施工技术建议书(英)

施工技术建议书(英)
施工技术建议书(英)

技术建议书

一、工程简介

工程位于分布于罗安达省内不同的土地上。建设面积为50000套,共分为T3 30% ,T4 50%,T5 20% 三种户型,总投资63亿美元。工期计划为5年,每年完成10000套房屋。

Construction survey Methods

1.Survey Precision

In accordance with the construction survey regulation issued by Beijing Construction Committee, the Survey precision requirement for construction is 1/15000.

2

Standard Coordinate Checking

Before positioning, in accordance with the construction survey regulation, the standard coordinates and the elevation controlling points must be checked.

3 Establishing Elevation Control Grid

Based on the elevation controlling points provided by the local authority, two temporary benchmarks will be set up for construction.

4

Survey Control For Sub-structrue

According to control grid to be established on site, grid lines will be transferred down with theodolite. Elevation level shall be transferred with leveling instrument. 5

Survey Control For Super-structure

1 )Vertical Transfer Of Grid Line

Grid line will be set out accurately on ground floor slab when structure comes to 0.00 level. Then, based on ground floor, grid lines will be transferred to the upper floors vertically.

2 )Vertical Transfer Of Level

1.00m level line will be set out on the external wall of ground floor accurately. Several places where it is convenient for tape measuring will be selected and marked with red point. Elevation level will then be transferred to upper floor by tape measuring based on the painted marks.

6 Survey Control For Finishing

1) Based on the axes of each floor, the controlling line can be set out

during finishing.

.2 )Based on +1.00m level line of ground floor, +1.00m level line of each

floor will be re-set out.

7 Acceptance Check For Survey Works

After positioning of the project and after structure comes to +0.00 level, we will invite Beijing Survey Institute to carry out acceptance check. Acceptance check of each floor will be carried out by the quality engineers and the supervise company.

8

Survey Instruments and Personnel Requirement

An engineer and two surveyers will be arranged on site. The survey instruments are as follows:

List of measuring instruments

Table 10

ITEM Name Specification Quantit

y

Remark

s

1 Total Station

TSJ-60 South 1

2 theodolite

J-6 1

3 surveyor's level DSC220 1

4 sliding staff- 1

5 Steel tape 50meter 2

6 aluminium alloy level2meter 1

7 vernier caliper

(large)

- 1

8 guiding rule 2meter 2

Concrete Works

The concrete of this construction is mixed at-site, and its strength accords the requirement of the drawings. The cement accords the requirement of the drawings, and the amount mud in medium sand is less than 3%, the diameter of the gravel is 5~25mm and its amount of mud is

less than 1%.

1 Mixing and Transportation of Concrete

During the mixing, control the temperature with the cold water extract from the well and control the amount of added water to reduce the slumps and the crack resulting from the plastic shrinkage.

2 Casting and Vibrating of the Concrete

Before the casting, it is better to lay a 5cm thickness cement motar which have the same ratio with the concrete at the root of the frame structural column. Or chisel the construction joint in order to expose the ballast-surfaced gravels, and then the casted concrete can overlap the previous one better.

When casting the frame structural column, penetrate the vibrating stick to the bottom of the column and vibrate it, then infuse the concrete. It should be done separately on every layer and the thickness of every layer should be less than 60cm. Infuse the material as well as vibrating. Generally, the height of casting should not more than 2m. If the imporosity of the casting can be ensured, it can be casted on every layer.

During the casting, 1 should be appointed to check if there is any deformation or displacement on templates and steel bars, any looseness, falling off or tilting on the buckles and supporter, and fix it on time if there is leakage.

Surface Floating: Compaction and floating should be done with wood float when every part of the concrete on beams, boards and stairs are vibrated. Loose concrete is not allowed on the surface.

3 The maintenance of the Concrete

The concrete should be covered and maintained with water within 12 hours after the casting. Watering twice everyday in normal temperature and the maintance should be more than 7 hours. When the temperature is high, the strength may reduce and the plastic shrinkage may appear without proper maintance, therefore, more work should be done on the maintance.

钢筋工程

1、原材料要求:

凡进场钢筋应有出场质量证明书和试验报告单,每捆钢筋应有标牌,对进场钢筋按规范标准抽样做机械性能试验,合格后方准使用,钢筋在加工过程中如发现脆断;焊接性能不良或机械性能显著不正常时,应进行化学成分检验或其它专项检验。

2、钢筋储存

进场后的钢筋和加工后的钢筋应根据钢筋的牌号直接分批堆放

在由水泥空心砖砖砌成的高30cm,间距2米的垄上,并挂牌表示,不得将钢筋放在凹处或易存水的地方,严禁随意堆放。并随时雨布覆盖,防止雨淋或受潮生锈。

3、钢筋加工

3.1、钢筋加工操作人员要求

操作人员必须持证上岗,并经培训合格。施工时人员要固定,不能随意调换。

3.2、钢筋的调直

钢筋调直应平直,无局部弯折,表面不得有明显擦伤,抗拉强度不得低于设计要求。

3.3、钢筋切断

a、将同规格的钢筋根据不同长度长短搭配,统筹配料,先断长料,后断短料,减少断头,减少损耗.

b﹑断料时避免用短尺量长料,防止量料中产生计量误差,为此

可在工作台上标出尺寸刻度线并设置控制断料尺寸用的挡板.

c﹑在切断过程中,如发现钢筋劈裂,缩头或严重的弯头等,必

须切除

d﹑钢筋的断面不得有马蹄形式的起弯现象.

4、钢筋绑扎

钢筋绑扎前,应检查有无锈蚀现象,除锈之后再运至绑扎部位,绑扎前,先整理、调直下层伸出的搭接筋,并将锈皮水泥浆等污垢清理干净。

4.1柱筋绑扎

柱筋绑扎前在立好的柱子钢筋上用粉笔划出箍筋间距,然后将已套好的箍筋往上移动,由上往下绑扎,箍筋与主筋垂直,箍筋转角与主筋交点均要绑扎,主筋与箍筋的平直部分处的交点成梅花型交错绑扎,箍筋接头应沿柱子竖向间交错布置,柱箍筋端头弯成135度,平直长度不小于10d,柱顶、梁柱交接处,箍筋间距按设计要求加密,柱筋绑扎完毕,随即将塑料卡卡在柱立筋上,间距1m左右,当柱截面尺寸有变化时,柱钢筋收缩位置尺寸要符合设计要求。柱钢筋连接采用电渣压力焊连接,连接质量必须符合要求。

4.2梁筋绑扎

纵向受力钢筋采用多层排列时,两排钢筋间应垫以直径25的短钢筋,以保持其设计间距,箍筋接头应交错布置,在两根架立钢筋上,框架、结点、钢筋穿插十分稠密时,应特别注意梁顶面主筋间净距要有30㎜,以利砼浇筑。梁柱及梁梁交接处箍筋按设计要求加密,

主次梁钢筋,在主筋下垫好垫块。间距1米,梁筋搭接采用电弧焊,搭焊长度应符合设计要求。在有构造柱位置的框架梁底部预埋同构造柱截面相同的预埋板,板厚12mm,预埋板锚固筋为4Ф14,长度250mm。

4.3板筋绑扎

a、板钢筋的绑扎顺序为,先绑扎底部受力钢筋,再绑扎定位钢筋(应有焊接加固措施),然后绑扎板上部负弯距钢筋及温度钢筋。

b、板筋绑扎前,清除干净杂物,在模板上画好主筋分布筋间距,按画好的间距先摆受力筋,后放分布筋、预埋件、电线管等及时配合安装,绑扎除外围两根筋的相交点全部绑扎外,其余交点可隔点绑扎(双向配筋板相交点,须全部绑扎),绑扎完毕,对板的负弯矩筋,每个扣均需要绑扎,在主筋下垫垫块,负筋下垫砂浆垫块。楼板的保护层为15mm厚,1个/㎡,钢筋下料时应注意扣除其保护层的厚度,偏差值在0~3mm范围之内。板筋尽量避免在板上接头,钢筋的接长部位应全部设置在节点处(梁上),其锚固长度必须符合规范的规定。为确保负筋位置,设置φ12钢筋通长马凳,避免负筋在浇筑混凝土时被踩弯。负弯矩筋绑扎后,绑扎分布筋,分布筋必须满绑且通长,分布筋搭接长度为300㎜,端部弯成180O,平直长度10d,绑扎牢固。第一根钢筋距梁边为50㎜。

c、钢筋绑扎完毕应检查下列方面:

①根据图纸查钢筋型号、直径、根数、间距是否正确,特别注意检查负筋位置;

②检查保护层是否符合要求;

③检查钢筋接头位置及搭接长度是否符合规定;

④检查钢筋绑扎是否牢固,有无松动变形现象;

⑤一般项目和保证项目有实测项目的进行实测;

