工程项目施工方案

工程项目施工方案
工程项目施工方案

工程项目施工方案

目录

一、工程概况General (2)

1.1、工程项目信息project information (2)

1.2、建筑特征construction features (2)

1.3、巴基斯坦现行有关技术规范、标准、技术规程。 (4)

二、作业准备Construction Preparation (4)

1、作业条件Work conditions (4)

2、技术、资料准备Technology and documentation preparation (4)

3、人员配置Personnel deployment (5)

4、主要施工机械及设备材料Major construction machinery, equipment and materials (7)

5、现场准备Site preparation (7)

四、施工进度计划Construction Schedule (9)

五、施工方法与工艺Construction Method and Process (9)

1、施工工艺流程Construction process flow (9)

2、施工部署Construction deployment (9)

3、施工测量放线Surveying and setting out (9)

4、脚手架工程Scaffolding (10)

5、钢筋施工Reinforcement (11)

6、模板施工Construction of formwork (13)

7、混凝土施工Concrete construction (15)

8、门窗安装 installation of windows and doors (17)

9、瓷砖铺设Floor Tiles (18)

10、油漆painting (18)

11、天花板ceiling (19)

五、质量保证措施Quality Assurance Measures (20)

1、质量目标quality goals (20)

2、质量保证措施quality guarantee measures (20)

一、工程概况General

1.1、工程项目信息project information

巴基斯坦吉航(Jhang)1263MW联合循环电站项目位于巴基斯坦旁遮普省Trimmu Barrage (特瑞穆巴瑞)附近的Jhang(彰)地区,为新建工程。

The new Jhang 1263 MW power plant project locates in the Punjab province, near Jhang.

永久生活区位于整个厂区北部,占地约118870平方米,分为公寓、宿舍、贵宾招待区、餐饮区、清真寺、娱乐区等多区块,满足吉航电站职工、来宾的工作生活需要。

The housing complex sits in the northern part of the plant. It covers around 118870 square meters and is divided into apartments, dormitories, VIP receptions, catering areas, mosques, entertainment areas and other blocks to meet the working and living needs of employees and guests in the Jhang plant.

1.2、建筑特征construction features

本工程主要建筑功能数据见下表。

The functional data of the main constructions is shown below.

1.3、巴基斯坦现行有关技术规范、标准、技术规程。

Pakistan current technical specifications, standards, technical procedures, building codes and regulations, and industrial requirements.

ACI 318-14Building Code Requirements for Structural Concrete

建筑规范中对结构混凝土的要求

ACI 301-10Specifications for Structural Concrete. American Concrete

Institute

结构混凝土规范。美国混凝土学会

ASTM C150Specifications for Portland Cement

硅酸盐水泥规范

ASTM C33Specifications for Concrete Aggregate

混凝土骨料规范

ISO/IEC 对应的电气标准

Corresponding electrical standard

二、作业准备Construction Preparation

1、作业条件Work conditions

1.1、基础施工前的地下、地上障碍物清除和处理完毕。

Obstacles above /underground have been cleaned up before foundation construction is commenced.

1.2、建筑物或构筑物的位置或场地的定位控制线(桩)、标准水平尺寸,已准备就绪。

The location of the buildings or structures or site locating control line (stake), the dimension of standard elevation are ready.

1.3、施工时,在危险地段应设置明显标志,如需要安排专人看管。

Clear signs are placed at risky area before construction, and designated personnel shall be assigned for supervision if needed.

1.4、各施工机具已空载试运行正常,可进行施工作业。

All construction machineries have gone through no-load trial run and are in normal conditions, which are ready for operation.

1.5、施工临建、生产水﹑电及施工道路,材料﹑机具已准备就绪。

Temporary construction facilities, water & power supply for production, service roads, materials and equipment are all in place.

2、技术、资料准备Technology and documentation preparation

2.1、组织图纸学习、自审与会审图纸,进行施工方案交底和施工技术交底以及安全技术交底并组织相关人员进行学习。

Organize the study of drawings as well as self-check and joint check of drawings, carry out the disclosure of construction method statement, construction technology, and HSE technology, and organize relevant staff to study.

2.2、搜集本工程的环境条件、工程地质资料、设计图纸、技术规范等资料。

Collect materials for the present Works, including environment conditions, geological data, design drawings, technical specifications, etc.

2.3、特种工种组织学习,进行上岗考核。

To organize personnel of special work types to study, and conduct on-duty exam.

2.4、提取材料计划,对模板进行配板设计。

Submit material plan, and carry out formwork design.

2.5、申报钢筋备料计划,编制钢筋下料委托单。

Submit steel bar material preparation plan, and make steel bar process standing order.

2.6、各种机械进行自检维修,试运转。

Conduct self-check and service for all machineries, conduct trial operation.

2.7、施工测量放线设备及放线依据资料准备齐全。

All survey and setting-out equipment and setting-out references data are made complete and ready in place.

3、人员配置Personnel deployment

3.1、管理人员配置management personnel deployment

根据工程管理需要,本次基础施工拟投入中国国籍管理人员15名,根据施工准备和进展情况,全体人员将于施工前全部进驻现场。人员配置见下表:

According to management requirements of the present Works, the foundation construction concerned herein will engage 15 Chinese management staff, and the whole staff is required to enter the site before the construction commencement in accordance with the construction preparation and progress. See the Personnel Deployment List below:

3.2、劳动力配置Manpower deployment

根据施工计划安排,同时考虑现场环境、技术间歇、天气等各种因素,并根据以往工程施工经验和工程进度安排情况,确定劳动力计划,具体如下表。

According to execution plan and arrangement, as well as considering the site environment, technical intervals, weather and other factors, referred to project execution experience in the past and condition of working schedule, to certify manpower plan, see details as below:

注:该劳动力计划表是通过分析工程的特点,工期、进度要求等因素确定的人员配备,满足劳动力优化组合,专业技术人员均满足施工要求,具体人员数量及工种可根据施工过程中现场实际情况相应变化。

Note: this manpower plan is determined through project feature analysis, working period, schedule requirement and other components, to meet manpower optimization grouping, all professional technical personnel to meet execution requirement, detailed quantity and type could be adjusted accordingly regarding the site actual situation.

4、主要施工机械及设备材料Major construction machinery, equipment and materials

5、现场准备Site preparation

针对本工程施工现场的特点、构筑物的位置,施工现场的布置要力争做到实用、科学、合理,以满足施工要求,因此在基础施工必须做好以下工作

According to the specific features of the construction site and the location of structures, the layout of the construction site should be practical, scientific and reasonable to satisfy the construction requirements. Hence, the following preparations should be completed before the foundation construction.

5.1、施工区域现场用安全护栏进行围蔽,方便人员、机械上下施工。

Construction area should be barricaded with security fence; ladders should be erected at edge of foundation pit, to convenient personnel, machinery to go up and down for execution.

5.2、施工用电:Construction power supply

保障用电安全,电线搭设与连接均由专业电工安装,其他人员不得擅自动用。夜间施工的照明已满足施工要求。

In order to assure the safe usage of electrical power, the erection and conducting of electrical cables should be carried out by professional electrician, other people should not touch. The illumination for night execution can meet the construction requirement.

5.3、现场临时用水:Site temporary water supply

施工用水采用水车运至现场,在现场设置临时储水箱,以确保可靠、稳定供给。

The construction water will be shipped to site by water tanker car, and a temporary water tank will be set on the site to assure dependable and stable supply of water.

5.4、水平运输及垂直运输:Horizontal and vertical transportation

(1)、水平运输:材料运输采用长平板车倒运材料,主要负责从生产临建到施工现场之间的材料的倒运;施工区域内的材料倒运,采用汽车吊、人工配合的方法。混凝土运输采用混凝土罐车运至现场,再用汽车泵(或拖式泵)以及溜槽输送到仓面。

For horizontal transportation, flatbed truck of 8tons will be used to mainly transfer the materials between the construction TSF and execution site. For transfer of materials within construction area, mobile cranes will be used, cooperated by man power. For the concrete transportation, we shall apply transit mixers to transport the concrete to the site, and then deliver the concrete to the formwork by truck pump (or trailer pump) and chute.

(2)、垂直运输:根据需要和现场情况,汽车吊可布置在基坑周边,进行基坑内的材料水平、垂直运输。

For the vertical transportation, according to site conditions, the mobile crane can be set near the foundation pit to carry out vertical and horizontal transportation of materials inside the pit.

5.5、各施工机具已经维护保养完毕,具备使用条件。

All construction machineries are ready for use after services.

5.6、施工布置:Construction deployment:

(1)、本工程重点加强安全文明施工管理的力度,使工程现场始终处于整洁、卫生、合理有序

的状态。

For the present Works, we will put more effort on safe and civilized construction management to keep the site tidy, clean and orderly at all times.

(2)、施工材料堆放应尽量设置在垂直运输机械覆盖的范围内,以减少二次搬运为原则。

Construction materials should be stockpiled within the coverage of vertical transportation machinery to reduce secondary

handling.

(3)、临时电源、电线敷设要避开运输通道,以及容易被坠落物打击的范围,电线尽量采用暗敷方式。

Placing of temporary power supply and cable wiring should avoid the transportation corridor and the areas that are easy to be hit by fallen objects, try the best to apply concealed way of conducting for cables.

四、施工进度计划Construction Schedule

本工程基础施工日期为2018年9月25日,计划完成时间为2019年10月30完成。

五、施工方法与工艺Construction Method and Process

1、施工工艺流程Construction process flow

2、施工部署Construction deployment

施工流向:为集中人力资源作业,加快施工进度,合理安排工作面,保证流水作业不间断,特编制此项施工部署。生活区中部设临时加工厂和材料堆场、施工顺序从西向东进行,先完成住宿区,在建设辅助生活设施。

Construction flow: to concentrate the human resource, expedite the construction progress, reasonably arrange the work and keep the work activity continuously, the construction deployment is especially composed. The middle of the living area sets up the temporary processing plant and material stock. The construction sequence is from the west to the east, accomplishing the living area in the first place, followed by the auxiliary living facilities.

3、施工测量放线Surveying and setting out

3.1、轴线控制桩Axis control stakes

1、施工放线要求Requirements on setting out

选定距离机力通风塔区域较近的二级测控网网点进行闭合复测,确保满足精度要求作为永久生活区轴线的基准点。

Select secondary measurement control network points which are close to the mechanical draft towers for closed re-measurement to ensure it is accurate enough to serve as the datum mark of the axis of the HOUSING COMPLEX AREA .

2、平面控制点布设Deployment of horizontal control points

根据测量组交设的平面控制点需设永久性和临时性两种,永久性标桩的埋设应作到施工中能长期保存,不致于发生下沉和位移。

According to the horizontal control points designed by the survey group, temporary and permanent points shall be set. Permanent stakes shall be embedded in such manner that they can be preserved for a long term during the construction without sedimentation or displacement.

临时性标桩以钢筋、木桩或构筑物施工中原状为主,其规格和打入地下的深度依实地条件而定,用油漆标设定位。

Temporary stakes mainly adopt steel bar, wooden pile or the original status during construction of structures. Their specifications and piling depth are determined based on local conditions and shall be painted for positioning.

