Management, including any unusual efforts or procedures
required for successful project completion. Areas of Concern relate to external
interfaces and engineering or operational issues that may affect the resulting
capability provided by the project should also be highlighted here.
3.1
4.1 Engineering Design
Highlight factors that may influence the project design (e.g., operations
manning philosophy, operating reliability, capital versus operating
costs, material sourcing premiums, labor premiums and location
constraints, etc.). Provide action plans to address any concerns.
3.1
4.2 Construction
Highlight factors that can influence the project construction (e.g., site
location, security, other projects, etc.). Provide action plans to address
any concerns.
3.1
4.3 Company Interface
Summarize other Saudi Aramco activities that will be affected by the
project (e.g., maintaining minimum production rates at existing
facilities).
3.1
4.4 Government Interface
Identify anticipated interfaces with Saudi Arabian Government
authorities including Land Permits and other required approvals.
Address the timing and duration of all such activities.
Next Planned Update: 19 June 2016 Project Execution Plan
3.1
4.5 Other Concerns
Identify other known factors that may impact efficient execution of the
project and provide plans that address the concerns (e.g., SAPMT
staffing restraints).
4 Responsibilities
4.1 Preparation
obtaining approval signatures are the responsibilities of the Project Manager.
Project Management Office Department (PMOD)/Project Execution
Optimization Division (PEOD) is available to explain this procedure.
4.2 Approvals
The Abbreviated PEP that is prepared prior to release of Preliminary
Management Department Manager. SAPMT shall submit a copy of the
Abbreviated PEP to Project Management Office Department (PMOD)/Project
Execution Metrics Division (PEMD) to verify the milestones. Copies of all
versions of the Abbreviated PEP shall also be included in the Preliminary
Project Close-out report (SAEP-329).
For projects with a value of $50MM or below and where the Department
Manager has elected to prepare a full PEP, the initial issues only require
approval by the Project Management Department Manager.
For projects with a value between $50MM and $100MM, the initial full PEP
requires approval by the Area General Manager after concurrence by the
Proponent Admin Area Head.
For projects with a value over $100MM the initial full PEP requires approval by
the Vice President of Project Management after concurrence by the Proponent
Admin Area Head (see approval sheet, Exhibit B).
A revised full PEP only requires approval by a Project Management Department
Manager after concurrence by the Proponent Department Manager. A copy of
the revised full PEP shall be forwarded to the signatory of the initial full PEP.
PMOD shall review PPU comments on the status of Full PEP submittals at 30%
preliminary engineering as an integral part of BISR reviews. Copies of all
versions of the Full PEP shall be included in the Preliminary Project Closeout
report (SAEP-329).
Next Planned Update: 19 June 2016 Project Execution Plan
4.3 Distribution
It is the Project Manager's responsibility to distribute the signed-off PEP
including initial and updated electronic or hard copies of both Abbreviated as
well as Full PEP. Distribution includes the Project Proponent, Project
Management Office Department (PMOD) and Materials Supply's Purchasing
Department. In addition, copies of revised PEPs shall be distributed to
signatories of Rev. 0 PEPs.
4.4 Confidentiality
In accordance with GI-0710.002, Classification of Sensitive Documents, PEPs
are to be classified by the SAPMT as either “Restricted” or “Confidential” (for
“major” expansions or developments) and marked and handled accordingly.
Revision Summary
19 June 2011 Revised the "Next Planned Update."
Scheduled update to incorporate improvements.
Next Planned Update: 19 June 2016 Project Execution Plan
Exhibits
Exhibit A – Table of Contents
SECTION TITLE
- APPROVAL SHEET
- REVISION CONTROL
1 PROJECT SUMMARY
2 CONTRACTING
3 MATERIAL PROCUREMENT PLAN
4 PRECOMMISSIONING, COMMISSIONING,
& STARTUP PLAN
5 PROJECT COST
6 PROJECT SCHEDULE
7 PROJECT ORGANIZATION AND INTERFACES
8 VALUE PRACTICES IMPLEMENTATION
9 PROJECT RISK MANAGEMENT
10 PROJECT SAFETY
11 AREAS OF CONCERN
12 EXHIBITS
Next Planned Update: 19 June 2016 Project Execution Plan
Exhibit B – Approval Sheet
(Refer to Section 4.2 for approval levels)
PROJECT EXECUTION PLAN
BUDGET ITEM NO.
PROJECT TITLE
_____________________________________ _____________
P ROJECT M ANAGER D ATE
P ROJECT M ANAGEMENT D EPARTMENT
_____________________________________ ______________
D EPARTMENT M ANAGER D ATE
P ROJECT M ANAGEMENT D EPARTMENT
_____________________________________ ______________
G ENERAL M ANAGER D ATE
A REA P ROJECT M ANAGEMENT
C ONCUR:
_____________________________________ ______________
D EPARTMENT M ANAGER D ATE
P ROPONENT O RGANIZATION
C ONCUR:
_____________________________________ ______________
V ICE P RESIDENT/E XECUTIVE D IRECTOR D ATE
P ROPONENT O RGANIZATION
A PPROVE:
____________________________________ ________________
V ICE P RESIDENT D ATE
P ROJECT M ANAGEMENT