4.4、质量要求

①钢筋的表面应洁净、无损伤、油渍和铁锈等,应在使用前清除干净。带有颗粒或片状老锈的钢筋不得使用。

②钢筋加工允许偏差为:受力钢筋为长度方向全长的净尺寸+10mm。

③安装允许偏差为:受力钢筋排距±5mm,箍筋、横向钢筋间距为绑扎骨架±20mm,受力钢筋保护层:基础±10mm,柱梁±5mm。

4.5、钢筋安装完毕后,应协同监理人员共同验筋,合格后方准进行后序施工。验筋应做隐蔽工程记录,主要检查以下几方面:A.根据设计图纸检查钢筋的钢号、直径、根数、间距是否正确,特别是要注意检查负筋的位置;

B.检查钢筋接头的位置及搭接长度是否符合规定;

C.检查钢筋保护层是否符合要求;

D.检查钢筋绑扎是否牢固,有无松动变形现象;

E.钢筋表面不允许有油渍、漆污和颗粒状(片状)铁锈;

F.安装钢筋时的允许偏差,不得大于规范规定;

G.检查有焊接接头的钢筋是否符合规范要求。

模版工程

1.支模前将构造柱圈梁及板缝处杂物全部清理干净。

2、支模板

1)构造柱模板:

砖混结构的构造柱模板,可采用木模板。可用一般的支模方法,为防止浇筑混凝土时模板鼓胀,影响外墙平整,用木模贴在外墙面上,并每隔1米以内设两根拉条,拉条与内墙拉结,拉条直径不应小于φ20。拉条穿过砖墙的洞要预留,留洞位置要求距地面30cm开始,每隔1米以内留一道,洞的平面位置在构造柱大马牙槎以外一个砖处。

外砖内模结构的组合柱,用角模与大模板连接,在外墙处为防止浇筑混凝土挤胀变形应进行加固处理,模板贴在外墙面上,然后用拉条拉牢。外板内模结构山墙处组合柱,模板采用木模板,用斜撑支牢。根部应留置清扫口。

2)圈梁模板:

圈梁模板可采用木模板上口弹线找平。圈梁模板采用落地支撑时,下面应垫方木,当用木方支撑时下面用木楔楔紧。用钢管支撑时高度调整合适。

钢筋绑扎完以后,模板上口宽度进行校正定位,并用木撑进行校正定位,用铁钉临时固定。

砖混,外砖内模结构的外墙圈梁,用横带扁担穿墙平面位置距墙两端24cm开始留洞,中间每隔50cm左右留一道,每面墙不宜少于5个洞。

3)板底模板:

板底模跨度大于4m时起拱,起拱高度为1/1000,最大起拱高

度不大于30mm,板的长边方向严禁起拱。用木板做底模,宜伸入板底5~10mm留出凹槽,便于拆模后顶棚抹砂浆找平。

板缝模板宜采用木支撑或钢管支撑。4cm以下板缝采用吊关方法。

3、楼梯模板

楼梯底面模板采用15厚木质胶合板模板,侧模采用胶合板,踏步模板采用胶合板。踏步模板与楼梯踏步高度相同,支设方法见图,支设时先支设楼梯平台梁底,待绑扎完钢筋后支设平台梁侧模,然后再支楼梯底模,楼梯底模根据与平台梁成的角度倒角,使角度与所成角相同。

砌筑工程

1、砌筑技术要求

承重隔墙中的构造柱的平面位置及截面除见建筑平面图和结

构楼板平面图外,所有悬墙端部和沿墙长每隔4m均设置构造柱240×墙厚,主筋4×12,构造筋6@200,墙内构造柱必须先砌墙后浇柱,构造柱内主筋上下两端与梁内插筋焊牢,与砖墙连结为每隔两皮砌块设置2φ6,伸入砖墙1000。

内墙采用200厚水泥水泥空心砌块砌筑,每天砌筑高度在1.5m 以内,次日在砌筑上部墙体前,用轻骨料混凝土灌实。灌实的施工工艺是,搅拌塌落度在80mm左右的用水泥、砂粉煤灰、页岩陶粒轻骨料混凝土,其强度为CL5.0,然后清理水泥空心砌块孔洞中的杂物,浇水窨湿砌体,然后灌入混凝土,用钢筋棍反复搅捣,使其密实。

±0.00以下墙体及各个卫生间、淋浴间隔墙距楼地面300mm

以下用混凝土灌实。灌实方法见上条。

砌筑前,应根据砌块高度和灰缝厚度计算皮数,制作皮数杆,并将皮数杆竖立于墙的转角处和交接处。皮数杆间距宜小于15米。

砌块的生产龄期不应小于28天。并清除砌块表面污物和严重的底部毛边。

砌块一般不需要浇水,当天气炎热且干燥时,可以提前喷水湿润。

对于自制的水泥水泥空心砌块,必须遵守反砌原则,每皮砌块应使其底面朝上砌筑。

砌筑应对孔错缝搭砌,个别情况下无法对孔砌筑时,允许错孔砌筑,但搭接长度不应小于90毫米。如果不能满足上述要求时,应再砌块的水平灰缝内设置拉结钢筋或钢筋网片。拉结网筋可以用2根直径6mm的Ⅰ级钢筋;钢筋网片可用直径4mm的钢筋焊接而成。对于需要混凝土灌实的砌体,必须对空砌筑。

水平灰缝应平直,按净面积计算的砂浆饱满度不应低于90%。竖向灰缝应采用加浆方法,使其砂浆饱满,严禁用水冲浆灌缝,不得出现瞎缝、透明缝。竖缝的砂浆饱满度不应该低于80%。水平灰缝厚度和竖向灰缝宽度一般为10mm,最小不小于8mm,最大不超过12mm。.

水泥空心砌块墙的转角处,应隔皮纵、横墙砌块相互搭砌,即隔皮纵、横砌块端面露头

水泥空心砌块墙的转角处和交接处应同时砌起,如不能同时砌

起,则应留置斜槎,斜槎的长度应等于或大于斜槎高度。

本工程在非抗震设防区,除外墙转角处,水泥空心砌块墙的临时间断处可从墙面伸出200mm砌成直槎,并每隔3皮砌块高在水平灰缝设2根直径6mm的拉结筋;拉结筋埋入长度,从留槎处算起,每边均不应小于600mm,钢筋外露部分不得任意弯折。

每层水泥空心砖顶部,当与上部结构梁、板相接时,按设计在结通施第12结点大样的要求实施,即砖墙砌至到顶时按1m间距留出宽120、高300的缺口,将梁或板内预设弯钩拉结筋(拉结筋在绑扎梁或板筋时预留于梁或板内)置于缺口内,然后将缺口用砂浆填实。其中Ф16钢筋在梁板施工时要按要求予留。在墙壁内予埋木砖、预埋件或敷设管道处周围,应分别用水泥空心砖块或现场混凝土砌块砌筑,水泥空心砖不得剔凿,不够整砖尺寸时,用实心水泥砖补砌。

水泥空心砌块表面不得予留或打凿水平沟槽,对设计规定的洞口、管道、沟槽和予埋件,应在砌筑时予留和予埋。

需要在墙上留脚手眼时,可以用辅助规格的单孔砌块砌筑,利用其空洞做脚手眼,墙体完工后用不低于C15的混凝土填实。

墙体中作为施工通道的临时洞口,其侧边离交接处的墙面不应小于600mm,并在顶部设过梁。填砌临时洞口的砌筑砂浆强度等级宜提高一级。

需要移动已经砌好的砌块时,应清除原由砂浆,重新铺砂浆砌筑。

水泥空心砌块墙的下列部位不得留置脚手眼:过梁上部与过梁

成60°角的范围内。宽度小于800mm窗间墙。梁或梁垫下及其左右

各500mm的范围内。门窗洞口两侧200mm和墙体交接处400mm的范围内。

Plastering Works

1 Workmanship process

Surface cleaning watering level controlling point steel wire mesh at the connecting location between two different block wall(100mm long each side) rendering coat surfacing plaster curing

2 Construction key point and quality requirement

At first the cross line shall be made on the floor as the reference line

of plaster work. And then based on such reference line the leveling controlling point shall be made in order to get the straight and smooth wall surface. At the location where different material block interface, the steel wire mesh with 20cm-30cm shall be fixed to avoid the plaster crack due to the future shrinking.

The concrete surface shall be dealt with special measure such as the making rough by use of dashing or adhering painting, and then the plaster thickness and layer shall be confirmed in accordance with the plaster grade to avoid hollow in future. In line to the design requirement, the 1:2.5 cement plaster corner protection with 40mm width in each side shall be made at the window and door opening, and such plaster corner protection shall be meet each other; the same cement plaster corner protection shall be made at each external corner, such corner protection shall be 40mm each side and 2000mm in the height.

The block shall be watered to get the wet surface before plastering. Quality requirement: the type and quality of the material shall comply

with the design requirement and the standard specification of the material. The different layer of the plaster shall be coherence very well to avoid the hollow situation. The cracking and peeling are definitely rejected. The plaster surface shall be smooth and cleaning, racking bond shall be leveling, corner line shall be straight. The joint between the door or window frame and the wall shall be filled tightly. The plaster tolerance shall comply with the related and acceptance code.