3.2、标高引测Elevation surveying

1、根据测量组指定的水准点在施工区域内布设三个临时水准点标桩,水准点标桩应埋置稳定牢固。标桩布置好后引出标高,临时水准点的测量结果闭合差必须符合规范规定的精度要。

According to the benchmark designated by the surveying group, three temporary benchmark stakes shall be deployed in the construction area and embedded stably and firmly. After the stakes are deployed, elevation shall be drawn. The closure error of the measurement results of the temporary benchmark must comply with specified accuracy.

2、平面控制点标桩及临时水准点标桩布设好后必须经测量组进行复核,认可后才能用于施工中做为控制依据。

After being deployed, the horizontal control point stakes and temporary benchmark stakes shall be reexamined and approved by the surveying group before being used as control basis for construction.

4、脚手架工程Scaffolding

4.1、脚手架的搭设Erection of scaffold

(1)、搭设场地平整、夯实。The ground shall be leveled and compacted.

(2)、脚手架立杆必须座在枕木上。The scaffold must be located on sleepers.

(3)、在搭设之前必须对所有脚手架钢管和配件进行严格检查,禁止使用规格和质量不合格的钢管

和配件。

All scaffold tubes and fittings must be strictly examined before erection. Do not use any steel tube or fittings which is unqualified or of wrong specification.

(4)、应按定位依次竖立立杆,将立杆与纵、横向扫地杆连接固定,然后搭设第一步的纵向和横向

平杆,校正立杆垂直之后予以固定,并按此要求继续向上搭设。

Upright tubes shall be erected in turn according to the positioning. Connect the upright tubes with the longitudinal and horizontal bottom tubes and then erect the longitudinal and horizontal tubes for the first step. Fix the upright tubes after there are calibrated for verticality. Then keep erecting upwards by the same method.

(5)、剪刀撑、斜杆等整体拉结件和连墙件应随脚手架一起及时设置。

Diagonal bracing, diagonal rods and other complete ties and wall-connecting tubes shall be set timely along with the scaffold.

4.2、脚手架的使用:Scaffold usage:

(1)、在脚手架上的施工通道和工作平台上放置的材料应放整齐稳固,不影响施工操作和人员通过,严禁在施工通道的施工平台上奔跑、退行或倒退拉车、和集中堆放材料。

Materials on the construction passageway and work platform of the scaffold shall be placed in an ordered and stable manner without influencing the construction and the personnel passing through. It is prohibited to run, move backwards, pull a cart backwards or pile a lot of materials on the construction platform.

(2)、在作业中,严禁随意拆除脚手架的基本构架杆件、整体杆件、连接紧固件等,确因操作要求需要临时拆除时,必须经主管人员同意,采取相应弥补措施,并在作业完毕后及时予以恢复。

During the operation, it is prohibited to remove any fundamental structural rod pieces, integrated rod pieces, connecting and fastening pieces. In case of temporary removal required for operation, it must be subject to the supervisor’s approval and provided with remedy measures. After the job is finished, the temporarily removed piece shall be restored in time.

(3)、工人在架上作业中,应注意自我安全保护和他人安全,避免发生碰撞、闪失和落物。严禁在架上、跳板上嬉闹,坐在栏杆上等不安全的地方休息。

The scaffolder shall be aware of his own safety and other people’s safety to avoid impact, accident and falling objects while he is working on the scaffold. It is prohibited to have fun on the scaffold and access board or rest on the rails and other unsafe places.

(4)、每班工人上脚手架时,应先检查有无影响安全作业的问题存在,在排除和解决后方可开始作业,在作业中发现不安全的情况和迹象时,应立即停止作业进行检查,解决后可以恢复作业,发现异常情况应立即通知架上人员撤离。

Before getting up to the scaffold, the scaffolder shall check for any danger which may jeopardize safety and eliminate the danger before starting to work. In case of any unsafe condition or sign, the scaffolder must stop to check and solve the problem before continuing the work. Anyone who discovers any abnormality shall immediately notify the personnel working on the scaffold to get off as soon as possible.

(5)、在每一步架的作业完成之后,必须将架上剩余材料及物品移至上(下)步脚手架或清除,每日下班前应整理安全通道和工作平台上材料、物品堆放整齐,垃圾及运走,在作业期间,应及时清理落入安全网内的物品和材料,在任何情况下,严禁在脚手架上向下抛掷物品和倾倒垃圾。

After the work on each step of the scaffold is finished, the remaining materials and articles on the scaffold must be moved to the upper (lower) step or be cleared. Every day before ending the work, the safety passage must be cleaned, the materials and articles on the working platform must be sorted out and the rubbish must be moved away. During the work, any article or material falling into the safety net shall be timely removed. In any circumstance, it is forbidden to throw any object or dump rubbish from the scaffold.

4.3、脚手架拆除Removal of scaffold

脚手架的拆除作业应按确定的拆除程序进行,在拆除过程中,凡已经松开连接的杆配件应及时拆除运走,避免误扶和误靠已松脱连接的杆件而发生危险,拆除的杆配件应以安全的方式运出和吊下,严禁向下抛掷,在脚手架的拆除过程中,应做好配合、协调动作,禁止单人进行拆除较重杆。

Removal of the scaffold shall be performed in accordance with specified procedure. During the removal, any loosen rod piece shall be dismantled and taken away in time to avoid danger caused by mistakenly resting on the loosen rod. The removed rod pieces shall be taken away and lift down safely instead of dropping down. The removal of the scaffold shall be completed by cooperation and coordination, especially the heavy rods, which are not allowed to be removed by only one person.

5、钢筋施工Reinforcement

本工程钢筋在现场综合加工区集中加工,按需要运至作业面安装成型。

The steel bars to be incorporated to the Works shall be processed in the comprehensive processing zone at the construction site and delivered to the working face for installation as required.

5.1、钢筋进场存放和钢筋试验Steel bar receiving, storage and test

(1)、钢筋进场时按照进度计划分批量进行。施工现场存放钢筋原材料和半成品,对钢筋原材按同等级、牌号、直径、长度分别做好标识,钢筋半成品要按部位、分层、分段和构件名称,按号码顺序堆放,同一部位或同一构件的钢筋要放在一起,并有明显标识,标识上注明构件名称、部位、钢筋型号、尺寸、直径、根数。加工场地设钢筋切断机、钢筋弯曲机、钢筋调直机等。钢筋堆放时下面要用垫木,以防钢筋锈蚀和污染。钢筋存放场地应设置防雨措施,以便于钢筋的存放和运输。

Steel bars shall be delivered to the construction site in batches in accordance with the schedule. For raw materials and semi-finished products of steel bars stored on the site, the raw materials shall be marked based on the class, grade number, diameter and length, and the semi-finished products shall be piled by sequence number based on their position, layer, section and component name. The steel bars for the same position or component shall be placed together and clearly identified with a marker indicating the component name, position, steel bar type, size, diameter and quantity. The processing site shall be provided with steel bar cutter, bender and straightener. The steel bar storing yard shall be provided with rain-proof measures for storage and transportation of steel bars.

5.2、钢筋加工Preparation of reinforcement bar

(1)、认真阅读图纸,正确理解设计意图,确认图中钢筋规格、型号、数量,严格按设计要求及有关施工规范进行钢筋翻样。

(1) Read carefully the drawings, understand the design idea correctly, confirm the specification, type and quantity of reinforcement bar specified by the drawings, and then prepare the sample of reinforcement bar in accordance with the design and the related construction specification strictly.

(2)、钢筋成批制作前,要严格按钢筋翻样表进行放样,每一品种钢筋先制作一根,检查其下料长度,弯钩角度、长度、弯起点位置是否与设计要求相符合,确认无误后,这根钢筋作为这一品种的样筋按此制作。

(2) Before starting the mass production, it is required to prepare the sample in accordance with the reinforcement bar sample table, and prepare one piece of reinforcement bar for every type of reinforcement bar. It is required to inspect if the blanking length, hook angle, length and bending origin are complied with the design or not; if yes, the mass production of the type of reinforcement bar can be started according to this sample.

(3)、钢筋工拿到翻样表后,先对翻样表中的尺寸数据待进行复核,无误后方可进行制作,制作前先将钢筋统一进行除锈,在调直制作过程中必须严格按照翻样表断料,制作成型后的钢筋必须分类堆放整齐,每10根一捆用铁丝安装好,以便核对数量并挂上标识牌。

(3) After taking the reinforcement bar sample table, the bar placer should review the dimensional data on the reinforcement bar sample table, and then start fabrication after ensuring their correctness. Before starting preparation, derust the reinforcement bar firstly, and cut the raw material strictly in accordance with the reinforcement bar sample table in the process of straightening the reinforcement bar; stack the finished reinforcement bar neatly and bundle 10 pieces of reinforcement bar; afterwards hang the tag to facilitate to check quantity.

5.3、钢筋半成品运输Transportation of semi-finished reinforcement bar

现场采用平板车将钢筋半成品运至安装区域,装车时,钢筋必须按规格整齐摆放,长钢筋放下面,短钢筋放上面。运输过程中,装卸人员不得坐在平板车上。钢筋装卸以人工为主,如有必要,卸车时,可考虑用吊机吊运,吊运时,必须有专职的起重指挥,钢筋必须用钢丝绳和卸克绑扎牢固并水平起吊。Use the platform car to move the semi-finished reinforcement bar to the installation area; place and arrange the reinforcement bar neatly when loading into the platform car, and place the long reinforcement bar at the bottom and the short reinforcement bar on

the top. No loader is allowed to sit on the platform car in the transportation process. Load and unload the reinforcement bar manually; if necessary, use the crane to hoist when unloading. When lifting reinforcement bar, appoint the full-time hoisting commander; tie and bind the reinforcement bar with the steel wire rope, and then hoist them horizontally.

5.4、钢筋安装:Installation of reinforcement bar

(1)、柱插筋安装:依据柱子的边线安装柱子的插筋。柱插筋时应先搭设钢管架子定位,将其安装固定在钢管架子上,并与基础模板加固系统相连,要保证其牢固及位置准确,柱插筋与底板筋点焊固定。

Installation of column joint bar: install the joint bar of column according to the side line of the column. Erect the steel tube frame to locate before applying the column joint bar; fix the column joint bar onto the steel tube frame, and connect it with the foundation formwork reinforcement system to ensure their fastness and accurate position; conduct the spot weld to the column joint bar and the base plate bar to fix them well.

(2)、隔墙钢筋安装:Installation of reinforcement bar of pool wall and partition wall

1)、钢筋绑扎时,先立2~4根立筋,画好水平筋的分档标志,在下部及齐胸处绑两根横筋定位,并在横筋上画好分档标志,接着连接其余立筋,最后再绑其余横筋,横筋放在里面或外面要符合设计要求。

When binding the reinforcement bar, erect 2~4 vertical bars and mark the level mark of horizontal bar; bind 2 pieces of cross bars at the lower part and the position as high as the chest of body, and then mark the level on the cross bar; connect the other vertical bars and finally bind the other cross bars; keep the cross bars inside or outside and ensure to meet the design requirements.

(3)、梁钢筋安装Installation of beam reinforcement bar

1)、梁钢筋绑扎时首先在模板侧帮上画出箍筋间距后摆放箍筋。然后穿梁的上、下部纵向受力筋,先绑底层纵筋,再绑上层纵筋。

Mark the gap of stirrup spacing on the lateral wall of formwork firstly when binding beam steel, and then place the stirrup bars; Put into the longitudinal stressed bar at the upper and lower part of the beam, bind the longitudinal bar at the bottom layer, and then the longitudinal bar on the top.

