Reviewer System General Specification for PDP

Ver1.0

YOUNGWON TECH CO., LTD.

www.ywtech.co.kr

119-47 Sasa-Dong, Sangnok-Gu, Ansan-City, Gyeonggi-Do, KOREA

Tel : +82-31-415-6161 Fax : +82-31-415-4321

Project No. YT-06- Spec. No. YWT - REVIEWER – IRICO0601(Ver.1) SUBMIT TO SIGNATURE DATE

PREP’D

CHK’D

CHK’D

APP’D

1. System Summery

1) RIB Review

This system support to operation for decision of bad or good after inspection system check to RIB configuration data on the PDP panel.

With one align camera is composed of the different one review camera and to the equipment which tries 3 ( same axle illumination 1 EA, inclined illumination 2 EA) it has an illumination and the possibility attitude of seeing the defective region in order to be.

Also under interface at it leads with the in-line and it equips automatic goods System.

2) Fluorescence Review

The equipment which it sees the PDP fluorescent chain R which is formed in the petal, G, The B with one Align camera it is composed of different one UV fluorescent lamp Camera with the equipment it will be able to decide a defective particulars in the work own last in order, and the three primary color the possibility attitude of seeing the defective region in order to be.

Also under Interface at it leads with the In-line and it equips a automatic goods system.

2. Basic Spec

1) Glass Size : Max. 2061 X 1164

2) Pass Line : 1,000 mm ( Basic of ground )

3) M/C Size : 3,300(L) X 3,000(W) X 2,000(H)

4) M/C Power : 3 Phase, 220 V, 60A

3. Basic Information

The composition of equipment is composed with 5 Unit a lot.

1) Frame Unit: The unit which arrives safely all Unit. ( Front and back side )

2) Conveyor Unit :The unit which it moves with a different interconnection device together moving to panel for

centering position.

3) Centering Unit : The unit which to centering and moving to panel.

4) Camera Unit : The unit which to centering and moving to panel.

5) X,Y Robot Unit : The unit which to moving for Camera on the X axis and Y axis

3-1 Frame Unit

< ELECTRIC PANEL > < AIR CIRCUIT PANEL >

< BTM FRAME > < TOP FRAME >

Unit : Frame, Air Part, Foot, Top Frame, Tower Lamp, Frame Door, Electric Panel

Skill : All Unit attaches and condition of optimum the Unit.

3-2 Conveyor Unit

Deceleration sensor

IN / OUT sensor

Conveyor Roller

Unit : Pro-File, Shaft, Roller, Drive Motor, Sensor, Magnet Skill : Moving for Panel.

3-3 Centering Unit Centering Robot

Unit : Constitution : Robot, Bracket, Cylinder, LM Guide, Spring, Centering panel Skill : It catches the place which is accurate and it makes under prosecuting attorney conditions of

3-4 Camera Unit (RIB Review)

Align Camera

Inclination Light

Unit : Possible to show the Rib configuration Camera, light, fix Plate and Bracket

Align, Light Source, Light Guide

Skill : After fix to position with Align Camera and illuminate so, find out to particle with Camera

(Review Camera)

3-5 Camera & UV LAMP Unit (Fluorescence Review) Review Camera

Unit : Possible to show the Fluorescent Camera, light, fix Plate and Bracket, Align, Light Source, Light

Guide

Skill : After fix to position with Align Camera and illuminate so, find out to particle with Camera

(Review Camera).

3-6 Gantry Unit Gantry-X Axis

Gantry-Y2 Axis

Gantry-Y1 Axis

Constitution : Linear Motor, Cableveyor

Skill : The unit witch to fix of Camera Sets for the optimum of good inspection.

4. System inspection schedule

1) Mechanical & Electric Elements

Schedule

Check Point Check process and Action Once

A Day

Once

A Week

Once

A Month

Once

3 Month

Once

6 Month

Over

A Year

Note

Measure

Check to level meter

-1M is 0.5mm

Frame

Base

Joint for Bearing

Existence to voiced sound

-Disassembly check

Conveyor Fix of limit switch Fix to bolt

Liner motor

Robot

Action of limit switch Moving to position

Liner motor

Robot

Safety system Check of repeat operation

Liner motor

Robot

Each section fix Check to bolt Etch

Section Belt tension Check to belt tension Conveyor Damage of belt Change to belt Conveyor Heating for motor

Check to temperature

-call to A/S team

Conveyor

Existence voiced to motor Check to sound

-call to A/S team

Conveyor

Isolation of motor

Check to MEGA

- Over to 100

Conveyor

Check to lubricant

Using to AFE Gress

[THK] Etch

Section

2) Electricity

Schedule

Check Point Check process and Action Once

A Day

Once

A Week

Once

A Month

Once

3 Month

Once

6 Month

Over

A Year

Note

Load of summer

relay

Isolation to relay

-Check to return switch

Electronic

Panel

Loose to wire Terminal nut check

Electronic

Panel Electronic circuit

loose

Check to bolt

Electronic

Panel Thin of electronic

Circuit

Check to connector

Electronic

Panel

Noise Filter Front View Earth Front View

3) Pneumatic

Schedule

Check Point

Check process and Action

Once A Day

Once A Week

Once A Month

Once 3 Month

Once 6 Month

Over A Year

Note

Leak to air pipe

Check to join

Pneumatic

Panel

Pressure

Gauge check

-5Kg/cm2

Pneumatic

Panel Control to air

Function check

Each Sector

Check

< Pneumatic >

< Cylinder >

< Cylinder >

5. Inspection

Inspection will be scheduled for a point of time designated by customer and conducted at the production site. 5-1. Interim inspection

1) Main items to inspect : Inspection of materials by dimension according to the specifications and approved drawings made before assembly, specifications and sub-assembly of parts purchased in the market,

confirmation of their makers, consultations about improvements in production, selection of materials and the state of processing.

5-2. Inspection in attendance

1) In-house inspection of the assembled state of equipment will be conducted after the interim inspection and a joint inspection will be carried out based on the inspection results.

5-3. Trial run inspection

1) When the problems and required improvements found in the interim inspection are resolved and complete manufacturing condition is recognized, this inspection will be carried out in accordance with the specifications and approved drawings.

2) Appearance and construction.

3) Overall operating condition.

4) Testing of some items tested by the manufacturer and the product.

6. Warranty

6-1. Warranty of the equipment

1) For 12 months from the final inspection and delivery date.

6-2. Warranty of the facilities

1) Breakdowns caused by the manufacturer’s design fault or production defect occurring within one year the trial run inspection will be repaired by the manufacturer.

2) A checklist on the operating manual will be submitted and adequate checkups for repair will be carried out.

6-3. Free services

1) In case any breakdown occurs during the warranty due to manufacture’s design fault, production defect or faulty installation, replacement of parts or repairing will be provided free of charge.

6-4. Charged services

1) Expendable supplies and a fall in performance caused by natural disasters.

2) Any drop in performance or breakdown caused by negligence of the ordering party.

3) Any drop in performance or breakdown caused by modification or alteration carried out by the ordering party.

7. Submit Documents

7-1. Inspection in attendance

1) Part inspection sheet : 1 copy

7-2. Finish agreement

1) Manual, Finish request sheet, Accepted sheet

2) Operation Manual

3) Maintenance manual : 2 copies on ordinary paper and 1 copy on clean paper of the above documents will be submitted.

8. Layout