九、屋面工程

1、木屋架安装工艺

1)划线、下料。采用样板划线时,对原木杆件,先砍平找正后弹十字线及中心线;将以套好样板上的轴线与杆件上的轴线对准,然后按样板划出长度,齿及齿槽等。

2)节点出的承压面必须平整、严密;榫肩应长出5mm,以

备拼装时修正。

3)上、下弦之间在支座处(非承压面)宜留空隙10mm,

腹杆与上下弦结合处(非承面)也留10mm的空隙;

4)钻螺栓孔的钻头要直,其直径应比螺栓直径大1mm每钻入50-60mm后,需提出钻头,加以清理,眼内不留木渣;在钻孔时,先将所要结合的杆件按正确的位置叠合起来,并加以固定,然后用钻子一气钻透,以提高结合的紧密性;

5)屋架的拼装:在平整的场地上先放好垫木,把下弦杆在垫木上访稳,然后,按照起拱高度将中间垫起,两端固定,再在接头处用加板和螺栓夹紧;下弦拼接后,即安装中柱,两边用临时支撑固

定,再安装上弦杆;最后安装斜腹杆,从桁架中心依次向两端进行,然后各拉杆穿过弦杆,两头加垫板,拧上螺母。各杆件安装完毕,检查合格后,再拧紧螺帽,钉上三角木。

2、彩钢瓦安装工艺

2.1 屋面

1)以山墙边做起点,由左而右(或同右而左)依顺序铺设。

2)第一片板安置完毕后,沿板下缘拉准线,每片依准线安装,随时检查不使发生偏离。

3)铺设面以自攻螺丝,沿每一板肋中心固定于衍条上。

2.2收边

1)屋面(含老虎窗)收边料搭接处,须以铝拉钉固定及止水胶防水。

2)屋面收边平板自攻螺丝头及铝拉钉头,须以止水胶防止。

3)屋脊处及檐口(含老虎窗),须铺塞山型发泡PE封口条。屋脊采用1厚成品彩钢瓦进行封口,用防水自攻螺钉固定。1厚彩钢瓦(成品)屋脊处处理做法专用防水自攻螺钉

4)收边板施工固定方式,依其现场丈量需做变更时,以确认后制做图为准。

2.3固定方法:

1)第一排第一个固定座,以自攻螺丝固定于檩条最左边,然后于檩条弹墨线做基准线,接着固定同排固定座。

2)第一块板之肋部对准固定座之肋板,压下卡入检查是否

扣合正确。

3)将固定座短臂扣上第一块已铺好之面板阴肋,依前述方法施工,并调整平齐。

4)按上述顺序铺设,最后所剩空中楼阁间小于板宽一半时,仅用固港区管理站办公楼屋面维修定座短臂固定板片,其余空间以泛水收头。

5)如最后所剩空间大于板宽一半时,则以固定座固定板片,其超出

部分裁除。

6)安装原则:牢固,不渗漏。安装采用自攻丝固定,间距不大于1000,但应按照瓦楞间距要求安装。自攻丝安装采用专用套筒,套筒安装在手提电钻上钻眼安装。冲孔时要控制牢固,防止划破彩钢瓦面烤漆,及防止冲孔直径过大,过大容易造成漏雨隐患及自攻丝安装不牢自攻丝安装采用彩钢瓦安装专用产品,附带塑胶防水垫圈,安装时孔洞抹玻璃胶防水处理。彩钢瓦搭接应符合规范及防水要求,安装牢固,注意防风防雨。

Doors and Windows engineering

Material, design, installation and test of windows & doors will meet the request of client.

1

Installation Procedure

Setting out the V/H control line Setting out the locating line in the

wall Water plate installation Anticorrosive treatment

Locating and temporary fixing Frame fixing Joint sealing Glass & hardware installation.

2

Quality requirement

1 )The articles and hardware of steel window & door shall comply

with the design requirement and the relevant standard.

2 )The installation location and the mode of O/C shall strictly comply with the design requirement.

3) The installation shall be strong and reliable. The number of anchoring position and the fixing method shall strictly comply with the design requirement and the relevant specifications.

4 )The anticorrosive treatment shall be applied to all the non-stainless steel surface where aluminium frame is connected or contacted. The joint between the alu-frame and the structure shall be correctly filled and sealed according to the design and the acceptance code .

5 )The windtight standard shall be ensured and even outlook connection shall also be obtained.

6 )Complete hardware, right positioning and perfect O/C functioning are essential.

7 )Clean and clear outlook , free of any damage and stain.

Wall and floor tiling

1 Technological process: --Preparation base course -- blinding layer --setting out tiling --curing -- joint filing --- product

--protection --- check and acceptance

2 The construction main point

1 )ase course preparation

Before leveling the base course ,all the rubbish such as concrete debris should be cleaned away .waterproofing layer should be protected during base course preparation.

2)The tiles used in this project shall be carefully selected

and well matched so that it has the same color and texture and the size and the thickness will be the same.

3)Selected tiles are emersed in water before using .

4)Base course levelinAccording to the design standard of floor and

wall ,the leveling coat shall be 1:4 dry cement mortar.

5)The drainage slope is set up in the room with floor drains .

.6)Making level before leveling, the leveling is placed in accordance

with the level .

7)linding shall be in accordance with requirement of the design

drawings

.8 )napping the control lines before setting out .

9 )ling should be made according to the design ,if there is no design requirements for some works , the tiling works shall start from the door to wall side or to tiling the fragmentary in place not remarkable.

Pipeline Works

1 Construction flow processes

Preparation setting out ditch/trough excavation bottom leveling pipeline foundation pipeline placement and joint treatment gully masonry/plaster sand belt backfill manhole and cover

2 Major points of construction

1)Setting-out: setting-out will be rechecked and approved by supervisor and client before work starts.

2 )Pipeline soil excavation: Excavator will be used. According to the site situation, suitable bracing methods will be adopted to prevent ditch wall from collapse.

3) Pipeline foundation: Lean concrete foundation strength will be not less than design required.

4 )Pipeline placement: Straight in placing pipes down into the ditch, bottoms of pipe loaded down will be stable and no reversed slope. Foundation surface free from mud and other matters. Even joint width and treatment as design requirement for special joints. Concrete pipe surround with sand shall be in good density and evenly distributed and compacted along the pipe wall.

.5) Brick gully: Gully foundation will be poured at the same time when pouring pipeline foundation.

.6 )Sand surround: It will be carried out only after pipeline water test. To pipeline without water test requirement, be carried out only after joints are completed.

7 )Backfill: all rubbish are cleared before backfill. Backfill from two sides of embedded pipeline, the difference of height of the two sides will not be more than 30cm.

二 Hydropower Installation Works

( I )Water Supplying System

1、Fabrication

The fabrication of this work is from the underground to the ground. Tubing first and then installation followed. It should be done according to the civil construction.

2、Operating Process

(1)Installation of internal Water Supplying Pipe

Preparation →Prefabrication →main pipe installation→branch pipe and fire hydrant installation→pipeline pressure testing→anticorrosion and heat preservation of pipe→pipe clearing→commissioning

(2)Installation of internal drainage pipe

preparation → prefabrication →main pipe installation →branch pipe and fire hydrant installation→ coupler securing →seal the hole→ commissioning without water→ commissioning with water→ ball passing test

(3)Installation of Sanitary Ware

preparation →test on the sanitary ware and its parts→prefabrication of the sanitary ware→setting out → stabilization of sanitary ware→appearance check→ maintenance→processing on supporter, walls and cracks→commissioning

(II)Electricity System

Fabrication: tubing in cast-in-site board, and then tubing and wiring on the wall, finally, ware erection.

Operating Process

(1)Concealed Piping in the electricity ware

Concealed Piping→prefabrication → setting out the position of the box→ stabilize the box→pipe connecting (casing pipe) →method of Concealed Piping (piping according to the walls and the cast-in-site concrete board)

(2)Tube Wiring

Guide line selection →wiring→setting out→colligation of guide line and →→guide line connection, welding→ colligation of the guide line and steel wire→circuit inspection, insulation inspection

(3)Installation of switch, plug-in and luminaries

Clearing→wiring→light ware installation→commissioning

(III)、Method of Construction

(1)Installation of Water Supplying Pipe

Before the commencement, the reservation of the pipe hole should be done according to the drawings and elevation.

According to the principle of indoor first, the inlet pipe should be erected indoor first and stretch out of the wall for 1000~1500mm, and the outdoor erection and

connecting should be done before the completion.

②During the pipe laying, the backfilling layer should be compacted every layer, and there should be no hard rock with diameter ≥10mm on the surface of the backfilling.

③Pipeline erection: secure and support with steel bar, work according to the regulation in the construction.

④The water supplying branch pipe of this project should be installed concealed. And pisition those according to the horizontal coordinate and elevation of the water point of every sanitary ware.

⑤After the construction is finished, temporary end cap should be used as temporary sealing.

⑥After the erection meets the regulation, water pressure test should be done. All concealed work record should be done after it is qualified, then the next fabrication can be taken.

(2)Erection of the indoor drainage pipe

The plastic pipe and socket connector as the drainage pipe of this project. Set the bracing and checkpoint according to the design and requirement, and the method is the same as the water supplying pipe. However, during the material supply of the branch pipe, the length shall measured one by one, instead of one for all. The end cap form should be a three-ply board of 300x300.