2)、框架节点处钢筋穿插十分稠密时,应特别注意梁顶面主筋间的净距要有30mm,以利浇筑混凝土。

If there is dense reinforcement bar at the frame joint, it is specially required to pay attention to leave a net gap between the main top reinforcement bars by 30mm so as to facilitate the cast-in-place construction.

(4)、钢筋安装时放好保护层垫块,钢筋保护层垫块以同标号的混凝土垫块控制,垫块应垫在下层钢筋的交叉点处。钢筋在安装前应核对成品钢筋的钢号、直径、形状、尺寸和数量是否与设计图纸相符,如有错漏,应予以纠正增补。

Place the protection layer cushion when installing reinforcement bar, use the concrete cushion block with the grade as same as the cushion block of reinforcement bar’s protection layer; keep the cushion block at the intersection of the lower reinforcement bar. Check the grade, diameter, shape and quantity of finished reinforcement bar before installation, and check if they meet the design drawing; if any of them is wrong or missing, it must be corrected and added.

Lead the elevation to the neighboring reinforcement bar so as to facilitate the local use (check the elevation accuracy before use).

6、模板施工Construction of formwork

6.1、模板采用1220*2440*18mm复塑大模板,第一次使用可不刷模板脱模剂,但必须进行清理,并用毛巾擦拭干净(严禁采用面纱)。第二次使用前均匀涂刷模板脱模剂,脱模剂采用食用色拉油。Adopt composite-plastic formwork of 1220*2440*18mm; do not coat the release agent if it is used firstly; however it is required to clean by towel (do not use the veil). Coat the formwork release agent for the second use, and use only the edible salad oil as the release agent.

6.2、模板制作Fabrication of formwork

(1)、对需切割的模板,圆盘锯锯片只能高出模板1.5cm以下(也就是比模板面稍高即可),切割产生的锯齿边缘用平刨刨平直。模板切割前,需进行切割试验,符合要求后方可批量切割。

For the formwork to be cut, the saw web of the disk saw must only be higher than the formwork by 1.5cm max. (namely the saw web can be slightly higher than the surface of formwork); the jagged edges produced by the cutting job should be straightened by the planer. Before cutting the formwork, it is required to make the cutting test and start the massive cutting operation after confirming to meet the given requirements.

(5)、如使用旧模板,对旧模板应按以下要求处理好:If using the old formwork, it should be processed as follows:

模板拆下后,应立即冲洗,用小铲刀将模板表混凝土残余除尽

After the formwork is removed, it is required to rinse the formwork, and remove the residual concrete from the formwork by the plough staff, and then clean with the washing powder and finally repair and patch the holes and damaged parts in the formwork.

(6) 旧模板处理好后,堆码模板时要求按照正面对正面的方式堆码(运输过程及现场堆码也如此),运输过程中车厢与模板接触的部位必须用木枋对模板进行保护。

After the old formwork is processed, stack only the formworks to keep them face to face (front face to front face) (same to the transportation and the field stacking); use the wood to protect the formwork at the place where the formwork contacts the vehicle.

(7) 周转使用的模板,翻面使用时应注意清理干净编号,不得使编号印在混凝土面上。

For the turnover formworks, it is required to remove the number when using on the reverse surface so as to avoid the number from printing on the concrete.

(8) 模板制作前,需根据施工图进行翻样配置。模板严格按配置图纸在加工场提前加工,配好的模板其尺寸必须精确,保证接缝严密;确保模板几何尺寸,保证混凝土的成型工艺质量。

Prepare sample and make matching assembly according to the construction drawing before making formwork. Conduct the early processing for formwork in the processing yard according to the configuration drawing; ensure the accurate dimension of the matched formwork and ensure their correct joint; keep the geometrical dimension of formwork to meet the given requirements and ensure the forming process quality of concrete.

6.3、模板安装Installation of formwork

(1)、柱模板安装Installation of column formwork

模板间拼缝以PE胶条粘贴,以保证混凝土表面平整光滑。钢筋应全部调整结束,不应有偏位影响柱子模板安装的现象。

The joint of formwork should be stuck by PE adhesive tape so as to guarantee a smooth concrete surface. After all reinforcement bars are adjusted, no affection to the installation of column formwork can be found.

(2)、隔墙模板安装

1)、检查隔墙模板安装位置的定位基准面墙线,符合图纸后,安装模板。

2)、隔墙模板安装时,严格控制垂直度,和隔墙厚度,并按600mm间距布置对拉丝杆。伸缩缝处隔墙先浇筑其中一侧,对拉丝杆预留2段隔墙长度,模板拆除后,不切断对拉丝杆,直接粘黏挤塑板,安装另一侧模板。

3) 、模板安装完毕后,全面检查扣件、螺栓、斜撑是否紧固、稳定,模板拼缝及下口是否严密。

4) After installing formwork, inspect fasteners, bolts and inclined supports comprehensively and check if they are fastened and stable, and if the formwork joint and the bottom opening are airtight.

(3)、梁模板安装

根据模板位置线、标高控制线等将模板放置在相应位置上,拼装时,由两端的基础边开始向中间排,并按模板位置线控制梁与基础的尺寸位置。模板接缝粘帖双面胶条,以免漏浆。

Place the formwork on the corresponding position according to the formwork position line and elevation control line; arrange the formworks from the foundation sides on both ends to the middle part, and control the dimensional position of beam and foundation according to the formwork position line. Apply the double-sided adhesive tap at the joint of formwork to avoid from leaking mortar.

6.4、模板拆除Removal of formwork

(1)、底板、池壁、柱及梁侧模拆除待混凝土强度达到保证其表面及棱角不受损伤时方可进行;拆除模板应轻轻撬动,使模板脱离混凝土表面,禁止猛砸猛敲,防止碰坏混凝土和模板。

After the concrete strength reaches to the given requirement and its surface and shape edges are not affected or damaged, the formwork of bottom plate, pool wall, column and beam can be removed; when doing this job, it is required to prize the formwork slightly to make the formwork to release from concrete surface; any hard force to hit the formwork must be avoided as to prevent concrete and formwork from damage.

(2)、拆模后穿墙螺栓端头凿出的凹槽应用嵌缝材料封堵密实,并应用聚合物水泥砂浆抹平。

After formwork is removed, the groove caused by the wall bolt should be filled by the joint material, and should be leveled by the polymer cement mortar.

对不能取出的对拉,严禁使用火焊靠近模板切割,必须采取对模板进行保护后分两次切割的方式拆除模板。

For the formwork that can not be removed easily, it is prohibited to use the fire welding to cut in the place approaching to the formwork, and it is required to protect the formwork and then remove the formwork by two cutting operations.

7、混凝土施工Concrete construction

7.1、混凝土生产、运输Production and transportation of concrete

采用自然连续级配的粗骨料配制的混凝土。因为连续级配粗骨料配制的混凝土具有较好的和易性。粗骨料的规格往往与结构配筋间距,模板形状以及浇筑工艺等因素有关,因此根据实际情况,本工程拟选用粒径较大,级配良好的5~25mm碎石,砂的细度模数应大于2.3-3.0。同时严格控制砂、石料的含泥量。

The concrete should be prepared by using the coarse aggregate of naturally continuous grading. The concrete prepared by using the coarse aggregate of naturally continuous grading is featured in good mixture. The specification of coarse aggregate is related to the gap of structural bar, formwork shape and pouring technology. Therefore according to the actual conditions, the 5~25mm broken stone with larger diameter and good grading, as well as the sand with the fineness modulus more than 2.3-3.0 should be used for the project. Meanwhile the mud content of sand and stone should be strictly controlled.

7.2、混凝土浇筑Pouring of concrete

(1)、混凝土采用混凝土泵车浇筑,罐车从搅拌站拉运混凝土。由汽车泵、拖式泵或溜槽直接从入仓。

The concrete will be poured and placed by the concrete pump truck, and the tank vehicle will transport the concrete from the mixing plant. The automobile pump, trailer-type pump or chute can be used.

(2)、混凝土浇筑前,对模板、钢筋等再次进行细致检查,做好记录。质检员做好会签工作。模板内、钢筋上的油污、泥土、垃圾、杂物等应清理干净,堵严缝隙。各种运输设施如混凝土运输车、汽车泵或拖式泵、溜槽等准备就位。

Before pouring the concrete, it is required to inspect the formwork and reinforcement bar again, and keep the records accordingly. The QC must provide the countersignature for confirmation. The oil, mud, rubbish and foreign matters inside formwork and on reinforcement bar should be removed and cleaned, all gaps must be filled. All transportation equipments, such as concrete carrier vehicle, automobile pump or trailer-type pump, as well as the chute must be prepared in place.

(3)、柱、隔墙混凝土浇筑时,要严格控制每层混凝土厚度和混凝土坍落度,每层不得超过500mm,坍落度过小分层厚度要随时调整。在振捣上一层时,应插入下一层50mm左右,以消除两层之间的接缝。

When pouring concrete for baseplate and column, it is required to control the thickness and slumps of concrete on every layer, and keep every less not exceeding 500mm; if the slump is too less, it is required to adjust the layering thickness from time to time. When vibrating the upper layer, the vibrating spear should insert into the lower layer by 50mm so as to eliminate the joint between two layers.

(4)、混凝土浇筑应连续进行,尽量减少中途停歇,不留施工缝。混凝土间歇时间混凝土浇筑前后间隔时间一般不能超过2小时,以防出现冷缝,以防堵管。不准随意加水。混凝土振捣要掌握好振捣时间,过短不易捣实,过长可能引起混凝土产生离析现象。操作时要快插慢拔,上下略为振动,插点均匀排列,逐点移动,顺序进行,不得遗漏,使混凝土达到均匀振实。

When making continuous pouring for concrete, it is required to reduce the midway pause as far as possible to avoid construction joint. The rest time for pouring concrete should not exceed 2 hrs; if not there will have cold joint and which will block the tube. Do not add water without prior consent. Master the vibrating time when vibrating the concrete; any shorter vibrating time is not preferred; however the longer vibrating time will cause concrete to separate. Insert the vibration spear quickly and remove it slowly; vibrate the top and the bottom slightly, arrange the insertion point of vibrating spear averagely and move one point by one point, and vibrate according to the given sequence; any omission or missing vibration point is not allowed; make the concrete compacted and uniform.

(6)、收面:混凝土找平的同时将局部不平整的地方修复,在初凝后用铁抹子收面,随后用磨光机进行磨面。磨面完成后,再用铁抹子进行抹压,抹压时应用力把所有压纹压平,压光,使表面密实光洁,从而有效减少表面出现裂缝。

Surface treatment: when leveling the concrete, it is required to repair the irregular area, and use the plasterer’s trowel to treat the surface when the concrete is initially setting; afterwards, the surface should be polished by the polishing machine. After the surface is treated, use the plasterer’s trowel to press; when pressing, it is required to press and polish all wrinkles hardly so as to reduce the crack on the surface.

(7)、混凝土的养护Conservation of concrete

由于当地温差较大,混凝土浇筑完应及时遮盖,大体积混凝土表面铺塑料薄膜并覆盖麻袋洒水养

护。派专人每天进行浇水养护,养护时间不少于7天。

Due to the huge difference of local temperature, it is required to cover the concrete after it is poured; the plastic film should be put onto the surface of mass concrete and the jute bag should be used to cover. Besides, the full-time person should be sent to do the preservation job and make the preservation time of concrete not less than 7days.

7.3、施工缝施工Construction joint

在下一次浇筑前,施工缝位置必须凿毛处理。凿毛应清除水泥薄膜、表面上松动砂石和软弱混凝土层,同时应露出石子。下一次浇筑前用水冲洗干净并充分湿润,残留在混凝土表面的积水应予清除。施工缝处理时,要注意施工缝位置附近钢筋,要做到钢筋周围的混凝土不受松动和损坏。钢筋上的油污、水泥砂浆及浮锈等杂物也应清除。

Before making the next pouring, the construction joint must be chiseled. The film on cement, loose stone on surface and weak concrete should be removed when chiseling, and meanwhile the stone must expose. Use the water to clean and moisten before making the following pouring; remove the water retained on the surface of concrete. When processing the construction joint, it is required to pay attention to the reinforcement bar near to the construction joint; the concrete around the reinforcement bar must not become loose and damaged. The oil, cement mortar, rust and other foreign matters should be cleaned.

8、门窗安装 installation of windows and doors

8.1、Doors Installation:门安装

Dimensions of doors must be as per drawings and checked by the engineers before ordering. Sample needs to be checked.

门的尺寸必须按照图纸和工程师在订购前检查。需要检查样品

Ensure that the slots for bolts, locks are as per drawings and specifications.

确保螺栓、锁的插槽按图纸和规格进行

The frames hold fast must be grouted with cement mortar rigidly.

支架必须牢固地用水泥砂浆进行灌浆

Ensure that the glass (Used in Aluminum and Steel Doors) is free from waves, and other defects. Check the thickness of the glass before fixing.

确保玻璃(用于铝和钢门)不受波浪和其他缺陷的影响。固定前检查玻璃厚度

Check that doors/windows frames are erected in plumb line, level and diagonals.

检查门/窗框架是否竖立在铅垂线、水平线和对角线上

Ensure that the work of painting/oiling is started after approval.

确保涂装/涂油工作在批准后开始

8.2、Aluminum Windows Installation: 铝窗安装

Finished opening sizes should match perfectly with prefabricated Window sizes. To ensure about the exact dimensions, make up sample or templates (either from wood material or M.S. material) shall be used.

成品开口尺寸应与预制窗尺寸完全匹配。为了确保精确的尺寸,应使用样品或模板(木材材料或M.S.材料)

Arrangement for all approved hardware fittings as per the drawing shall be ensured before fixing of the material.

在所有材料固定之前,应确保图纸上所有认可的五金配件的布置

Glazing shall be fixed to the extruded sections by means of extruded aluminum beading. Glass panes shall

be provided with rubber lining before fixing.

上釉应通过挤压铝珠固定在挤压型材上。玻璃板在安装前应提供橡胶衬里

The windows / ventilators shall be checked to ensure smooth operation, perfect level and plumb.

检查窗/通风机,确保操作平稳、水平和垂直度

9、瓷砖铺设Floor Tiles.

9.1、图纸指定的施工地面找平。Establish finished floor level as per approved drawing.

9.2、清洁混凝土板上的油、浆和杂物。Clean Concrete slab from oil, laitance and any foreign materials.

9.3、根据要求铺设一定厚度的砂层。Lay sand layer according to the required thickness.

9.4、用1份水泥混合4份砂配制砂浆。Prepare mortar Mix in 1 Part Cement and 4 Parts Sand.

9.5、铺瓷砖前先将砂层弄湿。Wet and damp the sand layer just before laying Ceramic tiles.

9.6、在大约2-4厘米厚的砂浆层上铺设瓷砖,按要求的图案,用木槌压制陶瓷砖,以确保达到所需的粘结,其他工作将遵循(联合灌浆,清洁将遵循前面所述的相同程序。lay Ceramic tiles on approximately 2-4 cm thick mortar bed , to the required patterns , Fix the ceramic by pressing using wooden hammer, to assure that required bond is achieved , other work will follow ( Joint Grouting , Cleaning will follow same procedure as described earlier.

9.7、在地漏位置,地面处理应向排水沟倾斜。Where floor drains are provided, the finished floor plan shall be sloped towards the drains.

9.8、在必要时沿地板的外边缘切割瓷砖,尽量不磨损瓷砖表面。瓷砖应紧密贴合地安装在所有的管道固定装置周围和电气出口。Cutting of Tiles where necessary shall be done along the outer edges of the floor and done without marring the tile surfaces. The tiles shall fit closely and neatly around all plumbing fixtures and around electrical out lets.

9.9、已完工的部分须采取适当保护措施Assure Protection to the finish works by establishing proper measures.

10、油漆painting

10.1、Surface Preparation:表面准备

Preparation of surface is made by removing all loose particles, old dry plaster surface.

除去表面颗粒、干旧泥灰。

10.2、Putty:腻子

Putty to be used for making up minor undulations in concrete surface, shuttering gaps and minor cracks, wherever necessary, Putty may be applied using scrapper / spatula / putty knife. 2 coats of Stucco Putty (white) have to be applied for a particular interval depending upon working temperature as mentioned in technical specification of paint.腻子用于弥补混凝土表面轻微的起伏、间隙和轻微裂缝,必要时可使用刮刀/油灰刀。根据涂料技术规范所述,刮两层Stucco 的(白色)腻子时,按制造商说明进行操作。

10.3、Paint Application: 上漆

2 coats of approved paint have to be applied by brush/ roller at the rate specified in the material data sheet. Interior/exterior house paint tends to separate when stored, the heavier components settling to the bottom. It should be mixed before use, with a flat wooden stick or a paint mixing accessory; pouring it back and forth between two containers is also an effective manual mixing method. Paint stores have machines for mixing the paint by shaking it vigorously in the can for a few minutes.

在材料数据表中规定的刷子/辊子上涂布2层认可油漆。室内外油漆在存放时趋于分离,较重的成分沉降到底部。在使用之前,应该用一个扁平木棍或一个油漆混合附件混合,在两个容器之间来回浇灌也是一种有效的手工混合方法。油漆店有机器来搅拌油漆,在罐头里用力摇晃几分钟。

11、天花板ceiling

11.1、Preparation准备

Before fixing ceiling, it shall be ensured surface is clean.

在固定天花板之前,应确保表面清洁

Before beginning fixing work, all machine and hand tools shall be ready.

在开始固定前,所有工具都要准备好。

The electrical lighting line and HV AC pipe should be completed before fixing ceiling.

电气照明线路和暖通空调管道应在安装吊顶前完成

11.2、吊杆固定:膨胀螺栓用于吊杆的固定。吊杆应安装在混凝土板上。采用电缆钻孔工具制作孔,孔直径略大于膨胀螺栓直径

Fixing of suspender: The expansion bolt is used to fix the hanging rod. The suspender shall be installed on the concrete slab. Using cable drilling tool make Hole, the hole diameter is a little bigger than the expansion bolt diameter.

11.3、主龙骨安装:主龙骨应悬挂在吊杆上,主龙骨间距为1200毫米。主龙骨应平行于房间的长度,并应同时拱起。主龙骨的搭接应对接。相邻龙骨的对接应错开。主龙骨悬挂后应平整。

Main keel installation: The main keel shall be hung on the suspender this main keel spacing 1200mm. The main keel should be parallel to the length of the room and should be arched at the same time. The overlap of main keel should be butt joint. The butt joint of adjacent keel should stagger each other. Main keel should be leveled after hanging.

11.4、侧龙骨安装:侧龙骨应按水平线的设计要求,沿(L形或U形)龙骨线水平的墙(柱),用钢带固定在墙上,用钉子固定。

Side keel installation: The side keel should be installed according to the design requirements of the level line, along the wall (column) on the level of (L or U shaped) keel line using steel strip for fixing in the wall by nails.

五、质量保证措施Quality Assurance Measures

1、质量目标quality goals

满足施工图设计和规范、规程要求,达到合格标准。

To meet the requirement of drawing design and regulations and rules, to reach the qualification standard

2、质量保证措施quality guarantee measures

3.1、质量保证体系quality guarantee system

(1)、项目部严格贯彻公司标准化管理,使质量管理制度化、文件化、系统化,以使影响工程质量的各个环节处于受控状态。

The project department implements standardized management required by the company headquarters, to make quality management with rules, documents and system, so as to make all quality influencing elements under control.

(2)、健立、健全质量保证体系,质量保证体系组织机构责权分明,指令畅通。

Erect and complete quality guarantee system, to make the organizational structure of quality guarantee system with clear rights and obligations and smooth instructions.

3.2、确保工程质量措施project quality guarantee measures

(1)、根据质量标准,做好质量预控计划,从工程总体到各分部分项,都制定出质量预控目标和质量保证措施,针对质量通病,技术人员先进行详细的技术交底,质检人员现场严格把关,不让不合格因素漏网。

Make quality pre-control plan according to quality standard, to make quality pre-control goals and quality guarantee measures for the whole project and every sub item as well, regarding general existing quality defects, detailed technique disclosure should be conducted by technical staff, strict site control by the quality inspector should be conducted as well, to avoid missing unqualified elements.

监控施工方案模板

监控施工技术方案 1. 工程的施工技术、施工方法、工艺流程及施工进度计划、工期安排 1.1施工程序 线缆敷设→设备安装→设备调试→投入试运行→竣工资料整理→验收交付使用 1.2主要施工方法 1.2.1系统安装 按照施工技术图的要求,明确安防系统中各种设备与摄像机的安装位置,明确各位置的设备型号和安装尺寸,根据供应商提供的产品样本确定安装要求。 根据安防系统设备供应商提供的技术参数,配合土建做好各设备安装所需的预埋和预留位置。 根据安防系统设备供应商提供的技术参数和施工设计图纸的要求。配置供电线路和接地装置。 摄像机应安装在监视目标附近,不易受外界损伤的地方。其安装位置不易影响现场设备和工作人员的正常活动。通常最低安装高度室内为2.50米,室外3.50米。 摄像机的镜头应从光源方向对准监视目标,镜头应避免受强光直射。 摄像机采用75Ω-5同轴视频电缆,云台控制箱与视频矩阵主机之间连线采用2芯屏蔽通讯线缆(RVVP)或3类双绞线。 必须在土建、装修工程结束后,各专业设备安装基本完毕,在整洁的环境中安装摄像机。从摄像机引出的电缆留有1m的余量,以便不影响摄像机的转动。 摄像机安装在监视目标附近不易受到外界损伤的地方,而且不影响附近人员的正常活动。安装高度室内2.5-5m,室外3.5-10m。电梯轿厢内的摄像机安装有顶部,其光轴与电梯厢的两壁、天花板成45度角。