(3)Erection of the Sanitary Ware

The sanitary ware should e smooth without hard spot, the color should be consistent and there is no breakage.

Preparation: the pressure and shutting water test of the pipe connected with the sanitary ware.

Putting the sanitary in place: the squatting pan should be put in place when mason the stairs, and level it with the leveling instrument. Then seal the outlet with the stopper and secure the inlet leather with the finished hose clamps.

③The installation of the delayed auto-switch washing valve: the height of the washing valve is 1.1m. Make a 90°bend washing pipe according to the distance between washing valve and leather to fit the both end. Demolish the lock net and the rubber ring of the washing valve, and install them on the straight section of the washing pipe separately. Penetrate the bottom of the bend pipe to the leather 40~50mm deep and secure it with hose clamps, and penetrate the upper part to the washing valve, push up the rubber ring, adjusting and centering, screw the lock net to

VMware技术方案建议书(doc 28页)

VMware技术方案建议书 xxx系统服务器整合

2006年X月 目录

1服务器虚拟技术剖析 1.1 VMWARE解决方案 1.1.1 VMware 服务器整合解决方案 随着企业的成长,IT部门必须快速地提升运算能力-以不同操作环境的新服务器形式而存在。因此而产生的服务器数量激增则需要大量的资金和人力去运作,管理和升级。 IT部门需要: ?提升系统维护的效率 ?快速部署新的系统来满足商业运行的需要 ?找到减少相关资产,人力和运作成本的方法 VMWARE服务器整合为这些挑战提供了解决方案 虚拟构架提供前所未有的负载隔离,为所有系统运算和I/O设计的微型资源控制。虚拟构架完美地结合现有的管理软件并在共享存储(SAN)上改进投资回报率。通过把物理系统整合到有VMWARE虚拟构架的数据中心上去,企业体验到: ?更少的硬件和维护费用 ?空闲系统资源的整合 ?提升系统的运作效率 ?性价比高,持续的产品环境 整合IT基础服务器

运行IT基础应用的服务器大多数是Intel构架的服务器 这一类的应用通常表现为文件和打印服务器,活动目录,网页服务器,防火墙,NAT/DHCP服务器等。 虽然大多数服务器系统资源的利用率在10%-15%,但是构架,安全和兼容性方面的问题导致必须指定不同的物理平台来运行它们。 管理,安装补丁和添加安全策略将花去大量的时间。另外,服务器的衍生组件将导致设备,动力和散热方面的成本上升。 因为低服务器的利用率,低CPU的合并和中等I/O的要求,IT基础服务器首选作为虚拟化和相关整合的候选者 虚拟化使得企业能实现: ?达到甚至超过每个CPU,4个负载的整合比率 ?更便宜的硬件和运作成本 ?在服务器管理方面的重大改进,包含添加,移动,变更,预制和重置 ?基础应用将变得更强壮和灾难抵御能力 整合重要应用服务器 根据5个不同的企业使用服务器软件来大幅降低成本的实例,VMWARE出具了一份研究报告。 使用服务器TCO模型来分类和计算成本,我们分析显示VMWARE服务器软件帮助这些企业实现: ?减少28%-53%的硬件成本 ?减少72%-79%的运作成本 ?减少29%-64%的综合成本 客户目标 ?整合空闲服务器和存储资源,为新项目重新部署这些资源 ?提升运作效率 ?改进服务器的管理灵活性 ?通过零当机维护改善服务等级 ?标准化环境和改进安全 ?灾难状态下,减少恢复时间 ?更少冗余的情况下,确保高可用性 ?更有效的适应动态商业的需求 ?高级备份策略 ?在技术支持和培训方面降低成本

人工挖孔桩施工技术方案建议书

人工挖孔桩施工技术方案建议书

目录1、编制范围、依据及原则 2、工程概况 3、工料机配置 4、施工进度计划 5、施工技术方案 6、质量保证措施 7、安全、环保措施 8、文明施工措施

郧十高速公路YSTJ-5合同段桩基 施工技术方案 1、编制范围、依据及原则 郧十高速公路YSTJ-5合同段桥梁工程桩基施工技术方案编制范围:郧十高速5标所有9座桥梁桩基础施工工程以及为实施以上工程必须的临时工程。 《湖北省郧县(鄂豫省界)至十堰高速公路一期土建工程施工招标文件项目专用本》--2011年5月; 《湖北省郧县(鄂豫省界)至十堰高速公路两阶段施工图设计第三册、工程地质勘查报告》--2011年6月; 《湖北郧十高速公路施工工艺标准化管理实施细则》--2011年5月; 国家、行业相关标准。 (鄂豫省界)至十堰高速公路一期土建工程施工招标文件要求,施工涵盖技术文件所规定的全部技术内容。 、可靠的工艺、材料、设备、达到技术先进,力求工艺成熟,具有可操作性。 (鄂豫省界)至十堰高速公路两阶段施工图设计成果,结合桥址的地质、水文、气象条件及工程规模、技术特点、工期要求、工程造价等多

方面比选来确定。 。 、合理有效的资源组织,力求缩短工期,为桥梁的施工提供有力保障。 、施工安全问题。 2、工程概况 线路区内属北亚热带大陆性季风气候,具有四季分明、立体气候明显、光照充足、降水集中等特点。夏长冬短,春秋相近,平均气温在10℃~16℃之间,℃,℃,年平均日照数位1928小时,日照率为44%,平均年降雨量800~950mm。 地表水不发育,无常年地表流水,主要为雨季时形成的地表面流;地下水主要赋存于基岩中的裂隙水,富水性若,水量贫乏,主要接受大气降水入渗补给,水文地质条件属简单类型。 桥址区地貌单元属构造剥蚀低山-丘陵地貌,地形起伏较大。山坡自然坡度较陡,植被较发育,多为乔木及小灌木;桥址区有G209国道公路,与拟建高速公路有交叉分布,交通较为方便。 桥址区大地构造属于昆仑-秦岭维向构造体系东秦岭南亚带,该构造体系是区内发展最早的构造体系,为区内主要构造格架,其他后期构造在才构造之上叠加、穿切、横跨,构造形态复杂,褶皱发育,断裂交织,具