摄像机避免逆光安装。 云台安装时按摄像监视范围决定云台的旋转方位,其旋转死角处在支、吊架和引线电缆一侧。电动云台重量大,支持其的支、吊架安装牢固可靠,并考虑其的转动惯性,在它旋转时不发生抖动现象。 安装球形摄像机、隐蔽式防护罩、半球形防护罩,由于占用天花板上方空间,因此必须确认该安装位置吊顶内无管道等阻档物。 解码器安装在离摄像机不远的现场,安装不要明显;若安装在吊顶内,吊顶要有足够的承载能力,并在附近有检修孔。 在监控室内的终端设备,在人力允许的情况下,可与摄像机的安装同时进行。监控室装修完成且电源线、接地线、各视频电缆、控制电缆敷设完毕后,将机柜及控制台运入安装。 机架底座与地面固定,安装竖直平稳,垂直偏差不超过3‰;几个机柜并排在一起,面板应在同一平面上并与基准线平行,前后偏差不大于3mm,两个机柜中间缝隙不大于3mm。控制台正面与墙的净距不小于1.2m,侧面与墙或其他设备的净距不小于0.8m。 监控室内电缆理直后从地槽或墙槽引入机架、控制台底部,再引到各设备处。所有电缆成捆绑扎,在电缆两端留适当余量。并标示明显的永久性标记。 1.2.2系统的调试 1)调试准备工作 检查本系统接线、电源、设备就位、接地、测试表格等。 用对线工具检查各种设备、器件之间线路连接正确性,并做好测试记录。 2)单体调试 检查摄像机开通、关断动作,云台操作和防护罩动作的正确性,检查画面分割器切换动作正确性。能够进行独立单项调试的设备、部件的调试、测试在设备安装前进行。如:摄像机的电气性能调试、配合镜头的调整、终端解码器的自检、云台转角限位的测定和调试、放大器的调试等。 开启主机系统,运行系统软件,打印系统运行时各种信息,确认总控室和各分控机房中央设备运行正常。各智能控制键盘操作正确。 3)系统调试 按调试设备的功能或作用和所在部位或区域划分。传输系统的每条线路都进行通、断、短路测试并做标记。遇到50Hz工频干扰,采用在传输线上输入“纵向扼流圈”来消除;当传输本身的质量原因与传输线两端相连的设备输入输出阻抗非75欧姆的传输线特性阻抗不匹配

施工方案及主要施工方法

施工方案及主要施工方法 1>外墙涂料施工方法 本工程中外墙建筑涂料涂装体系分为三层,即底漆、第一遍面 漆、第二遍面漆。其作用如下: 底漆:底漆封闭墙面碱性,提高面漆附着力,对面涂性能及表面效果有较大影响。如不使用底漆,漆膜附着力会有所削弱,墙面碱性对而漆性能的影响更大,尤其使用腻子的底面,可能造成漆膜粉化、泛黄、渗碱等问题,破坏面漆性能,影响漆膜的使用寿命。 第一遍面漆:第一遍面漆主要作用是提高附着力和遮盖力,增加丰满度,并相应减少面漆用量。 第二遍面漆:第二遍面漆是体系中最后涂层,具装饰功能,抗拒环境侵害。 2、外墙涂料施工工艺 修补T清扫T填补腻子、局部刮腻子T磨T—贴玻纤布T满刮腻子T磨-T—底漆施工T第一遍而漆施工f第二遍而漆施工

3、外墙涂料施工操作方法 a^修补 施涂前对于基体的缺棱掉角处、孔洞等缺陷采用仁3水泥砂浆 (或聚合物水泥砂浆)修补。下面为具体做法: 空鼓如为大面积(大于iocm2)空鼓,将空鼓部位全部铲除,清理干净,重新做基层,若为局部空鼓(小于wcm2),则用注射低粘度的环氧树脂进行修补。 缝隙一一细小裂缝采用腻子进行修补(修补时要求薄批而不宜厚刷),干后用砂纸打平;对于大的裂缝,可将裂缝部位凿成“V” 字形缝隙,清扫干净后做一层防水层,再嵌填仁2?5水泥砂浆,干后用水泥砂纸打磨平整。 孔洞——基层表面以下3mm以下的孔洞,采用聚合物水泥腻子进行找平,大于3mm的孔洞采用水泥砂浆进行修补待干后磨平。 此外对于新的水泥砂浆表面,如急需进行涂刷时,可采用15%-20% 浓度的硫酸锌或氧化锌溶液涂刷于水泥砂浆基层表而数次,待干燥后除去表面析出的粉末和浮砂即可进行涂刷。 b、清扫

工程项目建设方案

目录 一、项目概况 二、项目组织机构 三、项目建设程序办理计划 四、项目设计进度计划 五、项目招标进度计划 六、项目施工进度计划 七、项目资金使用计划 八、项目主要机电设备、装饰装修等材料采购计划 九、项目建设保证措施 一、项目概况 2010年4月12日,滨海新区建交局给建投集团下发津滨建交计[2010]3号“关于开展滨海文化商务中心前期工作的通知”,将滨海新区行政中心的项目暂定名为“滨海文化商务中心”。 1、项目位置和用地面积 滨海文化商务中心位于中央大道以东、大连东道以南、于家堡安居房以西、紫云中学以北,总用地面积约为30公顷。

2、主要建设内容和规模 滨海文化商务中心按照统一规划,分期建设的原则。本项目一期 总建筑面积约为47万平方米,其中地上建筑面积约为29万平方米、地下建筑面积约为18万平方米,由7座建筑和地下车库组成;它们为:商务主楼、培训中心、服务中心、接待中心、会议中心、商务辅楼、公寓。各建筑具体功能和建筑面积如下: 商务主楼(9) 为滨海新区区委、区政府、区人大区政协四套领导班子的办公场所,建筑位于基地北部,座北朝南布置成双“一”字形布局,用连廊相连接,各套班子办公区域分布明确又相互联系,均取得良好朝向,地上建筑面积6.78万平方米,宽度约172米,建筑层数最高9层,立面处理简洁大气,现代明快,该幢建筑为商务中心内最主要的建筑,外檐处理以浅色石材为主要装饰面,运用柱廊,檐口等细部的构造处理,以突出历久弥新,庄重典雅的建筑性格。 辅助办公楼(4层)

是辅助商务主楼的会议、办公场所,建筑位于行政办公楼的南侧,建筑面积2.87万平方米,建筑层数为四层。 服务中心(3层) 为滨海新区企业和市民提供工作和生活一站式服务的场所,一、二层设有开放式业务大厅,三层设有接待、办公、会议等项设施,建筑位于行政办公楼的西侧,主入口设置于南侧,方便前来办理业务的企业和市民。建筑面积为3.36万平方米,建筑层数为三层。 职工食堂(3层) 为商务中心提供接待,用餐的场所,设有多类大、小餐厅及接待服务设施,建筑位于行政办公楼的南侧,建筑面积3.09 万平方米,分三层设置。 会议中心(2层) 为大型行政会议场所,建筑位于行政办公楼东侧,建筑面积2.25万平方米,层数为两层,一层设置700人的会议厅和若干个大小会议室,二层为1200人,大会议厅并设200座席的主席台及服务于会议的其它设施。 商务辅楼(6层) 商务辅楼位于基地东侧,分三幢建筑,建筑面积8.2万平方米。主要功能为各委办局办公、会议、接待用地。 公寓2栋(10层、15层) 总建筑面积为6万平米,主要为办公人员住宿用。 地下车库 区域内及周边提供停车场所,车库面积为10.4万平米。 二、建设标准 (一)结构设计 本工程属重点设防类(乙类)建筑,按本地区抗震设防烈度7度设计基本加速度0.15g进行抗震设计,按高于本地区设防烈度即8

房屋建筑项目工程钢木模板工程施工方案[优秀工程方案]

模板工程施工方案 工程名称:唐山市东港龙城住宅小区 4号地3号楼、8号楼、9号楼工 程 编制人: 职务(职称): 审批人: 职务(职称): 总监: 职务(职称): 施工单位:唐山诚达建设集团有限公司

一、工程概况 本工程位于唐山市东出口、新华东道南侧,由唐山市妇兴房地产开发有限公司筹建,唐山诚达建设集团有限公司承建.要求2011年月日开工,2012年月竣工交付使用.该工程由北京东方华脉工程设计有限公司设计,唐山市工程建设监理公司全程监理. 模板施工方案编制依据《建筑施工安全检查标准》(JGJ59-99)、《建筑施工扣件式钢管脚手架安全技术规范》(JGJ130-2001)《河北省〈建筑施工安全检查标准〉实施细则》等. 二、模板安装概况 本工程地下室部分使用钢木组合模板.支撑采用φ48mm钢管,钢管符合国家现行规范A3钢的标准,?方木用65*100mm支柱模,用钢管通长上下卡牢,既能保证不走模,又能保证柱轴线不位移,柱间距不大于600mm用短钢管卡牢.梁板支撑用满堂φ48mm钢管,梁底模用木模,侧模用小钢模,为保证梁柱断面尺寸,梁柱内设直径 6.5mm钢筋,两端焊铁板打孔拉杆,梁底模起拱高度0.3%. 三、模板安装前的准备工作 1、模板安装前由项目技术负责人向作业班组长做书面安全技术交底,再由作业班组长向操作人员进行安全技术交底和安全教育,有关施工及操作人员应熟悉施工图及模板工程的施工设计. 2、施工现场设可靠的能满足模板安装和检查需用的测量控制点. 3、现场使用的模板及配件应按规格和数量逐项清点和检查,?未经修复的部件不得使用. 4、钢模板安装前应涂刷脱膜剂. 5、梁和楼板模板的支柱支设在土壤地面时,应将地面事先整平夯实,?并准备柱底垫板. 6、竖向模板的安装底面应平整坚实,并采取可靠的定位措施,?竖向模板应按施工设计要求预埋支承锚固件. 四、模板安装安全技术措施 1、模板的安装必须按模板的施工设计进行,严禁任意变动. 2、配件必须装插牢固,支柱和斜撑下的支承面应平整垫实,?并有足够的受力面积,支撑件应着力于外钢楞,予埋件与预留孔洞必须位置准确,安设牢固.基础模板必须支拉牢固,防止变形,侧模斜撑的底部应加设垫木.墙和柱子模板的底面应找平,下端应与事先做好的定位基准靠紧垫平,在墙、柱上继续安装模板时,模板应有可靠的支撑点,其平直度应进行校正. 3、下层楼板结构的强度,当达到能承受上层模板,?支撑和新浇砼的重量时,方可进行,否则下层楼板结构的支撑系统不能拆除,同时上下支柱应在同一垂直线上. 4、模板及其支撑系统在安装过程中,必须设置临时固定设施,严防倾覆,支柱全部安装完毕后,应及时沿横向和纵向加设水平撑和垂直剪刀撑,并与支柱固定牢靠,当支柱高度小于4米时,水平撑应设上下两道,两道水平撑之间,在纵、?横向加设剪刀撑,然后支柱每增高2米再增加一道水平撑,水平撑之间还需增加剪刀撑一道,支撑杆接长使用时,接头不能超过两个,且应采用辅助支柱来保证接头的承力和稳定. 5、模板安装必须按模板的施工设计进度,严禁任意变动. 6、下层楼板结构的强度,当达到能承受上层模板、支撑和新浇砼的重量时方可进行,否则下层楼板结构的支撑系统不能拆除,同时上下支柱必须在同一垂直线上. 7、模板及其支撑系统在安装过程中,必须设置临时固定设施,严防倾覆. 8、支柱全部安装完毕后,应及时沿横向和纵向加设水平撑和垂直剪刀撑,并与支柱固定牢

某安防监控实施计划方案

第一章编制依据 1.1施工组织设计的指导思想 本施工组织设计是按现行的国家施工验收规程规范、工程质量评定标准、施工操作规程、成都市政府的有关规定,再结合我公司的施工能力、技术准备力量及多年视频监控系统工程的设计施工经验和本工程的具体情况进行编制的。 施工组织设计作为直接指导施工的依据,在保证工程质量、工期、安全生产、成本的前提下,对加强施工管理、有效的调配劳动力、提高施工效率、节约工程成本、保证施工现场的安全文明有积极作用。 1.2编制范围及内容 1、本工程施工组织设计是严格按照本视频监控系统工程的要求进行质量策划后编制的,在人员、机械、材料供应、平衡调配、施工方案、质量要求、进度安排等方面统一进行部署下完成。 2、XXX公司高度重视本施工组织设计的编制工作,召集曾从事过类似工程工作的技术专家、有关负责人攻克本工程的重点、难点及特殊部位的施工技术,力求本方案重点突出,具有呼应性、针对性和可操作性。 3、本着对建设单位负责和资金的合理使用、对工程质量的高度责任感,针对本工程设计特点和使用功能要求,我们编制的原则是:“确保工程质量优、速度快、造价低、操作性强”。同时保证周

边和施工现场有良好环境。 1.3施工组织设计编制技术依据 建筑工程施工质量验收统一标准GB50300-2013 智能建筑设计标准GB50314-2015 智能建筑工程质量验收规范GB50339-2013 建筑电气安装工程施工质量验收规范GB50303-2011 视频安防监控系统工程设计规范GB50395-2007 安全防范工程技术规范GB50384-2004 防盗报警控制器材通用技术条件GB12663-2001 钢管敷设工艺标准305-1998 金属线槽配线安装工艺标准313-1998 防雷及接地安装施工工艺标准HFWXQB1-6-013-2004 甲方相关要求 招标文件有关内容 第二章工程概况 2.1工程内容 监控系统建设 2.2工期要求

完整的建筑工程临时设施施工方案

目录 第一章工程概况................................ 错误!未定义书签。第二章临时设施设置............................ 错误!未定义书签。第三章施工现场临时设施构成.................... 错误!未定义书签。 一、施工用房 ................................. 错误!未定义书签。 二、施工运输设施.............................. 错误!未定义书签。 三、施工供水设施.............................. 错误!未定义书签。 四、工地临时围墙.............................. 错误!未定义书签。 五、施工供电设施.............................. 错误!未定义书签。 六、通迅设施 ................................. 错误!未定义书签。 七、施工安全、文明设施........................ 错误!未定义书签。

XXXXXX工程 施工临时设施施工方案 第一章工程概况 工程名称:XXXXXXXX 建设地点:XXXXXXXX 建设单位:XXXXXXX 勘察单位:XXXXXXX 设计单位:XXXXXXX 监理单位:XXXXXXX 质监单位:XXXXXXX 施工单位:XXXXXXX 项目经理:XXXXXXX 建筑类型:XXXXXXX总建筑面积万平方米,是集商业、办公、住宅、地下停车为一体的多功能的智能型建筑,局部地下1层,地上层数为25层。工程结构形式为沿街商业框架结构2层至4层,高层住宅框剪结构25层,建筑最高高度为米。建筑耐火等级为二级,抗震设防烈度为7度。 第二章临时设施设置 1、结合施工现场具体情况,统筹安排,进行科学合理的布置; 2、结合本工程施工场地的平面布置,办公、生活区尽量避开施工区,施工区加工场地结合业主报建需要及建筑物的结构位置及建筑形状,减少材料的二次转运; 3、以经济适用为原则,合理地选择临时设施的形式; 4、符合安全文明施工和现场防火要求,同时起到美化环境的作用。 5、施工区与生活、办公区严格隔离,各区之间采用围墙隔离。办公区设置在场地的北

商场建筑工程主要项目施工方案

编号: 建筑工程 主要项目施工方案 编制人:职务(称): 审核人:职务(称): 批准人:职务(称): 批准部门(章): XX建设集团股份有限公司 20XX年X月X日

第一节、流水段划分 流水段划分既要考虑现浇砼工程的模板配置数量、周转次数及每日砼的浇筑量,也要考虑流水段材料和工程量的均衡程度和塔式起重机每台班的效率,具体流水段划分规划如下: 一、底板按后浇带的分划分为四个流水段。 二、地下室结构横向分为四个流水段,筒体为一单独流水段,穿插在横向流水施工中,不占用工期。 三、主体结构竖向分为三个流水段,筒体为一单独施工段,穿插在竖向流水段中,不占用工期。地下室、首层至四层及地上筒体段结构施工,先施工筒体及柱分项,后施工梁板分项。 第二节、测量放线 一、根据图纸及现场实际情况,对各流水段进行网状控制,兼顾+0.000以上施工,测试控制轴线2轴、3轴、9轴、15轴、19轴、B轴、E轴、J轴、M轴;根据测绘院提供水准点向施工现场内引高程控制点,距离基坑至少15m。控制点放样采用方向交汇法,按照导线施测,所有控制点设专人保护,且每月复核一次,使用前必须进行校核。 二、采用电子经纬仪,用采用方向交汇法投测各轴线的两端点测设轴线。 三、钢尺量距时要求采用标准拉力50N,季节复检时,根据气温情况进行温度校正。对悬空和倾斜测量,应在满足限差要求的情况下视具体情况考虑垂直及倾斜改正。要求每层轴线距离用引测轴线法进行校对。 四、标高抄测采用S2水准仪,视距差控制在20mm内,均以控制水准点作后视,并作往返闭合。 五、楼梯间放线扣除面层部分,放出详细平面、标高及砼面层控制线;以控制轴线及上下贯通线控制垂直偏差,外墙立面窗口两侧控制线从上到下弹通线,逐层上引控制。 六、所有测量仪器及工具定期由区以上技术监督局鉴定,合格后方可使用。 七、沉降观测:(由建设单位直接委托有资质单位)沉降观测点按施工图设

模板工程施工方案

目录 1.编制依据: (1) 2.工程概况: (1) 3.施工安排: (2) 4.施工准备: (3) 5 .主要施工方法及措施: (3) 6.质量要求: (10) 7.安全注意事项: (12) 8.一般要求: (12) 9.模板计算: (13)

1.编制依据: 1.1施工图纸 珠海立航磁电科技有限公司厂区工程结构、建筑施工图 1.2国家规范 《混凝土结构工程施工质量验收规范》(GB50204-2015) 《建筑工程施工质量验收统一标准》(GBJ50300-2013) 1.3行业标准 《建筑施工安全检查评分标准》(JGJ 59-2011) 《建筑施工高处作业安全技术规程》(JGJ80-2016) 《建筑施工扣件式钢管脚手架安全技术规范》(JGJ130-2011) 《建筑施工碗扣式钢管脚手架安全技术规范》(JGJ166-2016) 2.工程概况: 2.1工程概况: 珠海立航磁电科技有限公司厂区工程位于珠海市斗门区富山工业园,总建筑面积20746平方,框架结构,主要建筑物为加工车间、精细车间、餐厅宿舍综合楼、门卫、泵房及水池,其中加工车间为5层,建筑面积5980.2平方,高度23.4米,加工车间为5层,建筑面积5980.2平方,高度23.4米,餐厅宿舍缩合楼为6层,建筑面积1951.5平方,高度20.85米. 精细车间首层高6.3m,梁的跨度为7.5m,梁宽0.3m,梁最大高度0.8m. 建设单位:珠海立航磁电科技有限公司 设计单位:长宇(珠海)国际建筑设计有限公司 勘察单位:核工业赣州工程勘察院 施工单位:广东电白二建集团有限公司 监理单位:广东省广大工程顾问有限公司 2.2现场情况: 基础、梁、柱、顶板等均使用15mm厚多层板进行组配。

小区监控系统施工方案范本

小区监控系统施工 方案

小区监控系统新建、改造施工方案 皇鹏物业有限责任公司 6月30日

小区监控系统方案 皇鹏公司现管理住宅小区(东玉龙小区、星辉中路小区)的监控系统由于使用时间较长,有的设备和线路已经老化失效,需要更新相关设备及进行线路改造;有的地方存在监控死角,如车辆发生擦挂、盗窃后不能及时取证,容易给公司带来不必要纠纷和损失,需要增加监控摄像头;另外,为加强新华苑的安全管理,提高安全防范水平,拟给新华苑新建小区高清监控系统一套。 现在将各小区的改造、新建方案分别介绍如下: 一、东玉龙小区增加摄像头: 1.小区监控系统现状:东玉龙小区大门及停车场、办公大楼 各楼层现在一共建有25个模拟摄像头,2台16路海康威 视(Hikvision)普通硬盘录像机,机房设在大楼值班室 内。 2.增加摄像头目的:现在小区停车场有2个监控盲区,需要 分别增加2个摄像头,以消除监控死角;办公大楼2楼平 台新增加2个监控摄像头,以加强办公大楼的安防监控。 3.拟采用的设备及施工方案: 采用海康威视(HIKVISION) DS-2CD1203D-I3 720P监控 摄像头,由于原有海康硬盘录像机接口有富余,摄像头视 频信号直接接入原硬盘录像机,省去购买硬盘录像机费

用。增加的2个摄像头距离机房大约400米(布线距离),施工时间、材料规格及数量、价格等见小区监控设备及人工费预算表。 二、星辉中路小区监控设备老化更新: 1.小区现状:星辉中路小区现共有8个摄像监控头,1台16 路海康威视(Hikvision)普通硬盘录像机,机房设在值 班室内。由于小区监控系统安装时间较长,部分设备老化 严重,监控画面不清晰,达不到防范的目的。 2.拟采取的措施:本作节约公司开资,降低不必要的支出, 又能满足小区安防要求为原则,拟对该小区老化失效的摄 像头进行更新(6个),对视频线路进行梳理检查,对锈 蚀的线材、接头给予更换。保证小区的监控系统处在正常 的工作状态。 4.更换的设备:采用海康威视(HIKVISION) DS-2CD1203D- I3 720P监控摄像头,施工时间、材料规格及数量、价格等见小区监控设备及人工费预算表。 三、新华苑小区新建高清监控系统: 1.小区现状:新华苑小区原来的安防系统采用的是红外 对射报警系统,由于安装的时间长,设备老化严重已不能起到报警作用。该设备由于技术原因存在误报现象,比如墙上猫等动物爬过、树枝遮挡等都会引起该设备的误报。现在已经很少采用该系统方案。

主要项目施工方法与技术措施方案

主要项目施工方案 第一节、流水段划分 流水段划分既要考虑现浇砼工程的模板配置数量、周转次数及每日砼的浇筑量,也要考虑流水段材料和工程量的均衡程度和塔式起重机每台班的效率,具体流水段划分规划如下: 一、底板按后浇带的分划分为四个流水段。 二、地下室结构横向分为四个流水段,筒体为一单独流水段,穿插在横向流水施工中,不占用工期。 三、主体结构竖向分为三个流水段,筒体为一单独施工段,穿插在竖向流水段中,不占用工期。地下室、首层至四层及地上筒体段结构施工,先施工筒体及柱分项,后施工梁板分项。 第二节、测量放线 一、根据图纸及现场实际情况,对各流水段进行网状控制,兼顾+0.000以上施工,测试控制轴线2轴、3轴、9轴、15轴、19轴、B 轴、E轴、J轴、M轴;根据测绘院提供水准点向施工现场引高程控制点,距离基坑至少15m。控制点放样采用方向交汇法,按照导线施测,所有控制点设专人保护,且每月复核一次,使用前必须进行校核。 二、采用电子经纬仪,用采用方向交汇法投测各轴线的两端点测设轴线。 三、钢尺量距时要求采用标准拉力50N,季节复检时,根据气温情况进行温度校正。对悬空和倾斜测量,应在满足限差要求的情况下