浅谈工程技术管理存在问题与解决措施

浅谈工程技术管理存在问题与解决措施 发表时间:2018-06-15T09:34:37.077Z 来源:《基层建设》2018年第7期作者:李焕[导读] 摘要:近年来,我国建筑行业逐渐发展起来,极大的满足了人们对建筑的需求。 广州市方阵路桥工程技术有限公司 525300 摘要:近年来,我国建筑行业逐渐发展起来,极大的满足了人们对建筑的需求。在建筑工程施工建设中,不能缺少技术的运用,它是提升工程质量,促进企业发展的重要基础,然而,现阶段不少建筑工程在技术管理中还存在各种各样的问题,因此,本文将从建筑工程中做好技术管理的意义入手,联系建筑工程技术管理中存在的问题,并提出做好技术管理的对策。 关键词:建筑工程;技术管理;问题;对策引言:建筑工程当中的技术管理是重要内容,这也是促进工程施工质量的保障,通过技术管理的科学方法应用,对建筑工程企业的市场竞争力提升也有着积极意义。技术管理对工程施工所产生的影响也比较突出,在面对当前建筑工程行业发展的环境下,就要从多方面对技术管理的加强充分重视,保障技术管理水平提高。 1、建筑工程技术管理的重要性 1.1 提高企业的综合实力 随着中国建筑市场的连续发展,许多建筑企业不断成立起来并且希望从中得到巨大的利益。由于多数的建筑企业太过于重视建筑的数量从而忽略了建筑的质量,导致建筑市场处于一片混乱,进而造成建筑企业效益的不断降低。因此建筑质量的高低对企业市场具有重要的作用。技术管理是贯穿整个建筑工程中的重要的管理工作,管理水平的加强不仅仅对提高建筑的质量具有一定的帮助,还可以提高建筑企业的经济效益及其综合实力,促进它在建筑市场中持续发展。 1.2 提高建筑工程施工的质量 若想建筑工程施工顺利的进行,就必需不断提高其技术管理工作。既要确保建筑材料和相关设备质量及其充足性,也需要保证建筑管理制度的完善性。另外,还要在确定工期后调整好分包单位的建筑工程项目有顺序的连接关系工作面的流水施工。因此务必要使参加工程施工的全体员工全面了解建筑工程质量并提高其重视程度,提高施工水平。 2、建筑工程技术管理中存在的问题 2.1 建筑工程技术管理意识薄弱 当前,我国建筑行业同整体经济发展都面临着快速发展的时期,建筑工程项目管理在其中发挥的作用、承担的责任也越来越大。由于我国建筑行业发展历程还比较短,发展速度比较快,行业发展规模大,但科学创新性还没有充分的融入到各个项目建设过程中,建筑行业相关技术管理者对此还未提起足够多的重视,项目技术管理意识薄弱,或者管理水平还不足以适应行业发展的需求。 2.2 建筑工程技术管理工作不规范 工程建设是一项关系重大、要求严格的项目,一方面,要求管理者有全局意识,考虑到各个方面;另一方面,管理施工中的规范需要严格按照要求落实。但是,在具体实施中又会出现各种问题。如管理者为了私利,出现施工中偷工减料等情况。同时,管理人员缺乏技术管理能力、经验不足或对建筑施工中用到的材料、技术不了解,造成组织施工过程中常常心有余而力不足,行业施工中违反相关政策规范的行为层出不穷,建筑资源使用效率不高,工程质量难以保障。 2.3 建筑工程技术管理技术水平不高 就当前的形式来看,为了达到利益最大化的目的,建筑公司竭尽所能的降低成本,这就会形成一人饰演多个角色的场面,一些高技术的人才因公司节约成本的原则,不得不担当一些技术管理方面的岗位,这就导致其注意力分散开来,不能只关注和解决技术方面的问题,还要注意技术管理方面的问题,但一个人的精力就这些,最终就会导致技术上没有搞好,技术管理上也由于不是专业的技术管理人才缺乏管理经验导致管理方面的不到位、不合理。除此之外,建筑公司为节约成本还有可能招聘一些技术水平不高的人来担当管理岗位,这也对建筑工程技术管理造成一定的负面作用。 2.4 建筑工程技术管理措施落实不到位 随着我国建筑行业的发展逐渐步入正轨,规范行业发展的政策措施从行业实践中逐渐形成。然而,由于相关技术管理者的利益或完工进度的考量,原本高质量的技术管理要求也大打折扣,而且建筑行业对于大数据的应用还比较落后,相关管理数据的保管以及信息系统的建立也有一定的困难。所以,技术管理无法落到实践当中。 2.5 建筑施工管理的监管不到位 如果在建筑施工过程中存在着监管空白点,这很容易影响建筑工程的施工。一旦存在拖延施工时间的情况,就会延长了建筑工程的正常进行速度,如果要在规定时间内要完成建筑工程,建筑工程的施工质量的必然会有损。如果说建筑施工的工作人员没有专业的知识,对于一些新兴的专业技术根本无法理解并且应用,这就会影响施工的技术,最终导致建筑工程的建筑质量出现缺陷。同时在建筑工程的施工过程中由于存在这监管空白点,也会影响建筑施工过程中使用的建筑材料的监督管理。 3、建筑工程技术管理问题的优化解决措施 针对建筑工程技术管理中存在的问题,建设企业和相关监管部门要予以重视,要不断加强对施工技术管理的研究,在实际技术管理工作中找出问题出现的原因,并通过对原因的分析来找到解决技术管理问题的措施,要加强对技术管理人员的培训和教育、激励员工工作、构建科学可行的技术管理制度并对施工进行全方位的技术管理,以此来提高建筑工程施工技术管理的效率和质量。这样才能提高建筑工程的建设质量和水平。 3.1 加强技术管理人员的技术管理水平 技术管理的核心就是人才管理。其改善的手段有以下几点:①预订相关高校的应届毕业人才。高校毕业生虽不具备实际管理经验,却拥有相对较高的专业素质以及理论知识。②在企业的内部成立人才的培训部门。在企业应聘的技术管理人员中,其拥有一定的水平但还远远达不到要求,而且一部分应聘人员的素质也需要提升。③企业要对招聘标准要进行提升。对应聘的人员以及晋升管理阶层的人员要进行相对严格的考验。 3.2完善建筑工程技术管理制度

建筑工作方法施工图设计优化方案

建筑工作方法施工图设 计优化方案 文件排版存档编号:[UYTR-OUPT28-KBNTL98-UYNN208]

工作方法: 配合报规的组织安排以及工期计划: 为保证工程设计按进度完成并确保设计质量,我们安排工作经验丰富、专业素质较高的设计人员组成设计团队, 从项目开始即日起,我们要求各专业设计者利用这段时间与建设单位进行及时的沟通、了解,到现场勘查场地现状,作好充分的前期准备,设计最优方案。 规划方案报审阶段: 在确定我方设计后与建设单位的相关负责人进一步进行沟通,充分了解建筑方案的设计意向,组织各专业设计人员详细勘察现场,了解现状,尽可能详细的收集相关资料,以便对建筑方案进一步加深理解。 项目负责人组织各专业对建筑方案仔细讨论研究,从施工图角度对建筑方案提出合理化建议。 根据以上我们掌握的信息,我方对方案提出合理化建议,针对此些建议有建设单位组织与方案设计方进行方案讨论。 与方案设计方沟通完成后,及时配合建设单位以及方案设计单位进行方案深化工作,包括日照分析等,我方具有资质以及较专业的日照分析人员。 方案设计单位的方案完成后,将以我院的资质进行报规,充分利用我方对当地规划局的要求较熟悉,与规划部门及时沟通,尽快完成规划审批。 施工图设计进度安排: 进入施工图阶段我院会立即组织项目组的各专业人员对建筑方案进行深入的研究,与建设方进行施工图前的沟通讨论:项目负责人把整个项目的所有资料认真的浏览一遍,保证在进入施工图设计阶段时前期资料的完整。认真阅读甲方提

供的设计任务书,把所有资料传给各专业负责人,各专业负责人认真查看项目资料,做好施工图设计前期的准备工作。 项目负责人和各专业总工组织讨论,与建设方交流,根据初步设计审查意见进行技术问题讨论,特别是精细化设计讨论,确定优化技术措施,以便更好的节省造价。 各专业反提设计条件给建筑专业,提供之前应由专业负责人审核。结构专业需提供柱子、梁等截面,设备电气专业需提供相关设备用房及井道、集水坑的准确地位尺寸,人防需要多大面积、人防口部的设置等设计条件给建筑专业。 施工图设计工作完成,首先组织设计人员自校,修正设计中出现的不合理之处,项目负责人在此过程中定时组织各专业设计人员交流讨论保持与建设方的密切交流,认真听取建设方的合理意见,并作出及时反馈;设计院管理人员督促设计人员按时保质进行施工图的设计工作。 项目负责人组织各专业总工对施工图图纸和各专业计算书进行校对、审核工作和并修改图纸,各专业完成会签。 所有图纸提交总工办进行图纸审定,确认无误后,加盖注册师章后交由资料室负责晒图盖章,然后将图纸提交甲方。 密切关注项目施工进度,对建设方提出的变更,进行讨论后,及时提出处理方案及变更图纸,保证项目施工的顺利进行。 项目竣工后,组织设计人员进行验收,并虚心听取建设方和施工单位提出的建议和批评,公司内部组织设计人员进行项目总结,对项目的全过程进行评价,总结优点和不足,并进入公司存档系统。 在工程的施工过程中,提供7×24小时的服务,及时做好后期的施工现场服务工作,包括施工图设计交底;设计人员与施工人员的图纸会审;及时处理施工现场所遇到的各种问题,保证施工顺利进行。如果工程需要,我公司有关人员将

微信服务平台技术方案建议书

上海银行客服平台2.0项目微 信服务系统 项 目 建 议 书 深圳市云软信息技术有限公司 二〇一三年九月

目录 术语定义 7 第1章概述 (9) 1.1项目背景 (9) 1.2现状分析 (9) 1.3建设目标 (10) 1.4公司简介 (11) 第2章业务需求分析 (12) 2.1总体需求描述 (12) 2.2角色分析 (12) 2.2.1系统管理员 (12) 2.2.2运营管理员 (13) 2.2.3运营分析员 (13) 2.2.4营销管理员 (14) 2.2.5客服坐席 (14) 2.2.6质检坐席 (14) 2.2.7客服班长坐席 (15) 2.2.8留言处理 (15) 第3章平台架构设计 (16) 3.1设计原则 (16) 3.2总体架构设计 (18) 3.2.1逻辑架构 (20) 3.2.2部署架构 (21) 3.2.3系统技术介绍 (23) 3.3平台接口设计 (26) 3.3.1接口设计原则 (26) 第4章系统功能设计 (28) 4.1多渠道接入 (28) 4.2微信子系统 (28) 4.2.1用户绑定和解除绑定 (28) 4.2.2信用卡业务查询 (32) 4.2.3信息推送 (39) 4.2.4交易功能 (42)

4.3消息处理子系统 (65) 4.3.1渠道适配模块 (66) 4.3.2多技能路由策略 (69) 4.3.3坐席接入模块 (71) 4.3.4客服机器人 (77) 4.3.5微信系统消息格式处理模块 (80) 4.3.6业务功能 (81) 4.4客服子系统 (85) 4.4.1系统设计 (86) 4.4.2业务功能 (87) 4.4.3客服管理 (91) 4.5运营管理子系统 (92) 4.5.1系统设计 (92) 4.5.2营销模块 (93) 4.5.3留言管理 (100) 4.5.4可视化导航配置 (102) 4.5.5组织机构管理 (107) 4.5.6业务参数配置 (107) 4.5.7质检管理 (108) 4.5.8系统管理 (109) 4.5.9其他功能 (111) 4.6报表子系统 (112) 4.6.1运营报表 (112) 4.7外部接口子系统 (117) 4.7.1概述 (117) 4.7.2外部接口 (120) 4.7.3系统接口 (120) 4.8软件功能清单 (123) 第5章设备配置方案 (145) 5.1刀片服务器列表 (145) 5.2第三方软件 (146) 第6章工程实施方案 (147) 6.1概述 (147) 6.2项目人员组织 (147)