视具体情况考虑垂直及倾斜改正。要求每层轴线距离用引测轴线法进行校对。 四、标高抄测采用S2水准仪,视距差控制在20mm,均以控制水准点作后视,并作往返闭合。 五、楼梯间放线扣除面层部分,放出详细平面、标高及砼面层控制线;以控制轴线及上下贯通线控制垂直偏差,外墙立面窗口两侧控制线从上到下弹通线,逐层上引控制。 六、所有测量仪器及工具定期由区以上技术监督局鉴定,合格后方可使用。 七、沉降观测:(由建设单位直接委托有资质单位)沉降观测点按施工图设计位置布置。当浇筑完底板砼,即在底板上埋设临时观测点,待观测点稳定后及时进行观测,地下室施工完后,将临时观测点移至+0.000时,按规定埋设永久性观测点,然后每施工一层,复测一次,直至竣工。工程竣工后,第一年观测四次,第二年观测二次,第三年观测一次,至下沉量不大于1mm/100d停止观测。 沉降观测点等级按三等,观测方法为二等水准测量。 (具体详见《施工测量方案》) 第三节、降水护坡工程 一、止水、降水工程 根据勘测报告,本工程现场地下水位在现有地面1.0米左右,基坑的开挖和基础的施工采取降水或止水措施,由于本工程北面五层民房距地下室外墙只有3米,东面、南面、西面地下室外墙都紧靠市政道路边,采取井点降水,可能引起周边构筑物的下沉开裂和倾斜,只能采用深层水泥搅拌桩止水幕帏,搅拌桩深10m、桩径¢500。

主要工程项目的施工方案,施工方法

主要工程项目的施工方案,施工方法 一、清除植被 1、工程开工前根据征地红线图,开挖水沟,标明征地界线,对进场施工人员进行现场测量交底,避免超过征地界施工。 2、在路基施工范围中的中心线桩及水准点引出机械施工活动区域以外,并设标志予以保护,对关键桩号做好控制点,便于破坏后及时恢复。 3、对施工现场的地下、地上、空中障碍物进行全面调查了解,根据施工进度制定出排除各种障碍的时间,积极配合业主作好拆迁、征地、排障等工作。 4、在路基界限范围内,采用人工砍伐树木,用D85推土机清除树根、杂草灌木丛、垃圾物等并归堆,用汽车将清除的表层非适用材料运走堆放在指点地点。 5、对于填方区,清除植被和表层土后,应用压路机将原地面碾压至规范和标书要求的密实度后方可回填。 二、路基土石方工程 2.1路基土方工程施工 1.施工方案 路基土方开挖、装运、填筑、平整、碾压均采用机械化施工。挖土运距在0~75m范围内,用推土机作业直接分层推运至填方路段。100~300m采用自行式铲运机及挖掘机挖装配置自卸汽车运输或采用大马力推土机推松拢堆,装载机装车自卸汽车运输的方案施工。 路基回填地段现场清理,视地质情况,采用推土机清挤淤泥,障碍物、草皮,或反铲挖土机清挖淤泥特殊局部地方采用人工。

土方回填整平采用推土机粗平,平地机精平,CA25光轮振动碾及50T拖式振动羊足碾压实。 2.土方工程施工工艺流程图见附图: 3.施工方法 (1)用全站测距仪,S3水准仪准确测量放线,打桩,插小红旗,挖沟标明施工边界线。 (2)用推土机、铲运机清理施工现场内的树根、草皮耕植表土,并将其表土清除堆放在指定线外地点,路堤填方地段内有积水、水塘及稻田地时,采用排水疏干处理方法,沿路基两侧纵向开挖排水沟,在低洼积水地带开挖横向排水沟,以利排干积水。采用推土机推挤或挖土机挖除淤泥,或采用抛填片石挤压淤泥。按设计要求回填土或选料回填处理。 地表为旱地或丘陵地时,清除表土后用压路机碾压原地面使其密实度达90%以上时,再进行回填土施工。 (3)路堑挖土方:对距填方区距离较近的,在50~80m以内的土方采用推土机直接分层推运至填方区,当运距在80~300m时,则采用铲运机自行铲运至填方区,当运距在300~1000m以上时,则采用挖土机,装载机装车,自卸汽车运输到填方区的施工方法进行施工。 推土机开挖作业采用:槽形推土法、多刀片送土法、并列推土法、下坡推土法四种方法施工。根据路段开挖深度,坡面陡缓程度灵活运用不同的推土方法。正反铲挖掘机作业开挖、当路堑深≥4m时应采用分层挖土法,或多层挖土法,路堑挖方路段纵向距离较长,一般≥200m时,可采用中心线开挖法,或半幅路线开挖法。反铲挖掘机装土方法:采用汽车在开挖面装土法与汽车与挖掘机在同工作面装土法相结合,根据地形特点灵活运用,为提高装土效率一

模板工程施工方案范本[1]

八、模板工程施工方案 1、编制依据 主要依据施工图纸、施工组织设计、规范和规程,具体见表1。 表1 模板编制的主要依据 2、工程概况 2.1设计概况表见表2 表2 设计概况表

2.2结构平面图 《地下三层结构平面图》,《标准层结构平面图》详见附图(1)、(2)。 3、施工安排 3.1施工部位及工期安排 根据施工进度计划,施工部位及工期安排见表3 表3 施工部位及工期安排 3.2劳动组织及职责分工 3.2.1管理人员组织及职责分工:见图1

3.2.2劳务分包队人员组织及职责分工:分图2 3.2.3工人分工及数量 根据施工进度计划及施工流水段划分进行劳动力安排,主要劳动力分工及数量:见表4 表4 劳动力准备一览表 4、施工准备 4.1技术准备 项目总工组织经理部技术、生产人员熟悉图纸,认真学习掌握施工图的内容、要求和特点,同时针对有关施工技术和图纸存在的疑点作好记录,通过会审,对图纸中存在的问题,与设计、甲方、监理共同协商解决,取得一致意见后。办理图纸会审记录,作为施工图的变更依据和施工操作依据。熟悉各部位截面尺寸、标高制定模板初步设计方案。 4.2机具准备 主要机具及工具准备详见表5 表5 机具及工具准备一览表

4.3材料准备 顶板、梁、地下部分墙体、主柱模板材料选用覆膜多层板,模板周转次数为6次,地上部分主楼核心筒材料选用大钢模板约1000m2,支撑采用碗扣架,脱模剂选用油性脱膜剂。根据所需材料提前考察、选用相关材料厂家。 5、主要施工方法及措施 5.1流水段划分 施工流水段界限尽量与结构自然界限(后浇带)相吻合,流水施工可以使工程有节奏、均衡、连接施工,流水段划分图详见附图(3)~(7),流水段名称与相应的轴线对应见表6。 表6 流水段名称与相应的轴线对应关系

监控系统实施方案模板

实施方案 1概述 工程实施方法是整个监控联网系统建设成败的关键,其目的不仅要提供一个符合现在需求的质量优良的系统,更应为未来的维护和升级提供最大的便利、尽量节约资金。 监控联网系统工程实施是一个综合性很强的工作,工程涉及到监控、网络、视频管理、多媒体技术、计算机信息等多项专业知识,因此其核心是行之有效的管理。我公司作为监控联网系统工程设计和项目管理商的施工单位经过几年来实际工程的磨练,锻炼了一批比较成熟的技术工程师和项目经理和安装工程师,不断探索工程实施的模式,努力将由本公司自己设计、自己工程安装的身体力行的工程模式转变为不断加强自身技术实力、质量保证体系和向外输出项目管理模式的头脑智慧型的模式,以控制项目成本、灵活组合针对不同类型工程项目队伍,适应规模发展,极大提高了承接大型项目的能力。 2工程现场管理 在施工过程中,除了要求施工和技术具备一定水准以符合规范以外,其中也涉及其他专业的管理内容,工程的施工管理之所以必不可少,关键在于它的协调和组织的作用,我公司将会采取有效的措施在以下几个方面切实作好施工管理工作: 1.施工的进度管理 2.施工的界面管理 3.施工的组织管理 3工程技术管理 工程的技术管理贯穿整个工程施工的全过程,我公司将派出富有经验的一流专业技术工程师参加工程的技术督导。执行和贯彻国家、行业的技术标准及规范,严格按照监控系统工程设计的要求施工。在提供设备、线材规格、安装要求、调试工艺、验收标准等一系列方面进行技术监督和行之有效的管理,其管理内容重申如下: 1.技术标准和规范的管理

2.安装工艺管理 3.技术文件管理 4工程质量管理 工程质量管理是我公司各项工地工作的综合反映,我司将会在实际施工中作好以下几个质量环节,确实作好质量控制、质量检验和质量评定: 1.施工图的规范化和制图的质量标准 2.系统软件的安装使用质量标准 3.管,槽施工质量管理 4.线缆铺设的质量要求和监督 5.工作区,管理区设备安装的质量要求和监督 6.网络系统现场测试 7.竣工资料制作 8.系统初验,试运行与总结 5安全生产和文明施工 5.1安全防范重点 ●2米以上的高处坠落事故; ●触电事故; ●物体打击事故; ●设备机具伤害事故。 ●控制点的管理 ●制度健全无漏洞;检查无差错; ●设备无故障; ●人员无违章。 5.2安全保障措施 1、施工现场工作人员必须严格按照安全生产、文明施工的要求,积极推行施工现场的标准化管理,按施工组织设计,科学组织施工。 2、按照施工总平面图设置临时设施,严禁侵占场内道路及安全防护等设施。 3、施工现场全体人员必须严格执行《建筑安装工程安全技术规程》和《建筑安装工人安全技术操作规程》。

土建工程主要施工方案

土建工程主要施工方案 第一节施工测量控制 本工程将作为我公司的重点工程,施工测量控制工作由测量专业的工程师负责主持。 在本工程施工测量放线之前,除了检查好所有使用的测量仪器及工具外,还将做好以下准备工作。 1.熟悉和核对设计图中的各部位尺寸关系; 2.制定各细部的放样方案; 3.准备好放样数据。 一、了解施工部署、制定测量放线方案 从施工流水的划分、开工次序、进度安排和施工现场暂时工程布置情况等方面,了解测量放线的先后次序、时间要求以及测量放线人员的安排。 根据现场施工总平面与各方面的协调。选好点位,防止事后相互干扰,以保证控制网中主要点位能长期稳定地保留。根据设计要求和施工部署,制定切实可靠的测量放线方案。根据场地情况、设计与施工的要求,按照便于控制全面又能长期保留的原则,测设场地平面控制网与标高控制网。 各分项工程在测量放线后,应由测量工程师及专职质检员验线以保证精度、防止错误。 二、主轴线的控制 根据本工程的实际情况,建立一个方格网。在建立方格网的过程

中,点位布置要考虑便于方格网测量和施工定线需要,布设在建筑周围、次要通道或空隙处,这样能长期保存。 在标桩的顶端安装一块10×10厘米的钢板,钢板下面焊有锚固钩,然后将其埋固于桩身混凝土之中。标板上最后标定点位时,在钢板上钻一个直径为1-2毫米的小孔,通过中心区一个十字线。小孔周围用红漆画一圆圈,使点位醒目。施工中,在标桩四周打入保护桩,在上面围绕铁丝,对测量标桩加以保护,防止受毁坏。 三、主轴线的竖向传递 本工程竖向轴线的引测,主要是各层放线和结构竖向控制的依据,其中,以建筑物轮廓轴线和控制电梯井轴线的投测更为重要。施工中对竖向偏差的要求高,为了满足测量精度的要求,进行轴线的竖向投测。在标桩顶安置激光基点,用200×200×10毫米的钢板焊接锚固钩,设置到预定位置,用经纬仪投测各级轴线,定出如图所示激光基准点。在钢板上凿刻一小圆心即为激光控制点。在施工控制中,将铅垂仪架在这些激光基准点上对中、整平。在板面预留的激光洞孔盖上一块接收靶,然后使激光器起辉放光,光斑显示在接收靶上。为了保证激光控制点的准确性,在每次施测之前必须检查铅垂仪,使其激光点和十字丝中心点重合。另外为了消除竖轴不垂直水平轴的误差,需绕竖轴转动照准部,让水平度盘分别在0度、90度、180度、270度四个位置上,观察光斑变动位置,并作标注,若有变动,其变动的位置成十字的对称型,对称连线的交点即为精确的铅垂中点。重复此方法投出其余的激光点。检查无误后可弹墨线,作为放线依据。

建筑工程主要项目施工方案

建筑工程主要项目施工方案 1地下室及基础工程 土方地基工程施工前,组织施工班组熟悉有关的工程技术资料的设计图纸,包括地形测量图,工程地址勘察报告,文物考古钻探资料、地下管线、水文、气象资料和本工程的施工图纸。 工程开工前组织图纸会审、编制施工组织设计和施工总平面图,合理选择施工方案,尽量采用新技术和机械化施工,按合同要求安装施工进度,在施工准备工作全部就绪并经工程师批准后开工。 施工前,做好工程控制测量和建筑物的定位放线工作台,对轴线定位站和水准点重点保护。 为节约大型机械施工费用,全部基础工程(土方、砌筑、钢筋、混凝土)除砂浆、混凝土采用机械搅拌和水平运输采用小翻斗车外,其余均由人工施工。因基础深度大于1.5m,挖土时应按规定的1:0.33放坡,挖土时必须在四周圈起钢管护身栏,高度1.2m,四角设警告牌,夜间设红色路灯。坑边堆土或其他材料距坑边不小于1m。在坑内施工的所有人员必须戴安全帽。基坑填土前,应先清理坑内杂物,每层虚铺厚度20cm,采用蛙式打夯机夯实,每层填土隔40m取样做干密度试验,其值不得低于1.658/cm3。 地下室砌体及基础砼施工前,工程所用材料配比材料、及施工机械的安装就位工作应已完成并调试合格。 基础砼浇筑前,先进行验坑,轴线、标高、基坑尺寸符合图纸规定,坑内浮土、积水、淤泥清除干净后方可施工。 地下室墙的防潮层按图要求用1:2水泥砂浆加水泥用量3%的防水粉,厚度为20mm。 对隐蔽工程应进行中间验收,经检查合格后,方可进行下一道工序的施工。

由基础工程在晚冬季节施工,必须采取相应的防冻措施以保证质量。基础工程施工完毕后经质检部门、监理方、甲方验收合格后立即进行土方回填。 雨期施工时,采取有效措施,保证工程进度、质量和安全。 雨期到来前,对施工现场的排水系统进行检查,必要时增加排水设施,保证流水畅通。 冬期施工时,制订冬期施工措施,保证工程的进度、质量和安全。 冬期施工时,填方每层铺土厚度比常温施工时减少20-25%予留沉降量应常温施工时适当增加。 冬期进行填方施工时,应清除基底上的冰雪或保温材料。地面面层的填方中不得含有冻土块。填土完成后到地面施工前应采取防冻措施。 2砌砖工程 (1)结构工程以瓦工为主,木工及混凝土工按工作量配备力量。每层砌砖为两步架,两个施工层,每层平均砌砖配备瓦工15人(另加普工8人)。 (2)结构工程主要施工顺序为:放线立皮数杆→绑构造柱钢筋→一步架砌砖→支构造柱模板、浇筑混凝土→二步架砌砖→支构造柱模板、浇筑混凝土→安装过梁→绑圈梁钢筋、支模板→安装楼板→板缝支模、支现浇板模板、整理钢筋→浇筑圈梁、板缝、现浇板混凝土。 (3)结构砌砖采用满丁满条法。首层要作好排砖撂底,前后檐第一层排条砖,山墙第一层排丁砖,门窗旁加七分头,两边对称一致,以防止产生阴阳膀。外墙大角要同时砌筑,内外墙接槎每步架留斜槎到顶。砌筑时控制灰缝厚度,不得超越皮数杆灰缝高度。240mm、370mm墙均采用双面挂线。 (4)砌砖使用平台架子(里脚手),建筑物外设脚手架,随楼层升高,作挂安全网、勾缝、外檐装修用。砖用砖笼吊运,灰浆使用吊斗直接投入桶内。 (5)砖墙与构造柱交接处留三进三出直槎,进出要标准整齐,以保证构造柱断面尺寸。门窗洞口使用标准顶杆,控制墙面平整及洞口尺寸。圈梁下用硬

监控工程施工方案范本

建筑工地施工现场 电视监控设计方案 方 案 介 绍 目录 一、序言 3 二、统功能及组成 3 2.1 系统组成 3 2.2、系统功能说明 4 2.3监控安装位置范围示意表 4 三、系统结构示意图及器材报价 4 四、质量保证和售后服务 5 一、序言

随着社会经济的不断进步、发展,人们对安全生产的要求以越来越高。如何才能安全、高效的生产、生活,以越来越受到各行各业的关注,电视监控系统作为有效的防护措施已越来越受到各行各业的重视。其作为一种科学的、先进的管理系统以越来越受到人们的欢迎。 在建筑行业中,施工人员的人身安全,工地的建筑材料、设备等财产的保全尤为重要。但是,由于施工环境的限制,设备、材料的安全管理不完善及部分员工的自我防护意识的薄弱,为犯罪分子提供了可乘之机。为了建筑工地安全管理进一步完善,我们为此特为您做此方案。 二、统功能及组成 2.1 系统组成 系统由前端图像信号采集、图像信号及控制信号中间传输、中心图像切换控制三部分组成。结构示意图如下; 2.2、系统功能说明 1.施工现场重点监控部位分别架设4台带全方位云台、室外防护罩及带自动光圈镜头一体化摄像机,通过监控中心键盘、鼠标操作,可实现云台的上下、左右,镜头的远近、自动长短焦,光圈大小操作,实现对施工现场及人员的全方位监视需要。 2.硬盘录象可实现对画面的任意切换、定时切换、顺序切换及对前端设备的控制。

3.监控中心设数字硬盘录像机一台,实现长时间录象监控图像的需要。 2.3监控安装位置范围示意表 摄象机安装位置摄象机监控范围备注A B C D 三、系统结构示意图及器材报价 设计方案一 方案一设备器材造价明细表:

建筑工程施工方案范本

目录 第一章编制说明 (1) 第二章编制依据 (2) 第三章编制内容 (3) 第四章工程概况 (4) 第一节工程特点 (4) 第二节建设场区工程地质条件 (5) 第三节建设地区特征 (5) 第四节土建施工项目 (5) 第五节建设项目概况 (6) 第五章施工组织措施 (7) 第一节施工组织管理机构的建立 (7) 第二节施工组织机构的启动和高效运作 (7) 第三节工程质量保证体系 (8) 第四节安全保证体系 (8) 第六章施工进度计划安排 (9) 第一节施工总工期 (9) 第二节施工流水段划分 (9) 第三节构筑物土建主要施工顺序 (9) 第四节污水工程施工进度计划表 (9) 第七章施工总平面 (11) 第一节总体布置 (11) 第二节施工道路 (12)

第三节施工排水 (12) 第四节施工用电 (12) 第五节施工用水 (13) 第八章施工部署 (14) 第一节施工指导方针 (14) 第二节施工管理目标 (14) 第三节施工准备 (14) 第四节施工顺序安排 (15) 第五节施工劳动力的配备 (16) 第六节主要施工机械设备的配备 (16) 第七节主要施工材料及周转材料计划 (17) 第九章主要构筑物的施工方案 (18) 第一节构筑物轴线、标高控制 (18) 第二节圆型池放线措施 (18) 第三节施工降水 (19) 第四节氧化沟池体施工 (19) 第五节二沉池池体施工 (25) 第六节回流污泥泵池和沉渣井池体施工 (26) 第七节装饰工程 (26) 第八节防水工程 (27) 第九节其他附属工程施工 (28) 第十节脚手架工程 (28) 第十章施工技术措施 (30)

监控施工方案范本

四、技术标准及质量保证 (1)布线标准:乙方监控系统布线施工,严格遵照国际《民用闭路监控电视系统技术规范》GB50198-94。 (2)乙方所供设备均以生产厂家提供的产品技术资料为技术标准。 (3)乙方保证本项目所供产品均为合同中指定的产品,且包装为原包装。产品进场时提供供货证明,经甲方验收后进行施工。 (4)乙方对监控布线、设备质保见附件1(工程价格汇总表质保说明) 五、工程项目建设期限: 合同签定后5日内进场施工,整个施工工期XX天。(XX年XX月XX日开工,XX年XX 月XX日以前乙方按设计要求完成设备安装调试。并能投入正常使用。) 方案二:变电站图像监控系统施工方案 一、工程概况 本次工程是变电站田新装图像监控工程。 本次工程摄像机安装位置是:变电站 主控制室部分:布置4台枪击 室外消防水库及变电设施部分:布置2台球机看场地 变电站内部分:布置4台球机看场地及2枪击台看大门,通道室外住宿及停车场:布置1台球机看停车场及1台枪击看住宿区 变电站四周围墙安装8防区。 二、组织措施 1、本工程总负责人:XXXX 2、现场施工负责人:XXX

3、安全员:XXX 4、工作班组人员:XXXX 三、施工方法及工艺要求 1.电缆、网线、电源、视频电缆、控制电缆敷设 电缆沟、电缆管道应先进行路线勘察,确保顺利敷设电缆。敷设前,应检查电缆有无机械损伤,电缆芯线间及芯线与屏蔽层绝缘是否合格,电缆盘是否完好。电缆的弯曲半径应符合施工规范的要求。电缆应使用整条电缆。电缆在电缆沟内应排放整齐并固定。电缆的防火在电缆沟内采用防火包及防火堵料,进入屏柜处采用防火隔板及堵料。 2.电缆接头制作及核对 电缆接头的制作应统一施工工艺,做到整齐美观。电缆在屏柜内排列整齐,层次清楚;电缆牌标识清楚,有电缆规格、起点、终点及电缆标号。电源电缆在设备通电前应使用万用表测量每芯对地电压。电缆在敷设完毕后应使用无码测试仪对通道环回测试确认无误。网线在敷设完毕后应使用网络测试仪测试接头是否接触良好。 在视频监控屏安装工控主机,在配线架安装协议转换器。严格按图接线,屏柜箱上各电器元件的标号应清晰,电缆芯号牌采用塑料标号。 四、安全技术措施 1.在交流电源电缆接入图像监控屏及通信直流屏的两侧电源端子后,应用万用表测试接入两侧电缆芯火线、零线及地线是否对应以及两侧电缆芯间有无短路。在交流电源电缆接入图像监控屏及通信直流屏的两侧电源端子前,须断开交流空气开关,用绝缘胶布封闭空气开关,严禁空气开关合闸。 2.在工控主机电源线接入前,应用万用表测量交流火线、零线及地线对地电压,确认无电,并断开硬盘录像机电源空气开关