工程项目建议书模板

(项目名称) 项目建议书 (建设单位或设计单位名称) 年月日

说明 1、项目建议书一般由承建项目单位编写,也可委托设计单位或技术依托单位编写。 2、本格式为一般要求,大型项目、特种行业有些内容需进一步补充;小项目也可简化。 3、此格式为重庆青尘节能环保科技有限公司根据本公司情况编制。 4、未有标记的标目必须按要求编写,作※标记的可以简化或不写,有Δ符号的可以简化,但要有基本内容。

目录 一、项目名称 (4) 二、项目概况与项目背景 (4) ※三、项目建设的必要性和有利条件 (4) 四、市场分析与建设规模 (4) 五、主要建设条件 (4) 六、总体布置与主要技术方案 (4) 七、环境及安全影响分析 (5) ※八、节约使用能源 (5) 九、企业组织与人员组织 (5) 十、项目实施进度计划 (6) 十一、投资估算与资金筹措 (6) Δ十二、财务效益预测 (7)

一、项目名称 二、项目概况与项目背景 1、公司概况 2、项目背景 ※三、项目建设的必要性和有利条件 1、项目建设的必要性和有利条件。 2、适应国内外市场需求。 3、符合国家产业政策和投资方向。 4、符合地方计划发展规划。 5、有利企业自身发展。 6、具有良好的建设条件。 四、市场分析与建设规模 五、主要建设条件 1、建设选址(占地面积) 2、交通运输(交通状况,月货物、原料材料吞吐量等) 3、原料供应(资源优势)或配备件来源。 4、供电(电压等级、设备装机功率、用电要求) 5、给排水(生产、生活用水量/日、对水质要求、排水方式、排水污染状况及排水要求) 六、总体布置与主要技术方案 1、总体布置

浅析建筑工程施工技术管理

浅析建筑工程施工技术管理 摘要:建筑工程是指关乎居民生产生活的城市基础设施建设,与社会生产、人们生活密切相关。本文对如何通过科学先进合理的施工技术管理,为施工企业的发展提供良好的基础保障做简要阐述。关键字:建筑工程;技术;管理 abstract: the construction work is the urban infrastructure and social production related to residents’ production and living of, it is closely related to people’s lives. this paper described how to provide a good protection basis for construction enterprises through scientifically advanced and reasonable construction technology management.key words: construction; technology; management 中图分类号:tu71文献标识码: a 文章编号: 随着我国社会经济的不断飞速发展,人们对于建筑物的使用功能、工程质量等要求越来越高。要想建筑物具有优良的质量,就需要有好的施工技术管理,施工技术管理是建筑工程生存和发展的基础性资源,在常见的施工工程中技术管理是人们不容忽视的重点。施工技术管理是指确保施工质量和企业经济效益的、科学的、技术管理工作。技术工作贯穿于生产的各个环节,和各管理部门有密切的关系。由于长期以来建筑行业“一哄而上”的格局,引起国内市场的无序竞争,建筑施工企业之间的市场争夺战异常剧烈,加强建筑工

技术建议书

五、技术建议书 (1)对招标项目的理解和总体设计思路; 本项目为柘城县产业集聚区丹阳大道景观设计项目,其中丹阳景观带长1600米,总宽度150米。其中路面宽度50米(含人行道);景观带100米, 路东侧绿化带宽度80米(含丹阳渠,渠面控制宽度26-33米不等,坡度比例1:3),路西侧绿化带宽度20米。丹阳湖景区共占地280亩,其中湖面占地110亩,绿地占地170亩。 经过初步勘察,本项目作为城市产业集聚区的大型绿地,总体设计思路 是因地制宜的创造柘城县产业集聚区的生态景观,将丹阳大道打造为生态丰富、功能多样、独具地方特色的景观大道,同时结合当地实际情况,进行合理设计为本地区打造生态基底,维持生态平衡,改善城市环境。 (2)对招标项目设计的特点、关键性技术问题的认识及其对策措施; 本设计项目作为城市景观的重要部分,具有景观丰富,场地面积大,服务人群多等特点,本项目基本包含以下方面:道路景观、河道景观、人工湖、硬质铺装、苗木种植、景观小品、园林用电、照明、园林给排水等。 关键性技术为水景的处理,主要包括1600m长的丹阳渠,以及占地面积110亩的丹阳湖,针对水景我方主要对策以及安排如下: 1、根据现状条件进行合理布局,因地制宜的设置湖面,并在湖面周 围设置土山,打造山水景观并且做到土方基本平衡。 2、在湖面以及水路交界处着重打造湿地景观,创造良好的景观效果 的同时最大限度的发挥生态功能。 3、丹阳渠的处理上尽量做到自然式、不规则的界面,创造丰富多变 的景观。

4、在水源保持上,深挖丹阳湖,涵养水源,尽量做到以丹阳湖为水源地,形成水系循环,供应丹阳渠水景。 5、水景结合自然山石、滨水植物、园林小品等景观要素做到和谐统一,形成特色鲜明的滨水景观带。 (3)设计工作量及计划安排; 本项目主要包括方案设计(含估算)、初步设计(含概算)、施工图设计(含预算、工程量清单及组价)、设计变更等各阶段设计服务及后续阶段的施工现场服务等,我方计划一旦中标马上着手进行详细的现场勘查,着手进行场地分析,结合实际提出合理性方案,进入方案设计阶段,通过多方案比选确定最优方案,同时进行设计估算。 方案设计计划完成时间15天。 完成实际方案后经过与甲方进行沟通,进入初步设计阶段,通过交流调整,不断完善本设计方案,同时出效果图、表现图等,经过分析、研究最终确认初步设计方案,同时确定设计概算。 初步设计计划完成时间20天。 初步设计确定后进行施工图设计,进行园林、建筑、结构、给排水、电气等各个专业的分析综合研究,完成施工图,同时出施工图预算以及工程量清单。 施工图设计计划完成时间35天,总计设计周期为70天。 (4)后续服务的安排及保证措施; 我院承诺后续提供以下服务:

施工组织设计建议书 (1)

第一章总体供货的组织实施方案 若我公司中标,即按照本投标文件中的承诺,派遣强有力的领导班子,组建材料物资供应部。并由材料部长率领由各部门负责人、仓库负责人及部分劳动力组成的先遣队,迅速完成承包人驻地建设及贵阳供货临时设施布设,尽早全面展开供货。公司材料部挂牌办公,代表公司全面履行合同。 一、项目管理机构 根据本项目具体情况,结合我司供货经验,项目材料部设材料部长、技术负责人,下按“四部一室”(材料技术部、质安部、物资设备部、计财部、综合办公室)的编制设置。实行材料部长负责制,并按项目法实行统一组织、统一管理、统一协调,做到精心组织、科学管理、合理安排,确保本工程安全、质量、工期、环保及文明供货等各项目标的实现。 二、仓库临建 1、仓库建设 BDBXLCG合同段材料部及供货临时仓库营地设置在贵阳市白云区招标人指定地点,租用民房并完善办公、生产生活设施,仓库营地内设波形梁板及立柱区、波形梁配件存放区。 2、施工用水 本工程所在区域水系较发达,施工驻地内生产、生活用水分开设蓄水池,自附近居民用水点接入,施工现场用水采用水车供应。 3、施工用电 公路沿线电资源丰富,用电与地方电力部门协商接入,并自备350kw发电机组确保施工用电连续性,施工现场用电采用自发电。 4、通讯联络 当地通信条件较完善,所有人员配备移动电话,项目经理部配备固定电话一部,传真机一部,电脑1台并接入因特网。 三、施工任务划分及机械设备、劳动力配置 根据本合同段具体工程量及工期要求,拟设1个波形梁钢护栏专业施工队、1个标志标牌专业施工队、1个热熔标线专业施工队、1个后勤队及1个交通安全维护巡查组,分别承担本合同段的施工任务及交通安全畅通维护。因施工工期

浅谈建筑工程施工技术管理(标准版)

Enhance the initiative and predictability of work safety, take precautions, and comprehensively solve the problems of work safety. (安全管理) 单位:___________________ 姓名:___________________ 日期:___________________ 浅谈建筑工程施工技术管理(标 准版)

浅谈建筑工程施工技术管理(标准版)导语:根据时代发展的要求,转变观念,开拓创新,统筹规划,增强对安全生产工作的主动性和预见性,做到未雨绸缪,综合解决安全生产问题。文档可用作电子存档或实体印刷,使用时请详细阅读条款。 摘要:随着近几年房地产开发的规模越来越大,建筑市场的竞争也比以前激烈了很多,建筑工程施工管理作为能够有效地提升建筑质量、工作效率的手段,此外,它还可以有效地降低企业的成本,其重要性越来越凸显,但是建筑工程的施工管理是一个复杂的工程,其包括数个阶段,各个阶段又互有联系,因此,研究如何能够高效的做到建筑工程施工管理既有学术意义,又有现实的指导意义。 关键词:建筑工程;施工技术管理 0、引言 房地产的迅速发展也带来了建筑市场的空前发展,伴随着建筑行业快速发展的是空前激烈的竞争,各大建筑公司都在纷纷寻找提升自身竞争力的途径,建筑工程施工技术管理能够有效地提升建筑质量、工作效率,又可以有效地降低企业的成本,目前已经被各大建筑公司采用,并取得了一定的经验及成效。 1、建筑工程施工技术管理的原则

(1)经济效益原则 对于各大建筑公司而言,控制成本是提升竞争力的有效手段,尤其对于中国目前的国情而言,有效地降低施工成本几乎是企业成功的关键,建筑工程施工技术管理首要原则应该是经济效益原则,这一原则主要是指企业需要克服以往的只关注进度及质量的管理原则,应该更多的在降低成本,开拓市场上做出新的工作,在施工过程中提升生产资料的使用效率,量入为出,防止不合理的浪费。 (2)科学合理原则 科学技术是第一生产力,这一点在建筑工程施工技术管理中依旧体现的很明显,施工中要努力做到以科学的原则开展工作,即做到管理的科学化,使其符合现代化的可观需求,在施工中,这一点主要体现在方法和流程的科学化上,合理科学的方法能够有效地完成经济效益的原则,使其物尽所用,而合理的流程则会带来更高的工作效率。 (3)标准化规范化原则 这一原则是施工技术管理的基本原则,只有标准化规范原则的彻底落实,才能够够有效地开展基于这一原则的工作,在施工中,这一原则体现为应摆脱主观性,无论大事小事都要有标准,并以标准作为衡量其工作质量效率的方式,这对于科学合理原则是一个很大的促进。

施工技术规范方案最终版

广东铁塔公司2015年第一批新建及改造站点工程项目施工 技术标准和要求 一基站配套部分 二土建装修部分 三其他说明 一基站配套部分 1.施工要求 1.1施工准则 1.1.1施工单位必须严格按照批准后施工图设计进行施工。 1.1.2施工单位接到任务书,应制订详细的施工方案、计划和进度,保证按时完成任务。1.1.3施工单位接到施工图后,应组织相关的施工人员、讲解本次施工的要点、要求和注意事项,使施工人员明确施工的性质、内容和任务。更好的,按期、按质、按量完成施工任务。 1.1.4施工单位必须遵守国家或部委颁发的法规、标准和规范。 1.1.5施工单位必须严格执行国家或部委颁发的工程施工及验收技术规范或工程及验收暂行技术规定,以及中国铁塔公司的有关文件规定和要求。 1.1.6施工质量应以施工质量第一位宗旨,施工单位必须加强施工现场的管理和施工监督,严格执行施工规范。做到施工工艺精良,各种测试项目齐全、记录清楚、文字端正、数据准确。符合相关技术要求。 1.1.7施工单位必须严格按施工操作程序施工,做到文明施工、文明生产。施工中应做好防

火、防电、防雷、防化学气体、防事故等预防性的工作,做到施工人员的安全及设备材料的安全。 1.1.8施工完毕,各项测试指标合格,需对电路进行割接时、施工单位应制订出详细的割接方案、步骤和方法报建设单位和主管单位批准后进行割接并保证做到万无一失。 1.2施工工艺要求和测试要求 1.2.1设备安装 设备机架安装应按施工图平面设计位置安装。机架安装要求垂直、牢固、安装位置正确、方向一致,符合原邮电部及信息部通信设备安装抗震加固或设计文件抗震加固要求。新旧设备内的各种插件应按设计文件进行插接,不能插错,插接位置正确、牢固、不松动。 1.2.2槽道或走线梯的安装 槽道或走线梯安装位置应符合施工图的设计要求,与设计高度或原有槽道高度、水平一致,吊挂要垂直,安装位置正确,各种连接件、紧固件安装牢固符合抗震加固要求。 1.2.3音频线的布放 1.2.3.1 音频线的布放应按施工图设计指引的路由和方向布放,在水平和垂直的位置,电缆布放要平直不弯曲,绑扎要整齐、松紧要适度,转弯的地方要弯位适当、整齐、美观。 1.2.3.2 MDF架端的音频电缆制作。电缆在MDF架上排列应整齐,出线及预留长度应一致,卡接或绕接端子芯线应牢固,接触良好,不留尾巴。 1.2.4射频电缆布放及制作 1.2.4.1射频电缆应按施工图设计的路由布放,布放要顺直,转弯要符合相关规定。绑扎要松紧适度并符合设计要求。 1.2.4.2射频电缆余留长度应统一,同轴电缆各层的剥开尺寸应与电缆插头相应部分相适合。 1.2.4.3芯线焊接要端正、牢固,焊锡适量,焊点圆滑、不带尖、不成瘤形,组装同轴电缆

对施工图设计的几点建议

对施工图设计的几点建议 1.部分隧道口征地不足,无法按设计进行仰坡施工,无法设置坡顶截水沟,如:k42+920-k44+980处劝家山隧道出口。 2.临县枢纽CKO+578分离式立交( 28+40+28)、DKO+644分离式立交【5*25+4*30+(30+4*40+30)】匝道上跨太佳高速的两座匝道桥,离石枢纽IKO+530.5跨线桥【2*30+(40+56+40)+2*30】、HK1+125.4跨线立交桥(1*40)匝道上跨离军高速的两座匝道桥,主跨建议变为钢箱梁。 3.离石互通枢纽,部分现浇桥梁高度达20—35m之多,地形起伏又较大,采用支架浇筑成本高、工期长、安全风险大,建议改为小跨径预制梁桥。 4.部分涵洞的设置孔径过小,不能满足当地生产生活需要。如:k38+537.5处1-2m拱涵,建议改为4m拱涵。 5.设计上一些标段存在把隧道内开挖的土石方作路基填筑使用。由于每日开挖量太少,加之工期过紧,实际情况是隧道弃渣极少利用。建议按实际情况进行土石方调配。比如:米化梁隧道出口与大中局隧道入口之间的填方段(k51+488-k51+600)设计为利用隧道弃渣填筑。 6.设计上一些标段土石方利用存在跨桥、跨隧调用,有的标段甚至要跨越多座(道)桥隧进行调配。由于桥梁隧道是一个标段的制约性工程,工程都很长,不可能在桥隧完成后再行调配;如果长距离修筑又长又陡的便道调运,费用会更高,建议按实际情况进行调整。比如k5+420-k5+700段填方借要调用k3+836.5—k5+090段挖方 239863m3,因中间有王家畔隧

道,无法修便道。 7.有些桥梁布置很近,前桥尾与后桥头相距35m左右,为了减少桥头跳车次数,提高行车的舒适性,建议两座桥梁并为一座桥梁;同时为方便预制上部梁板,建议对相距极近的桥梁跨径及梁板型式进行统一。比如第一合同段五分部小石沟大桥与赵家岔大桥之间仅有35m,且桥跨结构分别是30m箱梁与40mT梁;16标安家沟大桥与陶家庄1#大桥之间首尾相距仅43m,建议合并为一座桥,且跨径统一。 8.同样的黄土冲沟地形及水文地质情况,有的填高20m左右就设桥梁,有的填高40m左右却不设桥梁。是否应把填高超过35m的路基改设为桥梁? 9.一些标段冲击碾压面积很少,而重夯、强夯有一定的数量。建议改冲击碾压为重夯或强夯。 10.钢筋砼拱涵设计上为无铰拱,稍有变形拱圈便会产生裂缝,建议改为两铰拱。 11.从设计图纸上看,超过55m的挖方槽段一般设置隧道通过。11标k42+000-k42+300段长330m,挖深59.7m; 19标k70+534-k71+080段长546m,最大挖深57.5m。这两段为何未设隧道? 12.建议沥青路面重车道及长大纵坡的中、上面层全改性。 13.临离高速填方段落特别多。为减少填挖接头处的沉降,提高行车舒适性,建议填挖方接头处每填筑3m高重夯一次。 14.为提高台背填土的强度及稳定性,挖方处桥台背墙底部每隔2-3m 需设一根?50mm泄水管。

智慧医疗项目技术解决方案建议书模板范文(完整方案)

技术解决方案/项目建设书 实用案例模板 (word,可编辑)

方案概述 智慧城市是新一代信息技术支撑、知识社会创新2.0环境下的城市形态,智慧城市通过物联网、云计算等新一代信息技术以及微博、社交网络、Fab Lab、Living Lab、综合集成法等工具和方法的应用,实现全面透彻的感知、宽带泛在的互联、智能融合的应用以及以用户创新、开放创新、大众创新、协同创新为特征的可持续创新。伴随网络帝国的崛起、移动技术的融合发展以及创新的民主化进程,知识社会环境下的智慧城市是继数字城市之后信息化城市发展的高级形态。 “数据驱动世界、软件定义世界,自动化正在接管世界,建设智慧城市将是下一波浪潮和拉动IT世界的重要载体。”《大数据》一书作者涂子沛这样描述。大数据遍布智慧城市的各个方面,从政府决策与服务,到人们衣食住行的生活方式,再到城市的产业布局和规划等,都将实现智慧化、智能化,大数据为智慧城市提供智慧引擎。 近年来,相关业界的领先者们也多次预言,大数据将引发新的“智慧革命”:从海量、复杂、实时的大数据中可以发现知识、提升智能、创造价值。“智慧来自大数据”——城市管理利用大数据,才能获得突破性改善,诸多产业利用大数据,才能发现创新升级的机会点,进而获得先发优势。 大数据驱动下的智慧城市,关乎每个人的生活。结合智慧城市对信息的需求,大数据在智慧城市中的落脚点集中在为其各个领域提供强大的决策支持。智慧交通、智慧安防、智慧医疗……未来智慧城市的美好图景已经被勾勒出来。 随着企业信息化水平逐步提高,信息化建设方向出现了重要的变化,突出表现在信息的集成整合和资源的共享利用,涉及到企业的安全防护、生产过程的调度、产品计量、决策及故障排除等方面。 解决方案Solution---就是针对某些已经体现出的,或者可以预期的问题、

Technical ProposalRequirements技术建议-工程建议书(技术标书)

Technical Proposal技术建议/工程建议书 (技术标) Personnel人员 Equipment设备 Site Organization现场组织 Method Statement施工方案

Personnel人员 Form PER – 1: Proposed Personnel人员表-1被推荐人员 Bidder shall provide the details of the proposed personnel and their experience records in the relevant Information Forms below for each candidate: 投标人应当提供被推荐人的详情和他们相关信息的经验记录,下表是每一个候选人的信息表: : *As listed in Section 6 (Employer’s Requirements). *按第6部分(业主的要求)中的列表。

Form PER – 2: Resume of Proposed Personnel 人事表—2:推荐人的简历: The Bidder shall provide all the information requested below: 投标人应当提供以下要求的所有信息: Summarize professional experience in reverse chronological order. Indicate particular technical and managerial experience relevant to the project. (时间)倒序专业经历概要。表明相关项目的特殊技术和管理经验。

浅谈工程前期技术管理 苏建涛

浅谈工程前期技术管理苏建涛 发表时间:2016-08-18T09:22:08.873Z 来源:《低碳地产》2015年第10期作者:苏建涛[导读] 施工前期技术管理是从投标开始编制施工组织设计,到中标后到大面积施工前这一阶段的工作内容。 中建三局装饰有限公司【摘要】施工前期技术管理是从投标开始编制施工组织设计,到中标后到大面积施工前这一阶段的工作内容;此阶段加大技术力量投入,对招标图纸进行全面分析,提出合理化建议,提高投标的针对性、合理性,能为进场前期较快的开展施工打下良好的基础。 【关键词】技术管理;技术先行贯穿工程始终;技术标;技术隐性成本;技术研讨会 一、施工前期技术管理可能存在的问题 通过对多个项目的多个专业的技术工作的调研,投标前到中标后施工前,这期间因技术力量投入、深化深度不足和投标技术人员与施工技术人员工作脱节等情况可能产生的不良后果,主要表现在以下几个方面 1)编制技术标期间技术人员对招标文件、图纸,尤其对现场情况了解不足,所编制出的技术标针对性、可操作性不强。 2)投标期间未能发现招标图纸中的影响成本的关键技术问题及隐形成本,未能协助预算人员提出具体技术解决措施,造成成本偏差较大。 3)施工前期深化设计投入不足,或深化方向偏离,所做的深化设计与现场实际情况产生偏差,开工后重新深化,耽误施工。 4)对材料性能或施工工艺的选择性错误,导致直接性预算偏差,同时也导致施工损失。 5)投标阶段技术人员、预算人员、材料人员等技术配合不密切,经常独自为政,闭门造车。 二、施工前期技术投入的必要性 做工程必须“技术先行、贯穿工程始终”,但是,技术上的失误或偏差很可能使得工程产生负价值,因此,加大技术的前期投入,让正确的技术成为工程开展的引导,是非常必要的。 投标阶段,通常我们投标做法均为商务标与技术标分开编制,技术部门主要任务为编制施工组织设计,预算部门编制商务标书;此做法目的性较强,基本针对招标文件要求进行编制,目的是为了响应招标单位和招标文件,最终得以中标。这种做法是符合市场要求的,但往往弱化了投标过程中技术深入分析潜在的风险,给中标后施工阶段带来不利因素。 施工前期阶段,主要是技术性复核性工作,复核内容主要是施工图纸与现场存在问题复核,通过测量放线、深化设计找出施工图纸与现场存在的不符合性问题。 三、施工前期技术解决措施 投标阶段强调施工前期技术配合的重要性,施工前技术分析与商务分析需同步进行,重视程度需与商务平等,加强技术密切配合,充分利用技术对商务的指导作用;通过专业技术人员投标前期介入,进行技术分析,对商务人员提出针对性、关键环节的技术性建议,使其做出可靠有竞争力的成本和报价;同时,在投标过程中通过协同配合,将影响中标后施工不利因素全部列举出来,能解决的投标阶段及时解决,不能解决的商议可行指导性方案,以便于项目施工时有针对性的施工运营。 施组编制过程中经过现场考察结合招标文件及图纸,作出针对性较强的施工组织设计,增加施工的指导性及投标过程中竞争力;施组编制前汇总图纸重点、难点做法区域,有专业技术人员一一剖析,一对一的编制施工方案,将深化节点做法导入方案中,需明确做法、材料品名、数量及难点剖析,图文并茂;然后将方案提交商务部门进行商务分析,套入商务标,再由商务提出商务建议,技术部门进行分析汇总;最终进行施组汇总编制,用公司专用模板,将各个施工方案套入施工组织设计内。此种做出的施工组织设计针对性较强,可增加技术标的竞争力。往往开标过程中在商务标分差较小时,技术标是重要增分项。前期的技术人员投入直接进入施工阶段组织架构,提高技术的连续性,降低或杜绝由于技术偏差或失误所带来的损失; 组建技术深化小组,增加设计深化和技术方案的编制力度,做出可行的方案或施工工艺,可降低造成的拆改、返修损失,提高整体装饰效果、降低综合成本。 四、施工前技术的具体方法简述 投标阶段要深入现场考查最大限度掌握第一手资料,在熟悉施工图及招标文件对技术标要求的情况下,编制施工组织设计、深化设计图,特别是节点图,一般标准性节点可根据行业标准结合公司自身技术优势进行编制,特殊要求的节点,比如专业化较强的节点,可由专业加工或安装的单位完成。 进场后强调复核,先将图纸与现场进行复核,有深化设计出精确放线控制图,然后一一分析各种材料的收口做法工作,针对重点难点进行细化节点,此时专业厂家必须配合,从专业角度分析,提可行性、针对性合理化建议,由技术部门进行汇总,在此精确放线,各个节点收口做法放到现场,墙、顶、地分区落到实际现场,对此阶段出现的问题再次分解,解决。如果此项工作能做扎实的话,可大大节省施工时间,提高效率和质量,减少或杜绝施工误差所带来的损失,收口不合理影响整体装饰效果。 五、工程技术保障措施 以上阐述的问题有最重要的两大基本因素:一是管理层面重视技术管理,二是重视技术人员培养 1)提高公司领导对技术管理意识,加强管理层对新兴材料及施工工艺的认知,可提高公司整体技术管理意识,定期组织高管技术研讨会,邀请各界专家学者进行讲座,组织各个项目技术负责人进行交流培训,建立技术创效长效机制,增强可持续性。 2)技术人员就是一个公司的软实力,攻坚克难均需技术人员默默地付出。故公司需重视对基层技术人员的培养,施工技术人员的晋升与施工现场管理人员需加于区分,明确晋升机制;技术人员是苦练内功的,非一朝一夕能成才,所以公司可着重考虑技术人员的培养模式。 3)除技术人员具备专业素养要求外,提高各个项目部技术负责人及技术人员的权利及地位是关键。使得技术人员培养机制良性循环。

施工技术建议书(英)

技术建议书 一、工程简介 工程位于分布于罗安达省内不同的土地上。建设面积为50000套,共分为T3 30% ,T4 50%,T5 20% 三种户型,总投资63亿美元。工期计划为5年,每年完成10000套房屋。 Construction survey Methods 1.Survey Precision In accordance with the construction survey regulation issued by Beijing Construction Committee, the Survey precision requirement for construction is 1/15000. 2 Standard Coordinate Checking Before positioning, in accordance with the construction survey regulation, the standard coordinates and the elevation controlling points must be checked. 3 Establishing Elevation Control Grid Based on the elevation controlling points provided by the local authority, two temporary benchmarks will be set up for construction. 4 Survey Control For Sub-structrue According to control grid to be established on site, grid lines will be transferred down with theodolite. Elevation level shall be transferred with leveling instrument. 5 Survey Control For Super-structure 1 )Vertical Transfer Of Grid Line Grid line will be set out accurately on ground floor slab when structure comes to 0.00 level. Then, based on ground floor, grid lines will be transferred to the upper floors vertically. 2 )Vertical Transfer Of Level 1.00m level line will be set out on the external wall of ground floor accurately. Several places where it is convenient for tape measuring will be selected and marked with red point. Elevation level will then be transferred to upper floor by tape measuring based on the painted marks. 6 Survey Control For Finishing 1) Based on the axes of each floor, the controlling line can be set out during finishing.

相关文档
相关文档 最新文档